Vernon LA Campus (with Goodman Group)

Vernon, Los Angeles County, California · All 30 DataBank sites

Under constructionNo reception on recordRecord updated October 19, 2026

Vernon LA Campus (with Goodman Group) is a data center under construction in Vernon, California (Los Angeles County), operated by DataBank. The public record puts it at announced April 7, 2026, 32 MW planned, 5.6 acres.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Under construction

Operator
DataBank
Facility type
Data center
Location
3094 East Vernon Avenue, Vernon, Los Angeles County, CA, 90058
Coordinates
34.0054, -118.2187 (approximate)
Power capacity
32 MW planned
Land
5.6 acres
Investment
Not established from a public source
Announced
April 7, 2026
Utility
City of Vernon Public Utilities Department
Power source
Grid
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
No reception on record
Source confidence
Confirmed by multiple independent sources or official documentation

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. September 14, 2026
    Under construction
    Goodman broke ground on the three-story building at 3094 E Vernon Avenue in March 2025 and topped out the shell in September 2025; the first 6 MW is scheduled for December 2026 with the remaining 26 MW staged through September 2027, so the site is past the proposed stage recorded on the line. Source: Hoodline
  2. 2026
    Proposed
    Opening Dec 2026, phased through Sept 2027. Source: PR Newswire

Opposition and litigation at this site

Nothing on record as of October 19, 2026. No lawsuit, organized opposition, or contested hearing over Vernon LA Campus (with Goodman Group) in Vernon, Los Angeles County, California appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.

A new status, a permit, a reception finding, or a lawsuit. Nothing else, ever.

Power and water

Goodman LAX01 Vernon is 49.5 MW total, about 32 MW critical IT when fully fitted out

Notes on the record

Joint venture with Goodman Group; opening December 2026, phased through September 2027.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • How the community has received it
Which document closes each gap
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
How the community has received it
Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Tell us about your situation

Living near Vernon LA Campus (with Goodman Group)?

Tell us the basics. Where a participating attorney in your state is available, we may share your information with them with your consent. Free, no obligation, and no guarantee anyone will contact you.

Questions people ask about this site

Is there opposition to the Vernon LA Campus (with Goodman Group) in Vernon?

Nothing on record as of October 19, 2026. No lawsuit, organized opposition, or contested hearing over Vernon LA Campus (with Goodman Group) in Vernon, Los Angeles County, California appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

Has anyone filed a lawsuit over the Vernon LA Campus (with Goodman Group)?

No lawsuit over Vernon LA Campus (with Goodman Group) appears in the record we track as of October 19, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Vernon LA Campus (with Goodman Group) use?

No water withdrawal figure for Vernon LA Campus (with Goodman Group) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Vernon LA Campus (with Goodman Group), and how big is it?

DataBank is the operator on record. We hold 30 sites for that company across the registry. Capacity on record is 32 MW. The site is recorded at 5.6 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Vernon LA Campus (with Goodman Group)," updated October 19, 2026, https://suedatacenters.org/data-centers/databank-vernon-la-ca.

Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/databank-vernon-la-ca, retrieved October 29, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.DataBank and Goodman Group partner to open new landmark data center in Los Angeles · PR Newswire · retrieved September 29, 2026 · original offline, archived copy from October 1, 2026
  2. 2.DataBank press release, DataBank and Goodman Group Partner to Open New Landmark Data Center in Los Angeles · retrieved July 25, 2026
  3. 3.Los Angeles Vernon Data Center (LAX2), 3094 E. Vernon Avenue · DataBank · retrieved September 14, 2026
  4. 4.DataBank, Goodman launch 32MW data center project in Vernon · Hoodline · retrieved October 19, 2026
  5. 5.Goodman breaks ground on 49.5 MW data center in Vernon · Connect CRE · retrieved October 19, 2026

Is a data center disrupting your home?

Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.

  • Tell us about your situation
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us