Data Center Registry
Prime Data Centers LAX01
Vernon, Los Angeles County, California · All 6 Prime Data Centers sites
Prime Data Centers LAX01 is an operating data center in Vernon, California (Los Angeles County), operated by Prime Data Centers. The public record puts it at 33 MW operating.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Operating
- Operator
- Prime Data Centers
- Facility type
- Data center, AI use confirmed
- Location
- 4701 South Santa Fe Avenue, Vernon, Los Angeles County, CA, 90058
- Coordinates
- 34.0014, -118.2303 (approximate)
- Power capacity
- 33 MW operating
- Land
- Not established from a public source
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Vernon Public Utilities
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Reported by at least one credible outlet or filing
Opposition and litigation at this site
Nothing on record as of August 2, 2026. No lawsuit, organized opposition, or contested hearing over Prime Data Centers LAX01 in Vernon, Los Angeles County, California appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Notes on the record
Opened November 14, 2024; 33MW of critical IT power at full build-out across six data halls, 100% leased at opening to two initially-unnamed AI companies. Lambda was named as a tenant via a separate press release approximately one year later (November 13, 2025), leasing 21MW of the 33MW total for NVIDIA Blackwell-based AI infrastructure - these are two distinct announcements, not one event. One of at least three independent data-center developments in Vernon (a small, ~200-resident, all-industrial city), alongside a separate Digital Realty land purchase (4400 Pacific Blvd) and the DataBank/Goodman Group 'Vernon LA Campus' - driven by Vernon Public Utilities offering industrial power at roughly half the rate of neighboring investor-owned utilities.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- Land area
- How the community has received it
Which document closes each gap
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Digital Realty Vernon Data Center · Vernon · Digital Realtyunder 1 mile · Proposed · 32 MW
- Vernon LA Campus (with Goodman Group) · Vernon · DataBankunder 1 mile · Proposed · 32 MW
- Digital Realty 727 S. Grand Avenue (DTLA) · Los Angeles · Digital Realty3 mi · Proposed
- CoreSite LA1 (One Wilshire) · Los Angeles · CoreSite4 mi · Operating
- CoreSite LA2 - Los Angeles, CA · Los Angeles · CoreSite4 mi · Operating
- DigiCo LAX1 (1977 Saturn Street) · Monterey Park · DigiCo Infrastructure REIT7 mi · Cancelled · Opposed
- Equinix LA4 · El Segundo · Equinix10 mi · Operating
- Serverfarm LAX1 · El Segundo · Serverfarm11 mi · Operating · 17.3 MW
Questions people ask about this site
Is there opposition to the Prime Data Centers LAX01 data center in Vernon?
Nothing on record as of August 2, 2026. No lawsuit, organized opposition, or contested hearing over Prime Data Centers LAX01 in Vernon, Los Angeles County, California appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the Prime Data Centers LAX01 data center?
No lawsuit over Prime Data Centers LAX01 appears in the record we track as of August 2, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Prime Data Centers LAX01 use?
No water withdrawal figure for Prime Data Centers LAX01 is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Prime Data Centers LAX01, and how big is it?
Prime Data Centers is the operator on record. We hold 6 sites for that company across the registry. Capacity on record is 33 MW.
How to cite this page
SueDataCenters.org Data Center Registry, "Prime Data Centers LAX01," updated August 2, 2026, https://suedatacenters.org/data-centers/prime-lax01-vernon-ca.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/prime-lax01-vernon-ca, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Prime opens Los Angeles data center · Prime Data Centers · retrieved August 2, 2026
- 2.Prime Data Centers announces opening of its hyperscale data center in Vernon, California · PR Newswire · retrieved August 2, 2026
- 3.Prime Data Centers and Lambda partner on AI-optimized infrastructure in Southern California · Prime Data Centers · retrieved August 2, 2026
- 4.Lambda partners with Prime Data Centers in Southern California · Lambda · retrieved August 2, 2026
- 5.Prime launches 33MW data center in Vernon, California · Data Center Dynamics · retrieved August 2, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us