Sue Data Centers

Data Center Registry

Roswell Information Park

Roswell, Chaves County, New Mexico

ProposedNo reception on recordRecord updated September 21, 2026

Roswell Information Park is a proposed data center in Roswell, New Mexico (Chaves County), operated by Roswell Information Park LLC (developer Sustany LLC). The public record puts it at announced September 24, 2025, 154 acres.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Proposed

Operator
Roswell Information Park LLC (developer Sustany LLC)
Facility type
Data center
Location
Roswell, Chaves County, NM
Coordinates
33.3943, -104.5230 (approximate)
Power capacity
Not established from a public source
Land
154 acres
Investment
Not established from a public source
Announced
September 24, 2025
Utility
Not established from a public source
Power source
On site gas
Cooling
Closed loop
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
No reception on record
Source confidence
Reported by at least one credible outlet or filing

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. May 29, 2026
    Proposed
    Desert Mountain Energy signed a 25-year lease (plus a five-year extension option) with Roswell Information Park LLC for a proposed off-grid data center on roughly 154 acres, with 14 acres carved out for a potential DME battery plant. The New Mexico Economic Development Department and the Roswell-Chaves County Economic Development Corporation provided letters of support. Source: The Newswire / Desert Mountain Energy Corp.

Opposition and litigation at this site

Nothing on record as of September 21, 2026. No lawsuit, organized opposition, or contested hearing over Roswell Information Park in Roswell, Chaves County, New Mexico appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.

A new status, a permit, a reception finding, or a lawsuit. Nothing else, ever.

Power and water

Planned as an off-grid campus with a dedicated natural gas supply: the park has agreed to purchase 100% of the natural gas produced from Desert Mountain Energy's West Pecos Gas Field and to manage additional third-party gas flows. Desert Mountain Energy has also been invited to develop carbon-capture solutions tied to the campus's power generation. No MW figure is disclosed in the cited releases.

Notes on the record

Distinct from the Zenith Volts Roswell/Chaves County project already tracked: different developer (Sustany LLC / Roswell Information Park LLC vs Zenith Volts Corp.), different site size (~154 acres vs a 300-acre initial site inside an 8,400-acre approval), and a different power model (off-grid gas from DME's West Pecos field vs on-site solar plus gas plus BESS). Capacity figures circulating in secondary coverage (100-200 MW at start-up scaling toward 4 GW) were NOT read on a primary page in this session and are deliberately omitted. Coordinate is the Roswell locality anchor; the releases say only 'near Roswell'.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Power capacity in megawatts
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • How the community has received it
  • Which utility serves it
Which document closes each gap
Power capacity in megawatts
The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
How the community has received it
Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Free case review

Living near Roswell Information Park?

Tell us the basics and an independent attorney handling data center cases in your state will follow up. Free, and you are never obligated to hire anyone.

Questions people ask about this site

Is there opposition to the Roswell Information Park data center in Roswell?

Nothing on record as of September 21, 2026. No lawsuit, organized opposition, or contested hearing over Roswell Information Park in Roswell, Chaves County, New Mexico appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

Has anyone filed a lawsuit over the Roswell Information Park data center?

No lawsuit over Roswell Information Park appears in the record we track as of September 21, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Roswell Information Park use?

No water withdrawal figure for Roswell Information Park is on record here. Cooling is recorded as closed_loop, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.

Who operates Roswell Information Park, and how big is it?

Roswell Information Park LLC (developer Sustany LLC) is the operator on record. No capacity figure is on record for this site. The site is recorded at 154 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Roswell Information Park," updated September 21, 2026, https://suedatacenters.org/data-centers/roswell-information-park-chaves-county-nm.

Facility data from Compute Atlas (E. Kubiak), version 1.34.0 (September 21, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/roswell-information-park-chaves-county-nm, retrieved October 1, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Desert Mountain Energy to support carbon capture at Roswell data centre; CEO appointed to advisory board · PR Newswire / Desert Mountain Energy Corp. · retrieved September 15, 2026
  2. 2.Desert Mountain Energy signs long-term lease agreement with Roswell Information Park developer · The Newswire / Desert Mountain Energy Corp. · retrieved September 21, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us