AAIM Data Centers, Hutchinson (Minnesota 2 Energy Park)
Hutchinson, McLeod County, Minnesota
AAIM Data Centers, Hutchinson (Minnesota 2 Energy Park) is a permitted crypto mining site in Hutchinson, Minnesota (McLeod County), operated by B-MN Data Centers Inc. (d/b/a AAIM DataCenters). The public record puts it at 20 MW planned.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Permitted
- Operator
- B-MN Data Centers Inc. (d/b/a AAIM DataCenters)
- Facility type
- Crypto mining
- Location
- 1025 5th Avenue SE, Hutchinson, McLeod County, MN, 55350
- Coordinates
- 44.8870, -94.3517 (approximate)
- Power capacity
- 20 MW planned
- Land
- Not established from a public source
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Hutchinson Utilities Commission
- Power source
- Grid
- Cooling
- air
- Water use
- Not established from a public source
- Jobs
- 4 permanent
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- August 26, 2025PermittedCity Council approved final permits (CUP) for the data center Source: City of Hutchinson
Opposition and litigation at this site
Nothing on record as of October 13, 2026. No lawsuit, organized opposition, or contested hearing over AAIM Data Centers, Hutchinson (Minnesota 2 Energy Park) in Hutchinson, McLeod County, Minnesota appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Power and water
Power Purchase Agreement approved by Hutchinson Utilities Commission on September 24, 2025 under a new Large Power Customer Tariff. The load is interruptible and ramps with market prices. Power is bought wholesale from MISO on a separate commercial pricing node. No backup generators are in the CUP site plan.
The city/HUC FAQ describes a pure air-cooled system. Water and sewer use is minimal (bathrooms and maintenance only).
Notes on the record
7,500 sq ft building, with room on the site for expansion to about 15,000 sq ft. Jobs are described as 'minimal, less then 5', so 4 is a ceiling reading and may be lower. The city's FAQ calls it a data center. It is classified as crypto mining from Baxtel's listing and the interruptible, price-responsive load. The city gave no financial incentives.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Tax abatements or other public subsidy
- Land area
- How the community has received it
Which document closes each gap
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Revolve Labs Glencoe · Glencoe · Revolve Labs13 mi · Operating · 20 MW
Questions people ask about this site
Is there opposition to the AAIM Data Centers, Hutchinson (Minnesota 2 Energy Park) data center in Hutchinson?
Nothing on record as of October 13, 2026. No lawsuit, organized opposition, or contested hearing over AAIM Data Centers, Hutchinson (Minnesota 2 Energy Park) in Hutchinson, McLeod County, Minnesota appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the AAIM Data Centers, Hutchinson (Minnesota 2 Energy Park) data center?
No lawsuit over AAIM Data Centers, Hutchinson (Minnesota 2 Energy Park) appears in the record we track as of October 13, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does AAIM Data Centers, Hutchinson (Minnesota 2 Energy Park) use?
No water withdrawal figure for AAIM Data Centers, Hutchinson (Minnesota 2 Energy Park) is on record here. Cooling is recorded as air, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.
Who operates AAIM Data Centers, Hutchinson (Minnesota 2 Energy Park), and how big is it?
B-MN Data Centers Inc. (d/b/a AAIM DataCenters) is the operator on record. Capacity on record is 20 MW.
How to cite this page
SueDataCenters.org Data Center Registry, "AAIM Data Centers, Hutchinson (Minnesota 2 Energy Park)," updated October 13, 2026, https://suedatacenters.org/data-centers/aaim-data-centers-hutchinson-mn.
Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/aaim-data-centers-hutchinson-mn, retrieved October 29, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.City of Hutchinson / Hutchinson Utilities Commission, Data Center Information FAQ · City of Hutchinson · retrieved October 13, 2026
- 2.AAIM: Minnesota 2 Energy Park (Hutchinson, MN) · Baxtel · retrieved October 13, 2026
Is a data center disrupting your home?
Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.
- Tell us about your situation
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us