Facility record
Operating
- Operator
- Revolve Labs
- Facility type
- Crypto mining
- Location
- Glencoe, McLeod County, MN
- Coordinates
- 44.7691, -94.1497 (approximate)
- Power capacity
- 20 MW planned
- Land
- 6.2 acres
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Reported by at least one credible outlet or filing
Opposition and litigation at this site
Nothing on record as of August 24, 2026. No lawsuit, organized opposition, or contested hearing over Revolve Labs Glencoe in Glencoe, McLeod County, Minnesota appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Notes on the record
Revolve Labs has operated a bitcoin-mining facility in Glencoe's industrial area since 2021. Separately, the Glencoe City Council approved a rezoning on Nov. 6, 2025 for a new first-phase 20 MW AI/HPC data center (reported $40-60M, ~6.2 acres, requiring a new substation); it is not independently confirmed whether the new build occupies the same parcel as the existing mine, so both are represented here as one site record. The 20 MW figure is the announced first phase of the new build, not current operating capacity.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- How the community has received it
- Which utility serves it
Which document closes each gap
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- LightEdge Chaska (fka Stream Data Centers Minneapolis I) · Chaska · LightEdge (GI Partners)26 mi · Operating · 3.6 MW
- Flexential Minneapolis - Chaska (MSP01) · Chaska · Flexential28 mi · Operating · 9 MW
Questions people ask about this site
Is there opposition to the Revolve Labs Glencoe data center in Glencoe?
Nothing on record as of August 24, 2026. No lawsuit, organized opposition, or contested hearing over Revolve Labs Glencoe in Glencoe, McLeod County, Minnesota appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the Revolve Labs Glencoe data center?
No lawsuit over Revolve Labs Glencoe appears in the record we track as of August 24, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Revolve Labs Glencoe use?
No water withdrawal figure for Revolve Labs Glencoe is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Revolve Labs Glencoe, and how big is it?
Revolve Labs is the operator on record. We hold 3 sites for that company across the registry. Capacity on record is 20 MW. The site is recorded at 6.2 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Revolve Labs Glencoe," updated August 24, 2026, https://suedatacenters.org/data-centers/revolve-labs-glencoe-mn.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/revolve-labs-glencoe-mn, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Revolve Labs: Minnesota Mining Data Center · Baxtel · retrieved August 8, 2026
- 2.Revolve Labs announces new high-performance data center in Glencoe · Glencoe News · retrieved August 8, 2026
- 3.Bitcoin miner Revolve Labs proposes $60m data center in Minnesota · crypto.news · retrieved August 8, 2026
- 4.Glencoe approves rezoning request for site of Revolve Labs' planned AI data center · Glencoe News · retrieved August 8, 2026
- 5.Revolve Labs announces new high-performance data center in Glencoe · Glencoe News · retrieved August 24, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us