Microsoft Pecos Data Center Campus
Pecos, Reeves County, Texas · All 45 Microsoft sites · Every Microsoft case on our tracker
Microsoft Pecos Data Center Campus is a proposed data center in Pecos, Texas (Reeves County), operated by Microsoft. The public record puts it at announced June 2026, 2 GW planned, 7,000 acres. It has documented public support and no documented opposition.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Proposed
- Operator
- Microsoft
- Facility type
- Data center, AI use confirmed
- Location
- Pecos, Reeves County, TX
- Coordinates
- 31.4200, -103.4900
- Power capacity
- 2 GW planned
- Land
- 7,000 acres
- Investment
- Not established from a public source
- Announced
- June 2026
- Utility
- Chevron/Energy Forge One LLC
- Power source
- On site gas
- On site generation
- 2.7 GW
- Cooling
- Closed loop
- Water use
- Not established from a public source
- Jobs
- 6,000 construction
- Public subsidy
- Not established from a public source
- Community reception
- Supported
- Source confidence
- Confirmed by multiple independent sources or official documentation
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- June 2026ProposedMicrosoft announces 2 GW campus in Pecos as one of largest single capacity additions in company history. Five-to-seven-year build-out planned. Source: Microsoft
Opposition and litigation at this site
Not that we can document. Local officials or residents have expressed public support for Microsoft Pecos Data Center Campus in Pecos, Reeves County, Texas, and no opposition, petition, or lawsuit appears in the sources this registry tracks as of September 10, 2026. Reeves County Judge Leo Hung is quoted welcoming the project at its June 2026 announcement; Microsoft describes a planned 'Community First approach' with future community meetings, but no meetings/hearings have occurred yet as of the article date and no opposition is documented.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: supported means local officials or residents have expressed public support and no opposition is documented.
Reeves County Judge Leo Hung is quoted welcoming the project at its June 2026 announcement; Microsoft describes a planned 'Community First approach' with future community meetings, but no meetings/hearings have occurred yet as of the article date and no opposition is documented. Checked: Microsoft's own announcement blog post only -- this is official/company-sourced reaction at announcement stage, not an independent local-news check.
Power and water
20-year PPA with Energy Forge One (Chevron subsidiary) for dedicated behind-the-meter natural gas plant (~$7B plant cost). GE Vernova and Caterpillar/Solar Turbines. Campus designed to eventually integrate with ERCOT regional grid.
Closed-loop cooling designed to minimize water use, compared by Microsoft to a fast-food restaurant on a lifecycle basis.
Notes on the record
7,000-acre campus in Reeves County. Natural gas plant investment estimated at $7B separate from campus construction. No groundbreaking date reported as of July 2026; coordinates are Pecos city center as exact parcel not disclosed.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Tax abatements or other public subsidy
- Permanent jobs promised
Which document closes each gap
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- BlockchAIn Reeves County AI GPU Hosting Site · BlockchAIn Digital Infrastructure, Inc.under 1 mile · Proposed
- Core Scientific Pecos AI Campus · Pecos · Core Scientific5 mi · Under construction · 1.5 GW
- Cipher Black Pearl Campus · Wink · Cipher Digital30 mi · Under construction · 300 MW
Questions people ask about this site
Is there opposition to the Microsoft Pecos Data Center Campus in Pecos?
Not that we can document. Local officials or residents have expressed public support for Microsoft Pecos Data Center Campus in Pecos, Reeves County, Texas, and no opposition, petition, or lawsuit appears in the sources this registry tracks as of September 10, 2026. Reeves County Judge Leo Hung is quoted welcoming the project at its June 2026 announcement; Microsoft describes a planned 'Community First approach' with future community meetings, but no meetings/hearings have occurred yet as of the article date and no opposition is documented.
Has anyone filed a lawsuit over the Microsoft Pecos Data Center Campus?
The reception note on this record refers to a court proceeding. Read it in full under opposition and litigation above, and check the sources at the foot of the page for the filing itself.
How much water does Microsoft Pecos Data Center Campus use?
No water withdrawal figure for Microsoft Pecos Data Center Campus is on record here. Cooling is recorded as closed_loop, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.
Who operates Microsoft Pecos Data Center Campus, and how big is it?
Microsoft is the operator on record. We hold 45 sites for that company across the registry. Capacity on record is 2 GW. The site is recorded at 7000 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Microsoft Pecos Data Center Campus," updated September 10, 2026, https://suedatacenters.org/data-centers/microsoft-pecos-tx.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/microsoft-pecos-tx, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Microsoft announces Pecos data center campus · Microsoft · retrieved July 6, 2026
- 2.Microsoft plans 2 GW data center campus in Pecos, Texas · Data Center Dynamics · retrieved July 6, 2026
- 3.Powering the next wave of AI: expanding capacity with our new datacenter in Pecos · retrieved September 10, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us