Sue Data Centers

Data Center Registry

Core Scientific Pecos AI Campus

Pecos, Reeves County, Texas · All 10 Core Scientific sites

Under constructionNo reception on recordAI confirmedRecord updated July 8, 2026

Core Scientific Pecos AI Campus is a data center under construction in Pecos, Texas (Reeves County), operated by Core Scientific. The public record puts it at 1.5 GW planned.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Under construction

Operator
Core Scientific
Facility type
Data center, AI use confirmed
Location
Pecos, Reeves County, TX
Coordinates
31.4400, -103.5800
Power capacity
1.5 GW planned
Land
Not established from a public source
Investment
Not established from a public source
Announced
Not established from a public source
Utility
Not established from a public source
Power source
Grid
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
No reception on record
Source confidence
Confirmed by multiple independent sources or official documentation

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. 2026
    Under construction
    Core Scientific announced expansion of its Pecos campus toward ~1.5 GW gross power; first data hall reached interior-footing milestone, first capacity expected early 2027 Source: Core Scientific Inc.

Opposition and litigation at this site

The record carries no reception finding for Core Scientific Pecos AI Campus in Pecos, Reeves County, Texas, but it does carry this note as of July 8, 2026: No community opposition or formal support vote was found specific to Core Scientific's Pecos campus; regional officials have publicly welcomed the adjacent Microsoft campus.

Power and water

Served by the ERCOT grid; Texas-New Mexico Power (TNMP) is the regional distribution utility for Pecos but Core Scientific's filings do not name it. Core Scientific announced a 'scalable behind-the-meter' power solution on 200+ acres (April 2026) with generation type/MW undisclosed - distinct from Microsoft's separate Project Kirby and the Chevron/Energy Forge One gas plant in the same county.

Notes on the record

High-density AI/HPC colocation. ~1.5 GW gross / ~1.0 GW leasable is an expansion ceiling (in notes). Co-located in Reeves County with Microsoft's separate 'Project Kirby' Pecos campus (distinct operator/parcel; tracked separately). Address on record: 1939 FM 2119. Core Scientific historically a bitcoin miner, repositioned to HDC. Coordinates are the Pecos area centroid. No Pecos-specific capex is disclosed (Q4 FY2025 capex of $279.2M is company-wide; the $226.2M CoreWeave-funded portion is contract revenue, not capex) -> investmentUsd omitted. No Reeves County abatement attributable to Core Scientific was found (the 'Pecos Power Plant LLC' abatement is a separate gas-plant entity).

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • Land area
  • How the community has received it
  • Which utility serves it
Which document closes each gap
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Land area
The rezoning application, the plat, or the deed recorded with the county.
How the community has received it
Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the Core Scientific Pecos AI Campus in Pecos?

The record carries no reception finding for Core Scientific Pecos AI Campus in Pecos, Reeves County, Texas, but it does carry this note as of July 8, 2026: No community opposition or formal support vote was found specific to Core Scientific's Pecos campus; regional officials have publicly welcomed the adjacent Microsoft campus.

Has anyone filed a lawsuit over the Core Scientific Pecos AI Campus?

No lawsuit over Core Scientific Pecos AI Campus appears in the record we track as of July 8, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Core Scientific Pecos AI Campus use?

No water withdrawal figure for Core Scientific Pecos AI Campus is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Core Scientific Pecos AI Campus, and how big is it?

Core Scientific is the operator on record. We hold 10 sites for that company across the registry. Capacity on record is 1.5 GW.

How to cite this page

SueDataCenters.org Data Center Registry, "Core Scientific Pecos AI Campus," updated July 8, 2026, https://suedatacenters.org/data-centers/core-scientific-pecos-tx.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/core-scientific-pecos-tx, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Core Scientific plans expansion to 1.5 gigawatts of gross power at Pecos, Texas campus · Core Scientific Inc. · retrieved July 7, 2026
  2. 2.Core Scientific plans expansion to 1.5 GW of gross power at Pecos, Texas campus · Core Scientific · retrieved July 8, 2026
  3. 3.Core Scientific announces Q4 FY2025 results · Core Scientific · retrieved July 8, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us