Amp Z East Texas Data Center Campus (former Southland Paper Mill)
Angelina County, Texas
Amp Z East Texas Data Center Campus (former Southland Paper Mill) is a proposed data center in Texas (Angelina County), operated by Amp Z (Amp Z Champion Data Center Holdings LLC). The public record puts it at 2.1 GW planned, 1,041 acres, a reported $1.1 billion investment.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Proposed
- Operator
- Amp Z (Amp Z Champion Data Center Holdings LLC)
- Facility type
- Data center
- Location
- Angelina County, TX
- Coordinates
- 31.3386, -94.7289 (approximate)
- Power capacity
- 2.1 GW planned
- Land
- 1,041 acres
- Investment
- $1.1 billion
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Power source
- Mixed
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- 30 permanent; 500 construction
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- February 6, 2026ProposedA memorandum of option recorded in Angelina County gives Amp Z the right to buy ~1,041 acres of the former Southland Paper Mill from Verdant Industries. Source: Lufkin Daily News
Opposition and litigation at this site
Nothing on record as of October 14, 2026. No lawsuit, organized opposition, or contested hearing over Amp Z East Texas Data Center Campus (former Southland Paper Mill) in Angelina County, Texas appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Power and water
Existing 55 MW onsite substation. The plan is to scale beyond 2.1 GW by 2029 through utility service (Oncor collateral rules apply) plus onsite generation.
Notes on the record
In unincorporated Angelina County outside Lufkin. Investment ($1.05B) and jobs come from a city of Lufkin fact sheet. The 2.1 GW is a 2029 target, not a commitment. The land is under option, not purchased. Distinct from the tracked HyperDataGrid site, which is on the former Northern Chip Mill off Ben Dunn Road. Coordinates are the Lufkin city point.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Cooling method and water use
- Tax abatements or other public subsidy
- How the community has received it
- Which utility serves it
Which document closes each gap
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- HyperDataGrid Lufkin Data Center (Former Timber Mill Site) · Lufkin · HyperDataGridunder 1 mile · Proposed · 20 MW
Questions people ask about this site
Is there opposition to the Amp Z East Texas Data Center Campus (former Southland Paper Mill) in Angelina County, Texas?
Nothing on record as of October 14, 2026. No lawsuit, organized opposition, or contested hearing over Amp Z East Texas Data Center Campus (former Southland Paper Mill) in Angelina County, Texas appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the Amp Z East Texas Data Center Campus (former Southland Paper Mill)?
No lawsuit over Amp Z East Texas Data Center Campus (former Southland Paper Mill) appears in the record we track as of October 14, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Amp Z East Texas Data Center Campus (former Southland Paper Mill) use?
No water withdrawal figure for Amp Z East Texas Data Center Campus (former Southland Paper Mill) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Amp Z East Texas Data Center Campus (former Southland Paper Mill), and how big is it?
Amp Z (Amp Z Champion Data Center Holdings LLC) is the operator on record. Capacity on record is 2.1 GW. The site is recorded at 1041 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Amp Z East Texas Data Center Campus (former Southland Paper Mill)," updated October 14, 2026, https://suedatacenters.org/data-centers/amp-z-lufkin-southland-mill-angelina-county-tx.
Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/amp-z-lufkin-southland-mill-angelina-county-tx, retrieved October 29, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.AI data center planned on 1,000+ acres at former Southland Paper Mill site · Lufkin Daily News · retrieved October 14, 2026
- 2.OpenStreetMap Nominatim geocode: Lufkin, TX · OpenStreetMap contributors · retrieved October 14, 2026
Is a data center disrupting your home?
Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.
- Tell us about your situation
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us