Salcido Cashmere Data Center is an operating crypto mining site in Cashmere, Washington (Chelan County), operated by Salcido Enterprises, LLC. The public record puts it at announced 2014.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Operating
- Operator
- Salcido Enterprises, LLC
- Facility type
- Crypto mining
- Location
- Cashmere, Chelan County, WA
- Coordinates
- 47.5262, -120.4692 (approximate)
- Power capacity
- Not established from a public source
- Land
- Not established from a public source
- Investment
- Not established from a public source
- Announced
- 2014
- Utility
- Not established from a public source
- Power source
- Hydro
- Cooling
- air
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Reported by at least one credible outlet or filing
Opposition and litigation at this site
Nothing on record as of September 21, 2026. No lawsuit, organized opposition, or contested hearing over Salcido Cashmere Data Center in Cashmere, Chelan County, Washington appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Notes on the record
Company's own site lists "Core (Cashmere)", completed 2014, described as a converted industrial complex for cryptocurrency mining, the company's oldest listed facility. Baxtel corroborates a Cashmere site in the Salcido portfolio. No independent (non-operator) press specifically naming this site was found; capacity not disclosed. Same company-wide crypto-to-AI pivot caveat applies (see Pangborn record).
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Tax abatements or other public subsidy
- Permanent jobs promised
- Land area
- How the community has received it
- Which utility serves it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Salcido Columbia Data Center · Wenatchee · Salcido Enterprises, LLC10 mi · Operating
- Bitdeer Wenatchee (Pangborn) Data Center · East Wenatchee · Bitdeer14 mi · Under construction · 13 MW
- Actapio East Wenatchee Data Center · East Wenatchee · Actapio, Inc.14 mi · Operating
- Microsoft East Wenatchee Data Center · East Wenatchee · Microsoft15 mi · Operating · 180 MW
- Salcido Pangborn Data Center · East Wenatchee · Salcido Enterprises, LLC15 mi · Operating · 10 MW
- Giga Watt Mining Facility (former) · East Wenatchee · Giga Watt Inc.15 mi · Cancelled
- Sabey Intergate.Columbia Building D · East Wenatchee · Sabey Data Centers15 mi · Under construction · 14.4 MW
- Sabey Intergate.Columbia Building A · East Wenatchee · Sabey Data Centers15 mi · Operating
Questions people ask about this site
Is there opposition to the Salcido Cashmere Data Center in Cashmere?
Nothing on record as of September 21, 2026. No lawsuit, organized opposition, or contested hearing over Salcido Cashmere Data Center in Cashmere, Chelan County, Washington appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the Salcido Cashmere Data Center?
No lawsuit over Salcido Cashmere Data Center appears in the record we track as of September 21, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Salcido Cashmere Data Center use?
No water withdrawal figure for Salcido Cashmere Data Center is on record here. Cooling is recorded as air, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.
Who operates Salcido Cashmere Data Center, and how big is it?
Salcido Enterprises, LLC is the operator on record. We hold 9 sites for that company across the registry. No capacity figure is on record for this site.
How to cite this page
SueDataCenters.org Data Center Registry, "Salcido Cashmere Data Center," updated September 21, 2026, https://suedatacenters.org/data-centers/salcido-cashmere-cashmere-wa.
Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/salcido-cashmere-cashmere-wa, retrieved October 29, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Salcido Enterprises, Data Centers (Core / Cashmere, complete 2014, cryptocurrency mining conversion) · Salcido Enterprises, LLC · retrieved September 21, 2026
- 2.Salcido Enterprises Data Centers and Colocation · Baxtel · retrieved August 5, 2026
Is a data center disrupting your home?
Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.
- Tell us about your situation
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us