Data Center Registry
CyrusOne New Albany COL-1
Johnstown, Licking County, Ohio · All 24 CyrusOne sites · Every CyrusOne case on our tracker
CyrusOne New Albany COL-1 is a data center under construction in Johnstown, Ohio (Licking County), operated by CyrusOne. The public record puts it at 93.8 acres, a reported $150 million investment.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Under construction
- Operator
- CyrusOne
- Facility type
- Data center
- Location
- Johnstown, Licking County, OH
- Coordinates
- 40.0929, -82.7181
- Power capacity
- Not established from a public source
- Land
- 93.8 acres
- Investment
- $150 million
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Confirmed by multiple independent sources or official documentation
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- September 2025Under constructionCeremonial groundbreaking September 18, 2025; state filings show construction beginning November 1, 2024. Estimated construction completion September 22, 2026. Source: NBC4 (WCMH)
Opposition and litigation at this site
Nothing on record as of July 18, 2026. No lawsuit, organized opposition, or contested hearing over CyrusOne New Albany COL-1 in Johnstown, Licking County, Ohio appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Notes on the record
12181 Jug St, Johnstown, in the Licking County section of the New Albany International Business Park. 274,518 sq ft, two-story building. Ohio Tax Credit Authority approved a 10-year, 75% data center sales tax exemption valued at $5.4M (approved ~April 2024). No IT-load MW figure is publicly disclosed for this site, an earlier 60MW figure found in some secondary sources actually belongs to a different operator's nearby New Albany campus (STACK Infrastructure NAL01) and is not attributable to CyrusOne COL-1; capacityMw is omitted rather than guessed. No AI/HPC-specific marketing found, treated as generic hyperscale colo.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- How the community has received it
- Which utility serves it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- EdgeConneX MCN New Albany (South Campus) · New Albany · EdgeConneXunder 1 mile · Under construction · 224 MW
- AWS New Albany (Newton Court) · New Albany · Amazon Web Servicesunder 1 mile · Operating
- Vantage Data Centers OH1 · Johnstown · Vantage Data Centers2 mi · Under construction · 192 MW · Supported
- AWS New Albany (2550 Beech Road) · New Albany · Amazon Web Services2 mi · Operating
- QTS New Albany IV · New Albany · QTS Data Centers2 mi · Permitted
- AWS New Albany (3180 Beech Road) · New Albany · Amazon Web Services2 mi · Operating
- AWS New Albany (Beech/Miller Road Campus) · New Albany · Amazon Web Services3 mi · Under construction
- QTS New Albany 1 · New Albany · QTS Data Centers3 mi · Under construction · 144 MW
Questions people ask about this site
Is there opposition to the CyrusOne New Albany COL-1 data center in Johnstown?
Nothing on record as of July 18, 2026. No lawsuit, organized opposition, or contested hearing over CyrusOne New Albany COL-1 in Johnstown, Licking County, Ohio appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the CyrusOne New Albany COL-1 data center?
No lawsuit over CyrusOne New Albany COL-1 appears in the record we track as of July 18, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does CyrusOne New Albany COL-1 use?
No water withdrawal figure for CyrusOne New Albany COL-1 is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates CyrusOne New Albany COL-1, and how big is it?
CyrusOne is the operator on record. We hold 24 sites for that company across the registry. No capacity figure is on record for this site. The site is recorded at 93.8 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "CyrusOne New Albany COL-1," updated July 18, 2026, https://suedatacenters.org/data-centers/cyrusone-new-albany-col1-licking-county-oh.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/cyrusone-new-albany-col1-licking-county-oh, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Permits offer details after groundbreaking of $150 million New Albany data center · NBC4 (WCMH) · retrieved July 10, 2026
- 2.CyrusOne breaks ground on New Albany, Ohio data center · Data Center Dynamics · retrieved July 10, 2026
- 3.Licking County parcel/GIS record (parcel 095-112236-00.000 (PID 95785)) · Licking County GIS / Assessor · retrieved July 18, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us