Sue Data Centers

Data Center Registry

EdgeConneX MCN New Albany (South Campus)

New Albany, Licking County, Ohio · All 16 EdgeConneX sites · Every EdgeConneX case on our tracker

Under constructionNo reception on recordRecord updated September 10, 2026

EdgeConneX MCN New Albany (South Campus) is a data center under construction in New Albany, Ohio (Licking County), operated by EdgeConneX. The public record puts it at announced July 16, 2025, 224 MW planned, 267 acres, a reported $1 billion investment.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Under construction

Operator
EdgeConneX
Facility type
Data center
Location
New Albany, Licking County, OH
Coordinates
40.0888, -82.7227
Power capacity
224 MW planned
Land
267 acres
Investment
$1 billion
Announced
July 16, 2025
Utility
Not established from a public source
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Ohio Tax Credit Authority, 50% data-center sales/use-tax exemption (10-year), State of Ohio, 2025
Community reception
No reception on record
Source confidence
Reported by at least one credible outlet or filing

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. 2025
    Under construction
    Phase I warehouse conversion (80 MW) underway; Phase II (two new 72 MW buildings) proposed. Ohio TCA sales-tax exemption approved Oct 2025. Source: Ohio Tax Credit Authority / Gongwer

Opposition and litigation at this site

Nothing on record as of September 10, 2026. No lawsuit, organized opposition, or contested hearing over EdgeConneX MCN New Albany (South Campus) in New Albany, Licking County, Ohio appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.

Public money on the record

ProgramAmountGranted byYear
Ohio Tax Credit Authority, 50% data-center sales/use-tax exemption (10-year)Not establishedState of Ohio2025

Notes on the record

EdgeConneX's ~$1B multi-phase "MCN New Albany" South campus. Per the Ohio Tax Credit Authority scope-of-work filing: Phase I converts a ~525,000 sq ft existing warehouse (9850 Innovation Campus Way) into an 80 MW data center; Phase II proposes two new 72 MW facilities (144 MW), capacityMw.planned = 224 (80 + 144, IT load). A co-located PowerConneX natural-gas energy center (reported 140 to 216 MW of generation across sources) is EXCLUDED from capacityMw as on-site generation, not IT load. Footprint spans the South PropCo 2 parcels (~97 ac incl. the built anchor) plus the adjacent North PropCo 1 parcel (3356 Clover Valley Rd NW, 170 ac); ~267 ac combined. "MCN" is EdgeConneX's internal project prefix (not publicly decoded). Distinct from EdgeConneX's separate Piper Farms parcel (~5 mi away) and from edgeconnex-ashville-oh (Pickaway County). Public-reception check (2026-09-10): IMPORTANT DISAMBIGUATION: this is EdgeConneX's New Albany/Licking County campus (Innovation Campus Way; Phase 1 120MW, Phase 2 216MW, Phase 3 430MW). It is a SEPARATE EdgeConneX project from the heavily-opposed EdgeConneX proposal in Ashville, Pickaway County, OH (denied annexation 2026-02-02 after packed council meetings and a Change.org petition) -- do not merge that record's contention into this one. For New Albany/Licking County specifically, a land-purchase article (2025, checked 2026-09-10) mentions only general Central Ohio-wide concern that data centers could raise electricity costs, immediately caveated because this project's power comes from dedicated on-site generation (PowerConneX), not the residential grid. No hearing, resident testimony, or official statement specific to this Licking County site was found.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Cooling method and water use
  • Permanent jobs promised
  • How the community has received it
  • Which utility serves it
Which document closes each gap
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
How the community has received it
Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the EdgeConneX MCN New Albany (South Campus) in New Albany?

Nothing on record as of September 10, 2026. No lawsuit, organized opposition, or contested hearing over EdgeConneX MCN New Albany (South Campus) in New Albany, Licking County, Ohio appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

Has anyone filed a lawsuit over the EdgeConneX MCN New Albany (South Campus)?

No lawsuit over EdgeConneX MCN New Albany (South Campus) appears in the record we track as of September 10, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does EdgeConneX MCN New Albany (South Campus) use?

No water withdrawal figure for EdgeConneX MCN New Albany (South Campus) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates EdgeConneX MCN New Albany (South Campus), and how big is it?

EdgeConneX is the operator on record. We hold 16 sites for that company across the registry. Capacity on record is 224 MW. The site is recorded at 267 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "EdgeConneX MCN New Albany (South Campus)," updated September 10, 2026, https://suedatacenters.org/data-centers/edgeconnex-mcn-new-albany-licking-county-oh.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/edgeconnex-mcn-new-albany-licking-county-oh, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Licking County parcel/GIS record (EdgeConneX MCN New Albany South PropCo 2 + North PropCo 1 parcels; anchor 9850 Innovation Campus Way, 33.86 ac, "Industrial Warehouses") · Licking County Auditor GIS / Assessor · retrieved July 18, 2026
  2. 2.Ohio Tax Credit Authority, Exhibit I Scope of Work, EdgeConneX MCN New Albany South Opco 1 LLC (Phase I 80 MW, Phase II 2×72 MW) · Ohio Tax Credit Authority / Gongwer · retrieved July 18, 2026
  3. 3.EdgeConneX plans more than 1 million square feet of data centers in New Albany · NBC4 WCMH-TV · retrieved July 18, 2026
  4. 4.$1 billion data center development buys 136 more acres in New Albany · 614NOW · retrieved July 18, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us