AWS New Albany (Newton Court) is an operating data center in New Albany, Ohio (Licking County), operated by Amazon Web Services. The public record puts it at 92.69 acres.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Operating
- Operator
- Amazon Web Services
- Facility type
- Data center, AI use likely
- Location
- New Albany, Licking County, OH
- Coordinates
- 40.0937, -82.7299
- Power capacity
- Not established from a public source
- Land
- 92.69 acres
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Power source
- Grid
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- 2024OperatingListed as built 2024 / fully operational by data-center directories; Licking County Auditor land-use class 305 ('Research/Chemical Labs' = built industrial) on the Amazon Data Services Inc parcel at 2575 Newton Ct. Source: Baxtel
Opposition and litigation at this site
Nothing on record as of July 24, 2026. No lawsuit, organized opposition, or contested hearing over AWS New Albany (Newton Court) in New Albany, Licking County, Ohio appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Power and water
Part of the New Albany 'Silicon Heartland' campus cluster. No site-specific clean-energy deal or on-site generation found for this address; same caveat as other New Albany-area buildings, Amazon's documented Ohio renewables are company-wide, not site-tied.
Notes on the record
Operational AWS data center on a ~93-acre Amazon Data Services Inc parcel at 2575 Newton Ct, New Albany (~7 km south of the Beech/Miller cluster), part of Amazon's AWS US-East-2 (Ohio) footprint. Data-center directories label it '2575 Newton' / 'Tower Ultra', built 2024 / fully operational. Licking County Auditor land-use class 305 ('Research/Chemical Labs' = built industrial); owner Amazon Data Services Inc. Data-center directories list numbered Newton addresses (2575/2675/2775/2875/2975) as separate sites, but only one Amazon-owned parcel (095-112074-00.000) exists at 2575 Newton Ct, the numbered addresses are buildings within this single parcel, not distinct sites. No site-specific IT-load MW is disclosed. Coordinates are the Licking County Auditor parcel centroid.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- How the community has received it
- Which utility serves it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Our reporting on this site
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- EdgeConneX MCN New Albany (South Campus) · New Albany · EdgeConneXunder 1 mile · Under construction · 224 MW
- CyrusOne New Albany COL-1 · Johnstown · CyrusOneunder 1 mile · Under construction
- Vantage Data Centers OH1 · Johnstown · Vantage Data Centers1 mi · Under construction · 192 MW · Supported
- AWS New Albany (2550 Beech Road) · New Albany · Amazon Web Services1 mi · Operating
- AWS New Albany (3180 Beech Road) · New Albany · Amazon Web Services1 mi · Operating
- QTS New Albany IV · New Albany · QTS Data Centers1 mi · Permitted
- AWS New Albany (Beech/Miller Road Campus) · New Albany · Amazon Web Services2 mi · Under construction
- QTS New Albany 1 · New Albany · QTS Data Centers3 mi · Under construction · 144 MW
Questions people ask about this site
Is there opposition to the AWS New Albany (Newton Court) data center in New Albany?
Nothing on record as of July 24, 2026. No lawsuit, organized opposition, or contested hearing over AWS New Albany (Newton Court) in New Albany, Licking County, Ohio appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the AWS New Albany (Newton Court) data center?
No lawsuit over AWS New Albany (Newton Court) appears in the record we track as of July 24, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does AWS New Albany (Newton Court) use?
No water withdrawal figure for AWS New Albany (Newton Court) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates AWS New Albany (Newton Court), and how big is it?
Amazon Web Services is the operator on record. We hold 54 sites for that company across the registry. No capacity figure is on record for this site. The site is recorded at 92.69 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "AWS New Albany (Newton Court)," updated July 24, 2026, https://suedatacenters.org/data-centers/aws-newton-court-new-albany-oh.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/aws-newton-court-new-albany-oh, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Licking County Auditor parcel/GIS record (parcel 095-112074-00.000, 2575 Newton Ct, Amazon Data Services Inc, Industrial land-use class 305 'Research/Chemical Labs' = built, 92.7 ac) · Licking County Auditor GIS / Assessor · retrieved July 19, 2026
- 2.Amazon 2575 Newton ('Tower Ultra'), fully operational, built 2024, AWS US East (Ohio) region · Baxtel · retrieved July 19, 2026
- 3.AWS News Blog: More Amazon wind and solar farms are live · retrieved July 24, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us