Data Center Registry
CleanSpark Lenoir City Bitcoin Mining Facility
Lenoir City, Loudon County, Tennessee · All 25 CleanSpark sites
CleanSpark Lenoir City Bitcoin Mining Facility is an operating crypto mining site in Lenoir City, Tennessee (Loudon County), operated by CleanSpark, Inc. The public record puts it at announced October 31, 2024, 40 MW planned.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Operating
- Operator
- CleanSpark, Inc.
- Facility type
- Crypto mining
- Location
- Lenoir City, Loudon County, TN
- Coordinates
- 35.7973, -84.2560 (approximate)
- Power capacity
- 20 MW operating; 40 MW planned
- Land
- Not established from a public source
- Investment
- Not established from a public source
- Announced
- October 31, 2024
- Utility
- TVA
- Power source
- Grid
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Confirmed by multiple independent sources or official documentation
Opposition and litigation at this site
Nothing on record as of September 9, 2026. No lawsuit, organized opposition, or contested hearing over CleanSpark Lenoir City Bitcoin Mining Facility in Lenoir City, Loudon County, Tennessee appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Power and water
GRIID/CleanSpark sites in Tennessee are serviced by the Tennessee Valley Authority.
Notes on the record
One of GRIID Infrastructure's three original Tennessee sites, inherited by CleanSpark when it closed the GRIID acquisition Oct 31, 2024. GRIID announced a 20 MW -> 40 MW expansion plan for this specific site in Feb 2024 (pre-acquisition); treat the 40 MW figure as a disclosed target, not a verified current state. The FY2025 10-K confirms CleanSpark operated 10 wholly-owned TN locations (234 MW / 12.43 EH/s aggregate) as of 2025-09-30, including this site, but discloses no updated per-site MW.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- Land area
- How the community has received it
Which document closes each gap
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Oak Ridge Reservation AI Data Center Sites (DOE land lease) · Oak Ridge · U.S. Department of Energy12 mi · Proposed
- The Fort (TenHats Knoxville Data Center) · Knoxville · TenHats (formerly SH Data Technologies)22 mi · Operating
- Bitdeer Knoxville AI Datacenter (5101 S. National Drive) · Knoxville · Bitdeer26 mi · Under construction · 86 MW
Questions people ask about this site
Is there opposition to the CleanSpark Lenoir City Bitcoin Mining Facility in Lenoir City?
Nothing on record as of September 9, 2026. No lawsuit, organized opposition, or contested hearing over CleanSpark Lenoir City Bitcoin Mining Facility in Lenoir City, Loudon County, Tennessee appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the CleanSpark Lenoir City Bitcoin Mining Facility?
No lawsuit over CleanSpark Lenoir City Bitcoin Mining Facility appears in the record we track as of September 9, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does CleanSpark Lenoir City Bitcoin Mining Facility use?
No water withdrawal figure for CleanSpark Lenoir City Bitcoin Mining Facility is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates CleanSpark Lenoir City Bitcoin Mining Facility, and how big is it?
CleanSpark, Inc. is the operator on record. We hold 25 sites for that company across the registry. Capacity on record is 40 MW.
How to cite this page
SueDataCenters.org Data Center Registry, "CleanSpark Lenoir City Bitcoin Mining Facility," updated September 9, 2026, https://suedatacenters.org/data-centers/cleanspark-lenoir-city-tn.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/cleanspark-lenoir-city-tn, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.CleanSpark Announces Agreement to Acquire GRIID Infrastructure · PR Newswire (CleanSpark, Inc.) · retrieved August 5, 2026
- 2.GRIID Infrastructure Announces Plans to Double Capacity of Lenoir City, Tenn. Bitcoin Mining Operations · GlobeNewswire (GRIID Infrastructure, Inc.) · retrieved August 5, 2026
- 3.CleanSpark, Inc. FY2025 Form 10-K (Item 2 Properties / Tennessee Operations) · CleanSpark, Inc. / SEC EDGAR · retrieved August 5, 2026
- 4.CleanSpark Releases December 2025 Bitcoin Mining Update · CleanSpark, Inc. (via StockTitan) · retrieved September 9, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us