Bradley County Made Data Centers Almost Impossible in April. In August, 850 Acres Asked to Join the City Instead, Where the Proposed Setback Is 500 Feet Rather Than 3,000.

On April 20, 2026 the Bradley County Commission unanimously passed data center rules a commissioner said made approval "99.9% impossible": a 3,000 foot setback from homes, schools and churches. On August 25 an 850 acre site on Old Lower River Road was submitted for annexation into the City of Cleveland, where the proposed ordinance sets a 500 foot setback. The developer says Project River is not a data center. Its own $11.3 billion breakdown puts $7.3 billion into data center buildings and 525 of 900 jobs into data center operations. Here is the record, the arithmetic, and the three dates that decide it.

Case facts

Regulatory fight

Status
No lawsuit filed. Annexation and rezoning pending before the City of Cleveland; PUD 77 final draft released September 18, 2026; Planning Commission presentation September 21; council vote expected October at the earliest
Dispute
Bradley County residents against the annexation and rezoning of an 850 acre site for Project River, an industrial energy campus whose largest single cost line is data center buildings. Supporters include the Wright family, Wright Brothers Construction and UA Local 43
Forum
Cleveland Municipal Planning Commission and Cleveland City Council. No court filing as of September 18, 2026
The site
Roughly 850 acres of privately owned Wright family land west of Interstate 75 and north of Old Lower River Road NW, along the Hiwassee River near Exit 33, across I-75 from the Wacker polysilicon plant. Submitted for annexation into the City of Cleveland and rezoning from Forestry Agricultural Residential on August 25, 2026
Developer
The Wright family, which owns the land, leading the project separately from Charleston, Tennessee based Wright Brothers Construction, founded in 1961. Mitchell Simpson is president and CEO of Wright Brothers Construction; Lukas Salyer, a Wright family member by marriage, is president of Wright Industrial Group
What is proposed
An 850 acre campus generating up to 1,500 MW on site, a 1,000 MW natural gas plant plus a 500 MW biomass plant burning southern pine, with a further 360 MW requested from TVA for backup and peaking. Built in four phases over 60 months, with groundbreaking hoped for late 2027 or early 2028
The money
$11.3 billion in private investment as itemised in press coverage: $7.3 billion data center buildings, $1.5 billion gas generation, $1.25 billion biomass, $750 million transmission, $500 million site work. Excludes servers and processors. The Chattanoogan reports the behind the meter generation facility as a $4 billion component
The jobs
900 permanent on site jobs at a stated median of $84,600, of which the developer's own breakdown is 525 data center operations, 250 power generation and 125 biomass handling, plus 1,700 claimed indirect forestry jobs and about 3,500 construction jobs at peak. None independently established
The tenant
None. Wright Industrial Group president Lukas Salyer told residents on September 1, 2026: "It is not a data center and what we can say today is we do not have a contract with an off taker of the power or a user of the power"
Litigation
None. No lawsuit has been filed by residents, the county, the city or the developer

Key Takeaways

  • Nothing is approved. The 850 acres were submitted for annexation into the City of Cleveland and rezoning on August 25, 2026, one day before the project was announced. The city published proposed conditions as Planned Unit Development 77, released the final draft at 5 p.m. on Friday, September 18, and has a Planning Commission presentation set for Monday, September 21 at 6 p.m. at the Cleveland Municipal Building. City Manager Joe Fivas has said a decision could be "October, November, December, January."
  • The sequence is the thing to understand, and the two numbers that matter are 3,000 and 500. On April 20, 2026 the Bradley County Commission unanimously adopted data center rules barring any such facility within 3,000 feet of a Forestry Agricultural Residential, R-1 or R-2 zone, or of any existing home, school or church. Commissioner Milan Blake said the rules made approval "99.9% impossible," and the commission described them as the strictest it could pass without inviting a lawsuit. Four months later the site asked to leave the county's zoning jurisdiction for the city's, where the proposed setback in PUD 77 is 500 feet.
  • We cannot tell you the annexation was filed to avoid the county rule, and we are not going to imply it. Large industrial sites seek annexation for ordinary reasons: city water, sewer, fire protection and a zoning category that fits. No document we have seen states a motive. What we can tell you is that the county rule would be difficult for this project to satisfy, that annexation removes the site from that rule, and that the replacement setback is six times shorter. Those three facts are not in dispute and a resident is entitled to weigh them.
  • The developer says it is not a data center. Its own numbers say a data center is 65 percent of the project. Lukas Salyer told residents on September 1 that "it is not a data center" and that there is no contract with any user of the power. The itemised $11.3 billion puts $7.3 billion into data center buildings, the jobs breakdown puts 525 of 900 permanent positions into data center operations, the company's own August 26 release describes a campus "anchored by an on-site power plant and data center," and the city has named its ordinance after one. Both things are true at once: there is no signed tenant, and the project is designed around one.
  • The water claim is the one we would press hardest, because the developer has published a number that can be checked. Mitchell Simpson told Mix 104.1 WCLE the biomass drying process yields about 200 gallons per minute of internal water for the cooling loops, and the project's site promises "zero local utility water day-to-day." Our arithmetic, and we flag it as ours: 200 gallons per minute is 288,000 gallons a day. A 1,500 MW thermal plant on conventional recirculating wet cooling typically needs makeup water in the low thousands of gallons per minute, an order of magnitude more. Dry or air cooled condensers would close most of that gap, and would be the honest answer to the question. No source we found states what heat rejection equipment Project River intends to use. That is the single most useful question a resident can ask on September 21.
  • The binding conditions are weaker than the marketing, in two specific and checkable places. The campaign says the project makes its own power and its own water. PUD 77 as proposed requires 75 percent of directly used power to be generated on site, which leaves a quarter to the grid, and 90 percent of process water to be produced on site "after initial filling," which exempts the first fill of a cooling system for a 1,500 MW plant entirely. Neither gap is hidden. Neither is in the brochure.
  • The forestry argument is real and deserves to be stated properly, because it is the strongest thing the developer has. Eleven pulp mills have closed across the South since 2022. Resolute's Calhoun mill took 350 jobs with it in December 2021 and International Paper's Cleveland mill took 115 in December 2024. Tennessee pine stumpage is under $4 a ton. A 500 MW biomass plant would consume about 5 million tons of timber a year against the 6 million tons the developer says are available within a 200 mile radius. That is roughly 83 percent of the stated regional supply going to one buyer, which is a genuine revival for landowners and loggers and a genuine concentration risk for everyone else who buys wood.

A reader in Bradley County, Tennessee asked us to look at this one, and the record turns out to be sharper than the coverage. On April 20, 2026 the Bradley County Commission voted unanimously to bar data centers within 3,000 feet of any home, school, church or residential zone, rules one commissioner called "99.9% impossible" to satisfy and the commission itself described as the strictest it could pass without being sued. On August 25 an 850 acre tract on Old Lower River Road was submitted for annexation into the City of Cleveland and for rezoning out of Forestry Agricultural Residential. On August 26 the Wright family announced Project River, an $11.3 billion industrial energy campus: 1,000 MW of gas, 500 MW of biomass burning southern pine, 360 MW requested from TVA, 900 permanent jobs, and 2,600 counting forestry. The president of Wright Industrial Group has told residents plainly that it is not a data center and that no customer has signed. The itemised budget puts $7.3 billion into data center buildings. This piece lays out the dates, the votes, the arithmetic we could do and the arithmetic we could not, and the three dates in the next few weeks that decide it.

Free case review

Something like this happening near you? See if you have a case.

The timeline, with the votes

Bradley County was thinking about data centers well before this project existed. In spring 2026 the commission moved to draft rules, in part to settle rumors about an unnamed AI site. On April 20, 2026 it adopted them unanimously. Data centers and cryptocurrency mining operations may not be adjacent to, or within 3,000 feet of, any Forestry Agricultural Residential, R-1 or R-2 zone, nor within 3,000 feet of any existing residential dwelling, school or church. Commissioners had been asked for an outright ban and declined, on the view that a ban would be constitutionally suspect. Commissioner Milan Blake's summary was that the rules make it "99.9% impossible" for a data center to be approved. Before that vote the county had no data center regulation at all.

On August 18, 2026 the Cleveland Municipal Planning Commission took up a different Wright Brothers request: annexation of nearly 400 acres on Lower River Road. Residents filled the room because they assumed it was a data center. Planning Director Robert Varnell told them the zoning sought "would not allow for a data center. It's not allowable," and said the intended use was a travel center or large service station. The commission recommended approval of all three related items and a motion to delay failed. That parcel is a separate matter from Project River, and we say so plainly because the two have been conflated in local discussion since.

On August 25 the 850 acre Project River tract was submitted for annexation into the City of Cleveland and for rezoning. On August 26 the project was announced. Two public meetings followed at Cleveland's PIE Center, on September 1 from 6 to 8 p.m. and September 12 from 10 a.m. to noon. On September 15 the Wright family said it would accept the city's proposed conditions, subject to the final text. The final draft of PUD 77 was released at 5 p.m. on Friday, September 18. The Planning Commission takes a presentation and a rezoning discussion on Monday, September 21 at 6 p.m. at the Cleveland Municipal Building, with no vote scheduled that night. A council vote is expected in October at the earliest.

Is it a data center? Both answers are in the same file

At the September 1 meeting Lukas Salyer, president of Wright Industrial Group, was unambiguous: "It is not a data center and what we can say today is we do not have a contract with an off taker of the power or a user of the power." Mitchell Simpson had put it the same way in August: "We definitely know we're developing a power plant. We don't know what it's going to power yet." He named advanced manufacturing, robotics and semiconductor manufacturing as possibilities, then added that with that much power on site "it's very likely going to be that," meaning a data center. Asked for detail, Simpson said the team has "20, 30% engineering drawings, and it's simply not time for that yet."

Taken at face value, that is a truthful statement about a contract. No tenant has signed. It is also, read against the project's own numbers, a very narrow truth:

What the project itself publishesFigure
Data center buildings, of $11.3 billion total$7.3 billion (65%)
Gas generation$1.5 billion
Biomass generation$1.25 billion
Transmission technology$750 million
Site work and buildings$500 million
Permanent jobs in data center operations, of 900525 (58%)
Permanent jobs in power generation250
Permanent jobs in biomass handling125

The company's own August 26 release describes a campus "anchored by an on-site power plant and data center." The City of Cleveland's draft ordinance sets a setback and a noise limit for "the data center." Local outlets from the Times Free Press to NewsChannel 9 describe it as a data center project in their headlines. The honest reading is that both statements are accurate and they answer different questions: there is no signed customer, and the campus is designed and costed around one. A resident who hears "it is not a data center" and stops there has been told something true and learned something false.

The water arithmetic, from the developer's own number

Project River's most striking promise is water. The project site says "zero local utility water day-to-day," describes water reclaimed from the biomass drying process circulating in a closed loop, and contrasts that with a typical industrial user consuming "up to 5 million gallons" a day. Simpson has said the plant needs no river intake and no discharge pipes, and that the campus "will not raise power or water bills or affect the water level of the Hiwassee River." On the Chattanoogan's account and in an interview with Mix 104.1 WCLE, the figure behind the promise is 200 gallons per minute of usable internal water recovered from drying wood.

That number can be checked, so here is the check. Our arithmetic, not the developer's: 200 gallons per minute is 12,000 gallons an hour, or about 288,000 gallons a day. A thermal power plant of 1,500 MW running on conventional recirculating wet cooling, the kind that uses cooling towers, typically needs makeup water in the low thousands of gallons per minute to replace what evaporates. Against that benchmark, 200 gallons per minute is on the order of a few percent of the requirement, not all of it.

There is a design that reconciles the two, and it is the obvious one: dry cooling. Air cooled condensers reject heat to the air instead of evaporating water, cut water consumption by roughly ninety percent or more, and are used at plants that have no water to spare. They cost more, take more space and lose some efficiency on hot days, which is why they are worth asking about rather than assuming. No source we found states what heat rejection equipment Project River intends to use. The registry note on this site records the same gap: the sources describe a recirculating circuit and do not state the equipment.

So the question for September 21 is not "will you use a lot of water," which invites the answer already given. It is narrower and harder to deflect: what is the heat rejection design, what is total plant makeup water demand in gallons per minute at full load on a 95 degree day, and what supplies the difference between that number and 200? Our guide to how much water a data center actually uses explains why the answer usually arrives through a utility service agreement or a state withdrawal permit rather than voluntarily.

Free case review

Dealing with something like this near your home?

The forestry case, and the concentration inside it

The strongest argument for Project River has nothing to do with computing. Eleven pulp mills have closed across the South since 2022. Resolute Forest Products shut its Calhoun mill in December 2021, taking 350 jobs, and International Paper closed its Cleveland mill in December 2024, taking 115. When mills close, the market for pulpwood collapses and standing timber stops being worth cutting. Tennessee pine stumpage is now under $4 a ton. Simpson's framing is direct: "We're revitalizing a timber industry that's died." For a landowner with pine and no buyer, that is not a talking point, it is the difference between an asset and a liability.

The scale deserves the same scrutiny as everything else. The project's own site says roughly 6 million tons a year of forest timber and residuals are available within a 200 mile radius. The Times Free Press reports the biomass plant would process about 5 million tons of timber annually. Our arithmetic from those two published figures: one plant would take roughly 83 percent of the regional supply the developer itself describes. That is a coherent number for a 500 MW biomass plant, and it is the whole ballgame for everyone else who buys wood in that radius. It is also, to be fair, exactly the point: the argument is that the supply currently has no buyer at all.

The questions that follow are ordinary forestry questions and nobody has answered them publicly. What happens to pulpwood prices for other buyers when a single consumer takes four fifths of the supply. What the truck traffic looks like, in loads per day on which roads, to move 5 million tons a year. What the fuel supply contract says if timber prices rise and burning wood stops penciling out, and whether the gas plant simply runs harder. PUD 77 requires traffic, environmental, emergency management, hydrology, lighting and spill response studies before permits issue, which is where several of those answers should appear.

What PUD 77 would actually require

The city's proposed conditions, which the developer has accepted subject to the final text, are more specific than most communities extract. As published before the September 18 final draft, PUD 77 would require:

  • A 500 foot setback for the data center from the property line.
  • A 60 decibel limit at the property line, with continuous noise monitoring.
  • 75 percent of directly used power generated on site.
  • 90 percent of process water produced on site after initial filling, with a closed loop cooling system and no direct utility connection to the Hiwassee River.
  • Annual reporting on water and power use.
  • Limits on emissions, dust, glare, exhaust and heat crossing the property line.
  • At least 20 percent green space.
  • Land and funding for a combined fire station, EMS facility and police precinct near Exit 33.
  • Traffic, environmental, emergency management, hydrology, lighting and spill response studies before permits.
  • A Community Benefit Agreement supporting Cleveland and Bradley County schools, projects and infrastructure in Cleveland, Bradley County and Charleston. No dollar amount has been announced.
  • Binding effect on current and future owners and operators.

Continuous noise monitoring with a numeric limit at the property line is the single most valuable clause in that list, and residents elsewhere would trade a great deal for it. The pattern our noise limits guide describes is a facility that is permitted, compliant on paper, and intolerable at the fence line because nobody agreed in advance on where and when to measure. A 60 dBA limit at the line with continuous monitoring answers that in advance. What the published summary does not say is who holds the monitoring data, how often it is reported, what happens on an exceedance, and whether a resident can obtain the record. Those are the questions to put to the final text.

The Community Benefit Agreement is the other place to look. An agreement with no number in it is a promise to negotiate, not a commitment, and the time to fix that is before the vote rather than after. Our guide to data center tax abatements covers how these packages are structured and where they are renegotiated. No PILOT, abatement or industrial development board agreement has been named in any source we reviewed for Project River, which is itself notable for a project of this size and worth confirming rather than assuming.

What a Bradley County resident can actually do

No lawsuit has been filed and there is nothing yet to sue over. A court will not enjoin a city council from voting, and no decision exists to challenge. What exists is a land use proceeding at the stage where public records and specific questions still change outcomes. Our guide to fighting a proposed data center covers the general playbook; these are the Cleveland specifics.

  • Read the final PUD 77 text. It was released at 5 p.m. on Friday, September 18. Everything above is drawn from the city's published summary of the proposal. The binding document is the ordinance, and the differences between a summary and an ordinance are where these fights are won and lost.
  • Monday, September 21, 6 p.m., Cleveland Municipal Building. A presentation and rezoning discussion, with no vote scheduled. This is the meeting to ask the heat rejection question, the monitoring enforcement question, and the Community Benefit Agreement dollar figure question.
  • The council vote, October at the earliest. City Manager Joe Fivas has said it could be "October, November, December, January." Annexation and rezoning are legislative acts of the City Council, so that is the decision point, not the Planning Commission.
  • Ask for the annexation and rezoning file. The application, the staff report and any fiscal impact analysis are public records. So is any correspondence about the county's April rules and their application to this site. That last request is the one that would settle, one way or the other, the question this piece has declined to answer.
  • If it is built, the record starts now. The claims that reach a courtroom in these cases are about what a finished facility does to the people beside it. If you live near Exit 33, dated photographs, a written log and baseline noise readings taken before construction are worth more than anything gathered afterward, because they establish what the place was like. Our guide to documenting data center harm explains what to keep, and what it takes to get an injunction explains why that record decides whether a court will act.

One more thing worth saying to the reader who asked us to look. The complaint we heard was that the fight "isn't swaying our elected officials at all." On this record that reads less like officials ignoring residents and more like a process that has not reached its decision point: the county already passed the strictest rules it believed it could defend, the city has drafted unusually specific conditions, the developer has accepted them, and no one has voted on anything. The leverage that remains is in the text of PUD 77 and in the questions asked before October. That is a narrower fight than stopping a project, and it is the one actually available.

Frequently asked questions

Is Project River a data center?

The developer says no. Wright Industrial Group president Lukas Salyer told residents on September 1, 2026 that "it is not a data center" and that there is no contract with any user of the power. The project's own itemised budget puts $7.3 billion of the $11.3 billion into data center buildings, its jobs breakdown puts 525 of 900 permanent positions into data center operations, and the company's August 26 release describes a campus "anchored by an on-site power plant and data center." Both are accurate: no tenant has signed, and the campus is designed and costed around one.

Where is Project River and how big is it?

Roughly 850 acres of Wright family land west of Interstate 75 and north of Old Lower River Road NW in Bradley County, Tennessee, along the Hiwassee River near Exit 33 and across I-75 from the Wacker polysilicon plant. The campus would generate up to 1,500 MW on site from a 1,000 MW natural gas plant and a 500 MW biomass plant, with a further 360 MW requested from TVA for backup and peaking. Construction is phased over 60 months with groundbreaking hoped for late 2027 or early 2028.

Why does the annexation into Cleveland matter?

Because zoning jurisdiction changes at the city line. On April 20, 2026 the Bradley County Commission unanimously adopted rules barring data centers within 3,000 feet of any residential zone, home, school or church, which one commissioner said made approval "99.9% impossible." The 850 acres were submitted for annexation into the City of Cleveland on August 25, 2026. Inside the city, the proposed condition in PUD 77 is a 500 foot setback. No document we have seen states that avoiding the county rule was a reason for the annexation, and we do not assert it. The sequence and the two numbers are a matter of record.

How much water would Project River use?

No total has been published. The developer promises "zero local utility water day-to-day," a closed loop fed by water reclaimed from drying wood, no river intake and no discharge pipes, and cites about 200 gallons per minute of recovered internal water. Our arithmetic from that figure: 200 gallons per minute is roughly 288,000 gallons a day, while a 1,500 MW thermal plant on conventional recirculating wet cooling typically needs makeup in the low thousands of gallons per minute. Dry or air cooled condensers would close most of that gap, and no source states which heat rejection equipment is planned. PUD 77 would require 90 percent of process water on site after initial filling, which exempts the first fill.

What would PUD 77 require?

As published before the September 18 final draft: a 500 foot setback for the data center, a 60 decibel limit at the property line with continuous noise monitoring, 75 percent of directly used power generated on site, 90 percent of process water produced on site after initial filling, closed loop cooling with no direct utility connection to the Hiwassee River, annual water and power reporting, limits on emissions, dust, glare, exhaust and heat past the property line, at least 20 percent green space, land and funding for a fire, EMS and police facility near Exit 33, pre-permit traffic, environmental, hydrology, lighting and spill response studies, and a Community Benefit Agreement with no dollar amount yet announced. It would bind current and future owners.

When does Cleveland vote on Project River?

Not before October. The final PUD 77 draft was released at 5 p.m. on Friday, September 18, 2026. The Cleveland Municipal Planning Commission takes a presentation and rezoning discussion on Monday, September 21 at 6 p.m. at the Cleveland Municipal Building, with no vote scheduled that night. Annexation and rezoning are decisions of the City Council, and City Manager Joe Fivas has said it could be "October, November, December, January" before the city moves.

Is there a lawsuit over Project River?

No. As of September 18, 2026 no lawsuit has been filed by residents, Bradley County, the City of Cleveland or the developer. The project is in the land use stage: annexation and rezoning are pending and no vote has been taken. A court will not enjoin a legislative body from voting, so the remedies available now are public records requests, the text of PUD 77 itself, and specific questions at the September 21 meeting and before the council vote.

How much timber would the biomass plant burn?

About 5 million tons a year, per the Chattanooga Times Free Press. The project's own site says roughly 6 million tons a year of forest timber and residuals are available within a 200 mile radius, so our arithmetic from those two published figures is that one plant would take roughly 83 percent of the stated regional supply. The developer's argument is that this supply currently has no buyer: eleven Southern pulp mills have closed since 2022, including Resolute's Calhoun mill in December 2021 and International Paper's Cleveland mill in December 2024, and Tennessee pine stumpage is under $4 a ton.

Article sources

Our editorial standards require primary sources: government publications, regulator data, company filings, and established industry research.

  1. 1.Project River: the developer's own site, with the 1,500 MW phasing to 1,860 MW, "over $11 billion," 2,600+ jobs, "zero local utility water day-to-day," 6 million tons of timber within 200 miles, and the Resolute Calhoun and International Paper Cleveland mill closures
  2. 2.Chattanooga Times Free Press: Project River, $11.3B Bradley County campus aims to revive logging, attract data center, August 26, 2026, with the 850 acres, the $7.3 billion data center line, the full investment itemisation, 900 jobs at a $84,600 median, 5 million tons of timber a year, and the Simpson and Salyer quotes
  3. 3.Chattanooga Times Free Press: Bradley County Commission approves strict data center rules, "Almost impossible," April 20, 2026, with the unanimous vote, the 3,000 foot setbacks and Commissioner Milan Blake's assessment
  4. 4.NewsChannel 9 / WTVC: Bradley County sets rules for data centers, rejecting calls for an outright ban, with the commission's reasoning that a ban would be constitutionally suspect
  5. 5.NewsChannel 9 / WTVC: $11.3B data center pitch in Bradley County comes amid growing local skepticism, confirming the August 25 submission for annexation into the City of Cleveland and rezoning, and that Project River is separate from the 400 acre proposal
  6. 6.NewsChannel 9 / WTVC: Bradley County residents get their turn to question developers behind $11.3B Project River, September 1 to 2, 2026, with Lukas Salyer's "it is not a data center" and the resident responses
  7. 7.NewsChannel 9 / WTVC: Cleveland weighing Project River data center guardrails, but some say it's not enough, with the full PUD 77 proposed conditions, the pre-permit studies, the binding-on-successors provision and City Manager Joe Fivas's timing
  8. 8.NewsChannel 9 / WTVC: Project River wasn't on the agenda, Cleveland residents brought it up anyway, with the September 21 Planning Commission date and the Misty Parks remarks
  9. 9.Fox Chattanooga: Project River developers say they'll accept Cleveland's proposed restrictions, September 15, 2026, with Salyer's statement on binding future owners, the 20 percent green space requirement, the "after initial filling" water qualifier and the unnamed Community Benefit Agreement amount
  10. 10.NewsChannel 9 / WTVC: Data center fears spur crowd as Cleveland reviews 400-acre annexation request from builder, August 18, 2026, with Planning Director Robert Varnell stating that zoning would not allow a data center on that separate parcel
  11. 11.Chattanoogan.com: Proponents of Bradley County project with large-scale data center cite tax benefits, August 26, 2026, with the $4 billion behind the meter generation figure, "tens of millions of dollars in annual public revenue," the 200 gallons per minute claim and roughly 3,500 peak construction jobs
  12. 12.WDEF: 'Project River' to bring $7.3 billion data center, 2,600 jobs to Bradley County, the initial announcement coverage keyed to the data center portion of the budget
  13. 13.The Center Square: Project announcement sparks data center debate, Tennessee
  14. 14.Our registry records for the two halves of the campus, kept separately because the generation is the certain element and the offtaker is not: the data center and the energy campus

Related cases

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us