Facility record
Operating
- Operator
- Vantage Data Centers
- Facility type
- Data center
- Location
- 2101 M Street NE, Quincy, Grant County, WA, 98848
- Coordinates
- 47.2502, -119.8145
- Power capacity
- Not established from a public source
- Land
- Not established from a public source
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- PUD No 2 of Grant County
- Power source
- Hydro
- Cooling
- Closed loop
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Reported by at least one credible outlet or filing
Opposition and litigation at this site
Nothing on record as of September 5, 2026. No lawsuit, organized opposition, or contested hearing over Vantage Quincy WA11 in Quincy, Grant County, Washington appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Power and water
Vantage says Grant County PUD's two large-scale hydroelectric dams produce an average of 1,050 MW annually and that hydro is more than 66% of the utility's generation mix; it markets GCPUD as offering the lowest per-kW rates in the country.
Campus uses a closed-loop chilled-water system with air-side economizers and CRAH units, with N+1 redundancy; Vantage reports water utilization efficiency approaching zero litres/kW/hr.
Notes on the record
2101 M Street NE, Quincy, Grant County WA; WA1 campus with WA11/WA12/WA13 buildings, 89MW total, per DCD + Vantage's own site.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Tax abatements or other public subsidy
- Permanent jobs promised
- Land area
- How the community has received it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Vantage WA12 · Quincy · Vantage Data Centersunder 1 mile · Operating
- Sabey Intergate.Quincy Campus · Quincy · Sabey Data Centersunder 1 mile · Operating · 70 MW
- Vantage WA13 · Quincy · Vantage Data Centersunder 1 mile · Operating · 64 MW
- Salcido Horizon Data Center · Quincy · Salcido Enterprises, LLC2 mi · Operating · 4 MW
- Salcido Fortress Data Center · Quincy · Salcido Enterprises, LLC2 mi · Operating · 4.6 MW
- H5 Data Centers Quincy Campus · Quincy · H5 Data Centers2 mi · Operating · 40 MW
- NTT Data Quincy Data Center · Quincy · NTT DATA2 mi · Operating
- Microsoft Columbia Data Center (Quincy) · Quincy · Microsoft3 mi · Operating
Questions people ask about this site
Is there opposition to the Vantage Quincy WA11 data center in Quincy?
Nothing on record as of September 5, 2026. No lawsuit, organized opposition, or contested hearing over Vantage Quincy WA11 in Quincy, Grant County, Washington appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the Vantage Quincy WA11 data center?
No lawsuit over Vantage Quincy WA11 appears in the record we track as of September 5, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Vantage Quincy WA11 use?
No water withdrawal figure for Vantage Quincy WA11 is on record here. Cooling is recorded as closed_loop, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.
Who operates Vantage Quincy WA11, and how big is it?
Vantage Data Centers is the operator on record. We hold 20 sites for that company across the registry. No capacity figure is on record for this site.
How to cite this page
SueDataCenters.org Data Center Registry, "Vantage Quincy WA11," updated September 5, 2026, https://suedatacenters.org/data-centers/vantage-quincy-wa11-wa.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/vantage-quincy-wa11-wa, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Vantage facility directory · Vantage · retrieved July 22, 2026
- 2.OpenStreetMap way/337127817 · OpenStreetMap · retrieved July 22, 2026
- 3.HIFLD Electric Retail Service Territories (ORNL/DOE-CESER, 2023-08 vintage) · Oak Ridge National Laboratory (ORNL) / HIFLD · retrieved July 23, 2026
- 4.Quincy, Washington Data Center Campus, 2101 M Street NE, Quincy, WA 98848 · Vantage Data Centers · retrieved September 5, 2026
- 5.Vantage Data Centers Completes Development of 89MW, $1 Billion Quincy, Washington Campus · Vantage Data Centers · retrieved September 5, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us