Sue Data Centers

Data Center Registry

MARA Kearney Facility

Kearney, Buffalo County, Nebraska · All 8 MARA Holdings sites · Every MARA Holdings case on our tracker

OperatingNo reception on recordRecord updated August 8, 2026

MARA Kearney Facility is an operating crypto mining site in Kearney, Nebraska (Buffalo County), operated by MARA Holdings. The public record puts it at 100 MW operating.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Operating

Operator
MARA Holdings
Facility type
Crypto mining
Location
Kearney, Buffalo County, NE
Coordinates
40.7283, -99.0458 (approximate)
Power capacity
100 MW operating
Land
Not established from a public source
Investment
Not established from a public source
Announced
Not established from a public source
Utility
Not established from a public source
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
No reception on record
Source confidence
Confirmed by multiple independent sources or official documentation

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. January 2024
    Operating
    MARA acquired the operational Kearney, NE bitcoin mining site (GC Data Center Acquisition, Jan 12 2024). Source: SEC EDGAR

Opposition and litigation at this site

Nothing on record as of August 8, 2026. No lawsuit, organized opposition, or contested hearing over MARA Kearney Facility in Kearney, Buffalo County, Nebraska appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.

Notes on the record

Operational bitcoin mining site in Kearney, Buffalo County, NE. Acquired by MARA in the GC Data Center Acquisition (closed Jan 12 2024) alongside the Granbury, TX site, the two totaled ~390 MW of nameplate capacity combined; the individual Kearney capacity is not separately disclosed by MARA. Coordinates are Kearney-area approximate. Site power capacity (100 MW) is sourced to the facility's original announcement by its prior operator, Compute North; MARA subsequently acquired the site, and no post-acquisition capacity figure has been published.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • Land area
  • How the community has received it
  • Which utility serves it
Which document closes each gap
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Land area
The rezoning application, the plat, or the deed recorded with the county.
How the community has received it
Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the MARA Kearney Facility in Kearney?

Nothing on record as of August 8, 2026. No lawsuit, organized opposition, or contested hearing over MARA Kearney Facility in Kearney, Buffalo County, Nebraska appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

Has anyone filed a lawsuit over the MARA Kearney Facility?

No lawsuit over MARA Kearney Facility appears in the record we track as of August 8, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does MARA Kearney Facility use?

No water withdrawal figure for MARA Kearney Facility is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates MARA Kearney Facility, and how big is it?

MARA Holdings is the operator on record. We hold 8 sites for that company across the registry. Capacity on record is 100 MW.

How to cite this page

SueDataCenters.org Data Center Registry, "MARA Kearney Facility," updated August 8, 2026, https://suedatacenters.org/data-centers/mara-kearney-buffalo-ne.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/mara-kearney-buffalo-ne, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.MARA Holdings FY2025 Form 10-K, Operations, GC Data Center Acquisition (Granbury, TX and Kearney, NE) · SEC EDGAR · retrieved July 17, 2026
  2. 2.MARA Holdings data centers portfolio · Baxtel · retrieved July 17, 2026
  3. 3.Compute North announces Nebraska colocation center for bitcoin mining · Bitcoin Magazine · retrieved August 8, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us