Sue Data Centers

Data Center Registry

Taylor Technology Campus (formerly Project Mustang)

Taylor, Williamson County County, Texas · All 2 Big Watt Digital sites · Every PowerHouse and Hillwood case on our tracker

ProposedContestedRecord updated November 4, 2026

Taylor Technology Campus (formerly Project Mustang) is a proposed data center in Taylor, Texas (Williamson County County), operated by Big Watt Digital / PowerHouse Data Centers. The public record puts it at 1 GW planned, 664 acres. It is the subject of active public debate, with hearings, petitions, or organized opposition on record.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Proposed

Operator
Big Watt Digital / PowerHouse Data Centers
Facility type
Data center
Location
Taylor, Williamson County County, TX
Coordinates
30.5708, -97.4094 (approximate)
Power capacity
1 GW planned
Land
664 acres
Investment
Not established from a public source
Announced
Not established from a public source
Utility
Not established from a public source
Power source
On site gas
On site generation
750 MW
Cooling
Closed loop
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
Contested
Source confidence
Reported by at least one credible outlet or filing

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. October 8, 2026
    Proposed
    Taylor City Council approved the development agreement and annexation 5-0 Source: Baxtel

Opposition and litigation at this site

Yes. Taylor Technology Campus (formerly Project Mustang) in Taylor, Williamson County County, Texas is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. Approved over the objections of many residents, who raised noise, air-quality and water concerns.

A new status, a permit, a reception finding, or a lawsuit. Nothing else, ever.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: contested means active public debate is on record, with hearings, petitions, or organized opposition, without litigation.

Approved over the objections of many residents, who raised noise, air-quality and water concerns.

Source: KUT

Power and water

New 750 MW on-site natural gas plant (behind the meter). Surplus power can be sold to the grid.

The development agreement requires closed-loop cooling on reclaimed water, with an initial fill of 1.575 million gallons.

People and entities in the record

  • Greg Redden · public_official

    Member of the Taylor City Council; voted for the Section 212.172 development agreement with Taylor Technology Campus LLC for about 664.39 acres along FM 112 (formerly Project Mustang). Outcome: carried unanimously, 5-0, with all five members present (2026-10-08).

    Source
  • Heather Long · public_official

    Member of the Taylor City Council; voted for the Section 212.172 development agreement with Taylor Technology Campus LLC for about 664.39 acres along FM 112 (formerly Project Mustang). Outcome: carried unanimously, 5-0, with all five members present (2026-10-08).

    Source
  • Jim Buzan · public_official

    Mayor of Taylor; voted for the Section 212.172 development agreement with Taylor Technology Campus LLC for about 664.39 acres along FM 112 (formerly Project Mustang). Outcome: carried unanimously, 5-0, with all five members present (2026-10-08).

    Source
  • Kelly Cmerek · public_official

    Mayor Pro Tem of the Taylor City Council; voted for the Section 212.172 development agreement with Taylor Technology Campus LLC for about 664.39 acres along FM 112 (formerly Project Mustang). Outcome: carried unanimously, 5-0, with all five members present (2026-10-08).

    Source
  • Shelli Cobb · public_official

    Member of the Taylor City Council; voted for the Section 212.172 development agreement with Taylor Technology Campus LLC for about 664.39 acres along FM 112 (formerly Project Mustang). Outcome: carried unanimously, 5-0, with all five members present (2026-10-08).

    Source

Notes on the record

The site lies between FM 112 and U.S. 79, east of Taylor. Phase 1 is 500 MW, with an option for another 500 MW. Construction is planned for 2027 to 2029, with first power targeted for the first half of 2028. The coordinates are the Taylor city point.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • Which utility serves it
Which document closes each gap
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Tell us about your situation

Living near Taylor Technology Campus (formerly Project Mustang)?

Tell us the basics. Where a participating attorney in your state is available, we may share your information with them with your consent. Free, no obligation, and no guarantee anyone will contact you.

Questions people ask about this site

Is there opposition to the Taylor Technology Campus (formerly Project Mustang) in Taylor?

Yes. Taylor Technology Campus (formerly Project Mustang) in Taylor, Williamson County County, Texas is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. Approved over the objections of many residents, who raised noise, air-quality and water concerns.

Has anyone filed a lawsuit over the Taylor Technology Campus (formerly Project Mustang)?

No lawsuit over Taylor Technology Campus (formerly Project Mustang) appears in the record we track as of November 4, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Taylor Technology Campus (formerly Project Mustang) use?

No water withdrawal figure for Taylor Technology Campus (formerly Project Mustang) is on record here. Cooling is recorded as closed_loop, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.

Who operates Taylor Technology Campus (formerly Project Mustang), and how big is it?

Big Watt Digital / PowerHouse Data Centers is the operator on record. We hold 2 sites for that company across the registry. Capacity on record is 1 GW. The site is recorded at 664 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Taylor Technology Campus (formerly Project Mustang)," updated November 4, 2026, https://suedatacenters.org/data-centers/big-watt-powerhouse-taylor-technology-campus-tx.

Facility data from Compute Atlas (E. Kubiak), version 1.35.1 (November 2, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/big-watt-powerhouse-taylor-technology-campus-tx, retrieved November 5, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Big Watt, PowerHouse Win Approval for 1GW Behind-the-Meter Texas Campus · Baxtel · retrieved November 4, 2026
  2. 2.Taylor approves agreement to annex data center and power plant · KUT · retrieved November 4, 2026
  3. 3.Taylor City Council regular meeting minutes, October 8, 2026 (signed and attested) · City of Taylor, Texas · retrieved November 4, 2026

Is a data center disrupting your home?

Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.

  • Tell us about your situation
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us