Taylor Technology Campus (formerly Project Mustang)
Taylor, Williamson County County, Texas · All 2 Big Watt Digital sites · Every PowerHouse and Hillwood case on our tracker
Taylor Technology Campus (formerly Project Mustang) is a proposed data center in Taylor, Texas (Williamson County County), operated by Big Watt Digital / PowerHouse Data Centers. The public record puts it at 1 GW planned, 664 acres. It is the subject of active public debate, with hearings, petitions, or organized opposition on record.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Proposed
- Operator
- Big Watt Digital / PowerHouse Data Centers
- Facility type
- Data center
- Location
- Taylor, Williamson County County, TX
- Coordinates
- 30.5708, -97.4094 (approximate)
- Power capacity
- 1 GW planned
- Land
- 664 acres
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Power source
- On site gas
- On site generation
- 750 MW
- Cooling
- Closed loop
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- Contested
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- October 8, 2026ProposedTaylor City Council approved the development agreement and annexation 5-0 Source: Baxtel
Opposition and litigation at this site
Yes. Taylor Technology Campus (formerly Project Mustang) in Taylor, Williamson County County, Texas is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. Approved over the objections of many residents, who raised noise, air-quality and water concerns.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: contested means active public debate is on record, with hearings, petitions, or organized opposition, without litigation.
Approved over the objections of many residents, who raised noise, air-quality and water concerns.
Power and water
New 750 MW on-site natural gas plant (behind the meter). Surplus power can be sold to the grid.
The development agreement requires closed-loop cooling on reclaimed water, with an initial fill of 1.575 million gallons.
People and entities in the record
Greg Redden · public_official
Member of the Taylor City Council; voted for the Section 212.172 development agreement with Taylor Technology Campus LLC for about 664.39 acres along FM 112 (formerly Project Mustang). Outcome: carried unanimously, 5-0, with all five members present (2026-10-08).
SourceHeather Long · public_official
Member of the Taylor City Council; voted for the Section 212.172 development agreement with Taylor Technology Campus LLC for about 664.39 acres along FM 112 (formerly Project Mustang). Outcome: carried unanimously, 5-0, with all five members present (2026-10-08).
SourceJim Buzan · public_official
Mayor of Taylor; voted for the Section 212.172 development agreement with Taylor Technology Campus LLC for about 664.39 acres along FM 112 (formerly Project Mustang). Outcome: carried unanimously, 5-0, with all five members present (2026-10-08).
SourceKelly Cmerek · public_official
Mayor Pro Tem of the Taylor City Council; voted for the Section 212.172 development agreement with Taylor Technology Campus LLC for about 664.39 acres along FM 112 (formerly Project Mustang). Outcome: carried unanimously, 5-0, with all five members present (2026-10-08).
SourceShelli Cobb · public_official
Member of the Taylor City Council; voted for the Section 212.172 development agreement with Taylor Technology Campus LLC for about 664.39 acres along FM 112 (formerly Project Mustang). Outcome: carried unanimously, 5-0, with all five members present (2026-10-08).
Source
Notes on the record
The site lies between FM 112 and U.S. 79, east of Taylor. Phase 1 is 500 MW, with an option for another 500 MW. Construction is planned for 2027 to 2029, with first power targeted for the first half of 2028. The coordinates are the Taylor city point.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Tax abatements or other public subsidy
- Permanent jobs promised
- Which utility serves it
Which document closes each gap
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Blueprint Data Centers Taylor · Taylor · Blueprint Data Centersunder 1 mile · Proposed · 60 MW
- Iron Mountain Williamson County Data Center Campus · Iron Mountainunder 1 mile · Proposed
- Skybox PowerCampus Austin (Hutto) · Hutto · Skybox Datacenters (with Prologis)8 mi · Under construction · 600 MW
- Blueprint Data Centers Georgetown · Georgetown · Blueprint Data Centers17 mi · Proposed · 25 MW
- Sabey SDC Austin (Round Rock) · Round Rock · Sabey Data Centers17 mi · Operating · 84 MW
- Switch: The Rock (Round Rock) · Round Rock · Switch17 mi · Under construction · 185 MW
- Element Critical Austin One · Austin · Element Critical23 mi · Operating · 5 MW
- Bitdeer Rockdale Facility · Rockdale · Bitdeer25 mi · Operating · 170 MW
Questions people ask about this site
Is there opposition to the Taylor Technology Campus (formerly Project Mustang) in Taylor?
Yes. Taylor Technology Campus (formerly Project Mustang) in Taylor, Williamson County County, Texas is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. Approved over the objections of many residents, who raised noise, air-quality and water concerns.
Has anyone filed a lawsuit over the Taylor Technology Campus (formerly Project Mustang)?
No lawsuit over Taylor Technology Campus (formerly Project Mustang) appears in the record we track as of November 4, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Taylor Technology Campus (formerly Project Mustang) use?
No water withdrawal figure for Taylor Technology Campus (formerly Project Mustang) is on record here. Cooling is recorded as closed_loop, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.
Who operates Taylor Technology Campus (formerly Project Mustang), and how big is it?
Big Watt Digital / PowerHouse Data Centers is the operator on record. We hold 2 sites for that company across the registry. Capacity on record is 1 GW. The site is recorded at 664 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Taylor Technology Campus (formerly Project Mustang)," updated November 4, 2026, https://suedatacenters.org/data-centers/big-watt-powerhouse-taylor-technology-campus-tx.
Facility data from Compute Atlas (E. Kubiak), version 1.35.1 (November 2, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/big-watt-powerhouse-taylor-technology-campus-tx, retrieved November 5, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Big Watt, PowerHouse Win Approval for 1GW Behind-the-Meter Texas Campus · Baxtel · retrieved November 4, 2026
- 2.Taylor approves agreement to annex data center and power plant · KUT · retrieved November 4, 2026
- 3.Taylor City Council regular meeting minutes, October 8, 2026 (signed and attested) · City of Taylor, Texas · retrieved November 4, 2026
Is a data center disrupting your home?
Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.
- Tell us about your situation
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us