Facility record
Operating
- Operator
- Aphorio Carter
- Facility type
- Data center
- Location
- Collierville, Shelby County, TN
- Coordinates
- 35.0420, -89.6645 (approximate)
- Power capacity
- Not established from a public source
- Land
- 4.62 acres
- Investment
- $13 million
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Confirmed by multiple independent sources or official documentation
Opposition and litigation at this site
Nothing on record as of September 9, 2026. No lawsuit, organized opposition, or contested hearing over Collierville Enterprise Data Center (FedEx World Technology Center Campus) in Collierville, Shelby County, Tennessee appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Notes on the record
capacityMw checked 2026-09-09 and left unset: the only power figure published for this site is 10 MW of generator backup, which is standby capacity, not critical IT load, and directory listings that print "10 MW" are restating that same backup figure. The building is 100% net leased to a single tenant, so no operator capacity sheet exists.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- How the community has received it
- Which utility serves it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- The STEM Practice Sycamore View AI Data Center · Memphis · Golden Acquisitions / The STEM Practice14 mi · Under construction
- DataBank MEM1 (Memphis) · Memphis · DataBank14 mi · Operating · 0.45 MW
- 5C MEM01 Memphis (former Fred's headquarters) · Memphis · 5C Data Centers15 mi · Proposed · 15 MW
- xAI Southaven · Southaven · xAI18 mi · Operating · 2 GW · In litigation
- Colossus · Memphis · xAI20 mi · Operating · 1.2 GW · In litigation
- Colossus 2 (Whitehaven) · Memphis · xAI21 mi · Operating
- MACROHARDRR (xAI Southaven Data Center III) · Southaven · xAI21 mi · Operating
- Minihard · Memphis · xAI22 mi · Under construction
Questions people ask about this site
Is there opposition to the Collierville Enterprise Data Center (FedEx World Technology Center Campus) in Collierville?
Nothing on record as of September 9, 2026. No lawsuit, organized opposition, or contested hearing over Collierville Enterprise Data Center (FedEx World Technology Center Campus) in Collierville, Shelby County, Tennessee appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the Collierville Enterprise Data Center (FedEx World Technology Center Campus)?
No lawsuit over Collierville Enterprise Data Center (FedEx World Technology Center Campus) appears in the record we track as of September 9, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Collierville Enterprise Data Center (FedEx World Technology Center Campus) use?
No water withdrawal figure for Collierville Enterprise Data Center (FedEx World Technology Center Campus) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Collierville Enterprise Data Center (FedEx World Technology Center Campus), and how big is it?
Aphorio Carter is the operator on record. No capacity figure is on record for this site. The site is recorded at 4.62 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Collierville Enterprise Data Center (FedEx World Technology Center Campus)," updated September 9, 2026, https://suedatacenters.org/data-centers/aphorio-carter-collierville-tn.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/aphorio-carter-collierville-tn, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Aphorio Carter Acquires Data Center in Collierville, TN · Aphorio Carter (via PR Newswire) · retrieved August 14, 2026
- 2.Memphis Data Centers & Colocation · Baxtel · retrieved August 14, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us