Vantage Data Centers OH2 (Millersport Campus)
Millersport, Fairfield County, Ohio · All 20 Vantage Data Centers sites · Every Vantage Data Centers case on our tracker
Vantage Data Centers OH2 (Millersport Campus) is a data center under construction in Millersport, Ohio (Fairfield County), operated by Vantage Data Centers. The public record puts it at 696 MW planned.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Under construction
- Operator
- Vantage Data Centers
- Facility type
- Data center, AI use likely
- Location
- Millersport, Fairfield County, OH
- Coordinates
- 39.9020, -82.5324 (approximate)
- Power capacity
- 696 MW planned
- Land
- Not established from a public source
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Confirmed by multiple independent sources or official documentation
Opposition and litigation at this site
Nothing on record as of September 10, 2026. No lawsuit, organized opposition, or contested hearing over Vantage Data Centers OH2 (Millersport Campus) in Millersport, Fairfield County, Ohio appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Notes on the record
Vantage's second Ohio campus (distinct from the tracked OH1 in Johnstown), at Lancaster-Newark Rd & Blacklick Rd near Millersport, up to 7 structures incl. 4 data-center buildings, $2.1B, powered by an adjacent natural-gas generation facility; under construction as of mid-2026. Capacity figures diverge: 696 MW on Vantage's own site (used here) vs ~800 MW / 500 acres on a project aggregator, the operator figure is used and the discrepancy flagged. Coordinates approximate (Millersport city-center, not parcel-verified). Public-reception check (2026-09-10): Checked the project's own campus microsite (2026-09-10); it covers only project description and planned economic benefits, with no documented public hearing, resident reaction, or official statement of support/opposition.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- Land area
- How the community has received it
- Which utility serves it
Which document closes each gap
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Microsoft Hebron Data Center · Hebron · Microsoft8 mi · Under construction · Supported
- Microsoft Heath Data Center · Heath · Microsoft9 mi · Under construction · Supported
- Aligned Data Centers, Pataskala · Pataskala · Aligned Data Centers10 mi · Cancelled · 200 MW · Contested
- Google Lancaster Data Center · Lancaster · Google15 mi · Operating
- QTS New Albany 2 · New Albany · QTS Data Centers16 mi · Under construction · 78 MW
- QTS New Albany 1 · New Albany · QTS Data Centers16 mi · Under construction · 144 MW
- EdgeConneX MCN New Albany (South Campus) · New Albany · EdgeConneX16 mi · Under construction · 224 MW
- CyrusOne New Albany COL-1 · Johnstown · CyrusOne16 mi · Under construction
Questions people ask about this site
Is there opposition to the Vantage Data Centers OH2 (Millersport Campus) in Millersport?
Nothing on record as of September 10, 2026. No lawsuit, organized opposition, or contested hearing over Vantage Data Centers OH2 (Millersport Campus) in Millersport, Fairfield County, Ohio appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the Vantage Data Centers OH2 (Millersport Campus)?
No lawsuit over Vantage Data Centers OH2 (Millersport Campus) appears in the record we track as of September 10, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Vantage Data Centers OH2 (Millersport Campus) use?
No water withdrawal figure for Vantage Data Centers OH2 (Millersport Campus) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Vantage Data Centers OH2 (Millersport Campus), and how big is it?
Vantage Data Centers is the operator on record. We hold 20 sites for that company across the registry. Capacity on record is 696 MW.
How to cite this page
SueDataCenters.org Data Center Registry, "Vantage Data Centers OH2 (Millersport Campus)," updated September 10, 2026, https://suedatacenters.org/data-centers/vantage-oh2-millersport-fairfield-oh.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/vantage-oh2-millersport-fairfield-oh, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Vantage Millersport Campus official site: 352 acres, 696 MW IT capacity, 7 structures (up to 4 data centers), Lancaster-Newark Rd & Blacklick Rd, adjacent natural-gas power, $2.1B+ · Vantage Data Centers · retrieved August 5, 2026
- 2.Powered By Who dossier: ~39.90N/-82.53W city-center pin (no exact address), 500 acres / 800 MW figures, 'under construction' as of 2026-06 · Powered By Who · retrieved August 5, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us