Sue Data Centers

Data Center Registry

Valley Oak Partners Shinn Street Data Center

Fremont, Alameda County, California

ProposedNo reception on recordRecord updated July 26, 2026

Valley Oak Partners Shinn Street Data Center is a proposed data center in Fremont, California (Alameda County), operated by Valley Oak Partners. The public record puts it at 90 MW planned, 12.5 acres.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Proposed

Operator
Valley Oak Partners
Facility type
Data center
Location
Fremont, Alameda County, CA
Coordinates
37.5671, -121.9837 (approximate)
Power capacity
90 MW planned
Land
12.5 acres
Investment
Not established from a public source
Announced
Not established from a public source
Utility
Pacific Gas & Electric (PG&E)
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
No reception on record
Source confidence
Reported by at least one credible outlet or filing

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. 2026
    Proposed
    Status change recorded. Source: Data Center Dynamics

Opposition and litigation at this site

Nothing on record as of July 26, 2026. No lawsuit, organized opposition, or contested hearing over Valley Oak Partners Shinn Street Data Center in Fremont, Alameda County, California appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.

Notes on the record

490,000 sq ft on 12.5 acres, former US Gypsum plant site. Application submitted June 2026. Standalone campus, not colo.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • How the community has received it
Which document closes each gap
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
How the community has received it
Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the Valley Oak Partners Shinn Street Data Center in Fremont?

Nothing on record as of July 26, 2026. No lawsuit, organized opposition, or contested hearing over Valley Oak Partners Shinn Street Data Center in Fremont, Alameda County, California appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

Has anyone filed a lawsuit over the Valley Oak Partners Shinn Street Data Center?

No lawsuit over Valley Oak Partners Shinn Street Data Center appears in the record we track as of July 26, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Valley Oak Partners Shinn Street Data Center use?

No water withdrawal figure for Valley Oak Partners Shinn Street Data Center is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Valley Oak Partners Shinn Street Data Center, and how big is it?

Valley Oak Partners is the operator on record. Capacity on record is 90 MW. The site is recorded at 12.5 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Valley Oak Partners Shinn Street Data Center," updated July 26, 2026, https://suedatacenters.org/data-centers/valley-oak-shinn-street-fremont-ca.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/valley-oak-shinn-street-fremont-ca, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Valley Oak proposes 90MW data center in Fremont, California · Data Center Dynamics · retrieved July 17, 2026
  2. 2.Old Fremont materials factory planned for massive data center · Baxtel · retrieved July 17, 2026
  3. 3.37887 Shinn Street, Fremont · Data Center Map · retrieved July 17, 2026
  4. 4.HIFLD Electric Retail Service Territories (ORNL/DOE-CESER, 2023-08 vintage) · Oak Ridge National Laboratory (ORNL) / HIFLD · retrieved July 23, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us