Sue Data Centers

Data Center Registry

Peak Mining Texas 2

Corpus Christi, Nueces County, Texas · All 2 Peak Mining sites

Under constructionNo reception on recordRecord updated August 5, 2026

Peak Mining Texas 2 is a crypto mining site under construction in Corpus Christi, Texas (Nueces County), operated by Peak Mining. The public record puts it at announced May 24, 2024, 300 MW planned.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Under construction

Operator
Peak Mining
Facility type
Crypto mining
Location
Corpus Christi, Nueces County, TX
Coordinates
27.8520, -97.4210 (approximate)
Power capacity
300 MW planned
Land
Not established from a public source
Investment
Not established from a public source
Announced
May 24, 2024
Utility
Not established from a public source
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
No reception on record
Source confidence
Reported by at least one credible outlet or filing

Opposition and litigation at this site

Nothing on record as of August 5, 2026. No lawsuit, organized opposition, or contested hearing over Peak Mining Texas 2 in Corpus Christi, Nueces County, Texas appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.

Notes on the record

Second 300MW parcel, adjacent to Texas 1, purchased May 2024 with its own ERCOT interconnect. Lowered to 'reported'/under_construction: Northern Data's Jan 2026 disclosure states the combined Corpus Christi campus has 600MW of available grid capacity but only 100MW is actually used for Bitcoin mining (matching Texas 1), implying Texas 2 is not yet in active mining use; a June 2026 Texas Observer piece describes the project as 'scaled to one facility.' Same ownership-change caveat as Texas 1. Coordinates are an approximate adjacent-parcel estimate.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • Land area
  • How the community has received it
  • Which utility serves it
Which document closes each gap
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Land area
The rezoning application, the plat, or the deed recorded with the county.
How the community has received it
Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the Peak Mining Texas 2 data center in Corpus Christi?

Nothing on record as of August 5, 2026. No lawsuit, organized opposition, or contested hearing over Peak Mining Texas 2 in Corpus Christi, Nueces County, Texas appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

Has anyone filed a lawsuit over the Peak Mining Texas 2 data center?

No lawsuit over Peak Mining Texas 2 appears in the record we track as of August 5, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Peak Mining Texas 2 use?

No water withdrawal figure for Peak Mining Texas 2 is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Peak Mining Texas 2, and how big is it?

Peak Mining is the operator on record. We hold 2 sites for that company across the registry. Capacity on record is 300 MW.

How to cite this page

SueDataCenters.org Data Center Registry, "Peak Mining Texas 2," updated August 5, 2026, https://suedatacenters.org/data-centers/peak-mining-texas-2-corpus-christi-tx.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/peak-mining-texas-2-corpus-christi-tx, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Peak Mining purchases a second 300MW data center location in Corpus Christi, Texas · PR Newswire / Northern Data Group · retrieved August 5, 2026
  2. 2.Tether-backed Northern Data sold bitcoin mining arm to companies run by Tether's own executives · The Block · retrieved August 5, 2026
  3. 3.Northern Data Announces Expiry of Option to Sell Corpus Christi Site (600MW available, 100MW used for mining) · Northern Data AG · retrieved August 5, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us