Lambda Kansas City AI Supercomputer

Kansas City, Platte County, Missouri · All 3 Lambda sites

Under constructionNo reception on recordAI confirmedRecord updated July 26, 2026

Lambda Kansas City AI Supercomputer is a data center under construction in Kansas City, Missouri (Platte County), operated by Lambda. The public record puts it at announced 2025, 100 MW planned, 16.9 acres, a reported $500 million investment.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Under construction

Operator
Lambda
Facility type
Data center, AI use confirmed
Location
Kansas City, Platte County, MO
Coordinates
39.3300, -94.7200
Power capacity
100 MW planned
Land
16.9 acres
Investment
$500 million
Announced
2025
Utility
Evergy
Power source
Grid
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Data Center Sales Tax Exemption Program, Missouri, 2025
Community reception
No reception on record
Source confidence
Confirmed by multiple independent sources or official documentation

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. 2025
    Under construction
    Lambda to build an AI factory at 11155 N. Airworld Dr (former Bank of America campus); launching early 2026 with 24 MW, scaling toward 100+ MW Source: Data Center Dynamics

Opposition and litigation at this site

Nothing on record as of July 26, 2026. No lawsuit, organized opposition, or contested hearing over Lambda Kansas City AI Supercomputer in Kansas City, Platte County, Missouri appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.

Power and water

Evergy electricity; Spire natural gas listed as a partner.

Public money on the record

ProgramAmountGranted byYear
Data Center Sales Tax Exemption ProgramNot establishedMissouri2025

Notes on the record

11155 N. Airworld Dr (former Bank of America campus, ~16.9 acres), Platte County near KCI airport. Launches early 2026 with 24 MW confirmed; >100 MW is a scale-up ceiling (planned figure). Distinct parcels from Google (Project Mica) and Meta's Kansas City sites. Eligible for the Missouri Data Center Sales Tax Exemption (eligibility only, no award amount confirmed; honest-zero). The >$500M figure is a press estimate (notes). Dedicated to a single unnamed AI customer under a multi-year agreement.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Cooling method and water use
  • Permanent jobs promised
  • How the community has received it
Which document closes each gap
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
How the community has received it
Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Our reporting on this site

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the Lambda Kansas City AI Supercomputer data center in Kansas City?

Nothing on record as of July 26, 2026. No lawsuit, organized opposition, or contested hearing over Lambda Kansas City AI Supercomputer in Kansas City, Platte County, Missouri appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

Has anyone filed a lawsuit over the Lambda Kansas City AI Supercomputer data center?

No lawsuit over Lambda Kansas City AI Supercomputer appears in the record we track as of July 26, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Lambda Kansas City AI Supercomputer use?

No water withdrawal figure for Lambda Kansas City AI Supercomputer is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Lambda Kansas City AI Supercomputer, and how big is it?

Lambda is the operator on record. We hold 3 sites for that company across the registry. Capacity on record is 100 MW. The site is recorded at 16.9 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Lambda Kansas City AI Supercomputer," updated July 26, 2026, https://suedatacenters.org/data-centers/lambda-kansas-city-mo.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/lambda-kansas-city-mo, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.AI cloud firm Lambda targets data center deployment in Kansas City, Missouri · Data Center Dynamics · retrieved July 7, 2026
  2. 2.Lambda to build a 100MW AI factory in Kansas City, MO · Lambda · retrieved July 7, 2026
  3. 3.Missouri Department of Economic Development, press release · retrieved July 25, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us