Google Project Mica is a data center under construction in Kansas City, Missouri (Clay County), operated by Google. The public record puts it at announced February 2026, 500 MW planned, 493 acres, a reported $10 billion investment.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Under construction
- Operator
- Facility type
- Data center, AI use likely
- Location
- 12701 N Arrowhead Trafficway, Kansas City, Clay County, MO
- Coordinates
- 39.2740, -94.6510
- Power capacity
- 500 MW planned
- Land
- 493 acres
- Investment
- $10 billion
- Announced
- February 2026
- Utility
- Evergy
- Power source
- Grid
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Port KC taxable revenue bond authorization, ceiling $10B (a financing authorization, NOT an abatement value: the city takes title so the property becomes tax-exempt, and the resulting relief is the separate property-tax abatement itemized below), Kansas City, MO, 2025 | 25-year 75% property tax abatement and 100% local/state sales tax exemption on construction materials, Missouri / City of Smithville, 2025
- Community reception
- No reception on record
- Source confidence
- Confirmed by multiple independent sources or official documentation
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- February 2026Under constructionGoogle confirms Project Mica; construction already underway; first building expected within 18 to 24 months Source: KSHB
- July 2025PermittedCity of Smithville and Port KC approve $10B campus; Google still unconfirmed publicly at this stage Source: KCTV5
- 2024ProposedGoogle acquires ~493 acres in KC Northland; site originally known as Rocky Branch Creek Technology Park (formerly a QTS/Diode Ventures plan)
Opposition and litigation at this site
Nothing on record as of August 24, 2026. No lawsuit, organized opposition, or contested hearing over Google Project Mica in Kansas City, Clay County, Missouri appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Power and water
Google is Evergy's first customer under its Large Load Power Tariff (approved Nov 2025 by Missouri PSC and Kansas CC); up to ~700 MW to be supplied from Nashua substation and onsite substations at full campus buildout
Public money on the record
| Program | Amount | Granted by | Year |
|---|---|---|---|
| Port KC taxable revenue bond authorization, ceiling $10B (a financing authorization, NOT an abatement value: the city takes title so the property becomes tax-exempt, and the resulting relief is the separate property-tax abatement itemized below) | Not established | Kansas City, MO | 2025 |
| 25-year 75% property tax abatement and 100% local/state sales tax exemption on construction materials | Not established | Missouri / City of Smithville | 2025 |
Notes on the record
Five hyperscale data center buildings on 493 acres, northeast of I-435 and US-169 in KC Northland (near Smithville, Clay County). Google committed $1.5M to Smithville School District and $250K to Northland Career Center. Coordinates are approximate for the site northeast of the I-435/US-169 interchange.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Cooling method and water use
- Permanent jobs promised
- How the community has received it
Which document closes each gap
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Meta Kansas City Northland · Kansas City · Meta3 mi · Operating · 750 MW · Supported
- Lambda Kansas City AI Supercomputer · Kansas City · Lambda5 mi · Under construction · 100 MW
- Project Kestrel · Kansas City · Shenandoah Computing LLC6 mi · Permitted
- Project Yardbird · Kansas City · PowerTransitions9 mi · Proposed · 200 MW
- Metrobloks Liberty Campus · Liberty · Metrobloks13 mi · Proposed · 150 MW · Mixed reception
- Patmos KC Star Building Campus · Kansas City · Patmos Hosting13 mi · Operating · 35 MW
- Project Red Wolf · Kansas City · Red Wolf DCD Properties LLC16 mi · Proposed · 600 MW · In litigation
- Nebius AI Factory (Independence) · Independence · Nebius Group21 mi · Under construction · 1.2 GW · In litigation
Questions people ask about this site
Is there opposition to the Google Project Mica data center in Kansas City?
Nothing on record as of August 24, 2026. No lawsuit, organized opposition, or contested hearing over Google Project Mica in Kansas City, Clay County, Missouri appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the Google Project Mica data center?
No lawsuit over Google Project Mica appears in the record we track as of August 24, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Google Project Mica use?
No water withdrawal figure for Google Project Mica is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Google Project Mica, and how big is it?
Google is the operator on record. We hold 53 sites for that company across the registry. Capacity on record is 500 MW. The site is recorded at 493 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Google Project Mica," updated August 24, 2026, https://suedatacenters.org/data-centers/google-project-mica-kc-northland-mo.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/google-project-mica-kc-northland-mo, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.$10B, 500-acre Google campus gets stamp of approval near Smithville · KCTV5 · retrieved July 6, 2026
- 2.Google announces construction underway for second data center campus in Kansas City · KSHB · retrieved July 6, 2026
- 3.Google confirms new data center development in Kansas City's Northland · KCTV5 · retrieved August 24, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us