CyrusOne SAT2-SAT4 (San Antonio) is an operating data center in San Antonio, Texas (Bexar County), operated by CyrusOne. The public record puts it at 36 MW operating.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Operating

Operator
CyrusOne
Facility type
Data center, AI use likely
Location
San Antonio, Bexar County, TX
Coordinates
29.4709, -98.6730
Power capacity
36 MW operating
Land
Not established from a public source
Investment
Not established from a public source
Announced
Not established from a public source
Utility
CPS Energy
Power source
Grid
Cooling
Closed loop
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
No reception on record
Source confidence
Reported by at least one credible outlet or filing

Opposition and litigation at this site

Nothing on record as of September 21, 2026. No lawsuit, organized opposition, or contested hearing over CyrusOne SAT2-SAT4 (San Antonio) in San Antonio, Bexar County, Texas appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.

A new status, a permit, a reception finding, or a lawsuit. Nothing else, ever.

Power and water

San Antonio campus (SAT1-SAT5) draws from CPS Energy substations. CPS Energy representatives attended the SAT5 groundbreaking as the utility partner, but no site-specific renewable PPA or dedicated generation project was found for SAT2-SAT4.

Notes on the record

OSM label 'San Antonio II' resolved to SAT2-SAT4 campus (9554 Westover Hills Blvd / 9655 Raba Dr). AI/HPC (likely): HPC spec: over 1,000 watts/sqft in designated areas.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • Land area
  • How the community has received it
Which document closes each gap
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Land area
The rezoning application, the plat, or the deed recorded with the county.
How the community has received it
Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Tell us about your situation

Living near CyrusOne SAT2-SAT4 (San Antonio)?

Tell us the basics. Where a participating attorney in your state is available, we may share your information with them with your consent. Free, no obligation, and no guarantee anyone will contact you.

Questions people ask about this site

Is there opposition to the CyrusOne SAT2-SAT4 (San Antonio) data center in San Antonio?

Nothing on record as of September 21, 2026. No lawsuit, organized opposition, or contested hearing over CyrusOne SAT2-SAT4 (San Antonio) in San Antonio, Bexar County, Texas appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

Has anyone filed a lawsuit over the CyrusOne SAT2-SAT4 (San Antonio) data center?

No lawsuit over CyrusOne SAT2-SAT4 (San Antonio) appears in the record we track as of September 21, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does CyrusOne SAT2-SAT4 (San Antonio) use?

No water withdrawal figure for CyrusOne SAT2-SAT4 (San Antonio) is on record here. Cooling is recorded as closed_loop, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.

Who operates CyrusOne SAT2-SAT4 (San Antonio), and how big is it?

CyrusOne is the operator on record. We hold 35 sites for that company across the registry. Capacity on record is 36 MW.

How to cite this page

SueDataCenters.org Data Center Registry, "CyrusOne SAT2-SAT4 (San Antonio)," updated September 21, 2026, https://suedatacenters.org/data-centers/cyrusone-sat2-sat4-san-antonio-tx.

Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/cyrusone-sat2-sat4-san-antonio-tx, retrieved October 29, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.CyrusOne facility directory · CyrusOne · retrieved September 21, 2026
  2. 2.OpenStreetMap way/509611438 · OpenStreetMap · retrieved July 22, 2026
  3. 3.CyrusOne AI/HPC, HPC spec: over 1,000 watts/sqft in designated areas · datacentermap.com · retrieved July 23, 2026
  4. 4.CyrusOne breaks ground on fifth San Antonio campus (CPS Energy attendance) · retrieved July 24, 2026

Is a data center disrupting your home?

Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.

  • Tell us about your situation
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us