Core Scientific Auburn Data Center (AUBix) is a data center under construction in Auburn, Alabama (Lee County), operated by Core Scientific. The public record puts it at 16 MW planned, a reported $400 million investment. It has documented public support and no documented opposition.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Under construction

Operator
Core Scientific
Facility type
Data center, AI use likely
Location
Auburn, Lee County, AL
Coordinates
32.6089, -85.4879 (approximate)
Power capacity
16 MW planned
Land
Not established from a public source
Investment
$400 million
Announced
Not established from a public source
Utility
Not established from a public source
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
20 permanent
Public subsidy
Not established from a public source
Community reception
Supported
Source confidence
Confirmed by multiple independent sources or official documentation

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. February 19, 2025
    Under construction
    Core Scientific leased the existing AUBix facility at 1571 W Samford Ave and is bringing it online in phases; first ~16MW targeted, full ~$400M build ongoing as of the Feb 2025 announcement. Source: Core Scientific IR (BusinessWire-syndicated)

Opposition and litigation at this site

Not that we can document. Local officials or residents have expressed public support for Core Scientific Auburn Data Center (AUBix) in Auburn, Lee County, Alabama, and no opposition, petition, or lawsuit appears in the sources this registry tracks as of September 9, 2026. Core Scientific retained the facility's 11 existing full-time employees and plans to grow to 20+; local officials (Auburn city/state leaders) publicly supportive; projected ~$1.5M/yr local tax revenue.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: supported means local officials or residents have expressed public support and no opposition is documented.

Core Scientific retained the facility's 11 existing full-time employees and plans to grow to 20+; local officials (Auburn city/state leaders) publicly supportive; projected ~$1.5M/yr local tax revenue.

Source: DataCenterMap

Notes on the record

STATUS RE-CHECK, NO CHANGE APPLIED, BUT FLAGGED. Two sources fetched this run point toward the site already serving customers - Core Scientific sells it as a current product, and the February 2026 $55M permit is framed as an EXPANSION of an existing facility rather than a first build. Neither states outright that the data center is energized and serving load, and this record is a pre-existing AUBix building that Core Scientific leased, so the boundary between the incumbent facility and Core Scientific's fit-out is genuinely unclear. I did not promote under_construction to operational on marketing tense alone. Worth a targeted check of Core Scientific's 10-Q or an earnings call transcript, which I did not reach this run.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Land area
  • Which utility serves it
Which document closes each gap
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Land area
The rezoning application, the plat, or the deed recorded with the county.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Questions people ask about this site

Is there opposition to the Core Scientific Auburn Data Center (AUBix) in Auburn?

Not that we can document. Local officials or residents have expressed public support for Core Scientific Auburn Data Center (AUBix) in Auburn, Lee County, Alabama, and no opposition, petition, or lawsuit appears in the sources this registry tracks as of September 9, 2026. Core Scientific retained the facility's 11 existing full-time employees and plans to grow to 20+; local officials (Auburn city/state leaders) publicly supportive; projected ~$1.5M/yr local tax revenue.

Has anyone filed a lawsuit over the Core Scientific Auburn Data Center (AUBix)?

No lawsuit over Core Scientific Auburn Data Center (AUBix) appears in the record we track as of September 9, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Core Scientific Auburn Data Center (AUBix) use?

No water withdrawal figure for Core Scientific Auburn Data Center (AUBix) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Core Scientific Auburn Data Center (AUBix), and how big is it?

Core Scientific is the operator on record. We hold 10 sites for that company across the registry. Capacity on record is 16 MW.

How to cite this page

SueDataCenters.org Data Center Registry, "Core Scientific Auburn Data Center (AUBix)," updated September 9, 2026, https://suedatacenters.org/data-centers/core-scientific-auburn-al.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/core-scientific-auburn-al, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Core Scientific Announces Expansion into Auburn, Alabama with New High-Performance Computing Facility · Core Scientific IR (BusinessWire-syndicated) · retrieved August 3, 2026
  2. 2.Core Scientific bringing high-performance computing operation to Auburn, Alabama · Alabama News Center · retrieved August 3, 2026
  3. 3.AUBix Data Center in Auburn | 1571 W Samford Ave (3 MW) · DataCenterMap · retrieved August 3, 2026
  4. 4.Alabama Data Center | High-Density in Auburn · Core Scientific · retrieved September 9, 2026
  5. 5.Core Scientific bringing high-performance computing operation to Auburn · Made in Alabama (Alabama Dept. of Commerce) · retrieved September 9, 2026
  6. 6.Data center expansion and manufacturing project expected to bring hundreds of jobs to Lee County · WTVM · retrieved September 9, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us