Stopping a Project
Two Records, Ten Days Apart: What Armstrong County's Own Documents Say About the Data Center Near Claude, Texas
Google lists Armstrong County, Texas as in development with no figures published. The county's own executed tax abatement is with GN DC1, LLC, signed from a crusoe.ai address, for a campus its site plan calls Project Llano at 10001 Lima Road outside Claude. What the two agreements, the reinvestment zone, the federal permits, the groundwater district and the TxDOT crash tables establish, what they leave out, and why the relationship between the two records is not knowable from either.
Key Takeaways
- Two records sit ten days apart and nothing in the public file connects them. Armstrong County's Commissioners Court approved an amended, restated and consolidated Chapter 312 tax abatement agreement with GN DC1, LLC on October 14, 2025, and the electronic signature record on the county's posted copy is dated November 3 and 4, 2025 from an address at crusoe.ai. Google announced Armstrong County as a data center location on November 14, 2025. Whether they are the same project, a tenancy in it, or separate parcels is not established by anything either party has published.
- Neither of the county's two posted abatement agreements contains the word water, a megawatt figure, a cooling method, an air emissions term, or any environmental monitoring requirement. The only environmental provision is one sentence of site maintenance: noise, light and dust are to be minimal off the site, and noise at the project site boundaries shall not exceed 80 dBA during normal commercial operations. No measurement point, no measurement method, no day and night distinction. By contrast, the county's own wind abatement file shows a Chapter 312 project that had to be operating above 100 MW by a fixed date.
- There are two abatements, not one. The county's tax abatement page labels them Crusoe DC1 LLC A and Crusoe DC1 LLC B. The first grants a 100 percent, ten year abatement of all county taxes on each phase with an annual payment in lieu of taxes of $1,360,375. The second grants a further ten year abatement on property first placed on the site after the first abatement period ends, with a payment in lieu of taxes of 15 percent of what the county taxes would have been. Up to eight phases are authorized, four are anticipated, and each is expected to require about $1,000,000,000 of initial capital investment.
- The jobs commitment is 19 full time jobs per phase, and it does not begin until the third calendar year of that phase's abatement period. Measured against the anticipated $1,000,000,000 per phase, that is about $52.6 million of capital investment per required job. Armstrong County's entire 2025 certified taxable value for the general fund was $350,494,230, so one phase at the anticipated figure would be roughly 2.9 times the whole county tax roll and four phases roughly 11.4 times it.
- The federal record is where the site becomes specific. EPA's Clean Water Act database lists construction stormwater coverage in Armstrong County for PROJECT LLANO and WEST LLANO at 10001 Lima Road and for GOODNIGHT POWER PLANT PROJECT at 9921 Lima Road, the last carrying NAICS code 518210, Computing Infrastructure Providers, Data Processing, Web Hosting, and Related Services. All three sit in the Town of Claude to Mulberry Creek watershed, about seven miles from the center of Claude, and all three expire March 4, 2028.
- The traffic is the one impact residents can already measure, and two records now describe it. TxDOT counted 52 crashes in Armstrong County in 2023, 44 in 2024 and 71 in 2025, with commercial vehicle involved crashes of 18, 18 and 32, a 61 percent rise in total crashes and a 78 percent rise in truck involved crashes in one year. For 2026, which TxDOT will not publish until about June 2027, Armstrong County Sheriff Melissa Anderson told NewsChannel 10 in August that wrecks had gone from about two to three a month to as many as two to three a day.
- The county's own document trail goes quiet at the moment the project accelerates. On the Commissioners Court page, every month of 2026 and every month from August 2025 forward carries the same list of document headings, agenda, minutes, sheriff's report, emergency manager report, and beneath each heading there is no file. The last month with posted documents is July 2025. Records exist under Texas law whether or not a website shows them, and they are obtainable by written request.
In this article
Google's public list of data center locations shows Armstrong County, Texas, marked in development, with no investment figure, no workforce number, no timeline, no water figure and no power figure. Armstrong County's own website, meanwhile, posts two executed Chapter 312 property tax abatement agreements for a data center campus, and the counterparty is not Google. It is GN DC1, LLC, a Delaware limited liability company at a Denver address, and the notice provisions in the agreement run to Crusoe Energy Systems, LLC. The county's tax abatement page labels the two files Crusoe DC1 LLC A and Crusoe DC1 LLC B. The site plan attached as an exhibit is titled Project Llano, Building 1 and 2, 10001 Lima Road, Claude, TX 79019. We read both agreements in full, including the exhibits, and pulled the reinvestment zone resolutions, the county's abatement guidelines, the posted road exhibits, the EPA drinking water and Clean Water Act records, the groundwater district's rules, the U.S. Energy Information Administration's generator inventory, the Census gazetteer and the Texas Department of Transportation crash tables. This is what those records establish, what they do not, and the single question the public record cannot answer: how, if at all, the Google announcement of November 14, 2025 relates to the abatement the county signed ten days earlier. Every construction impact described on this page traces to records naming GN DC1, LLC or to the site at Lima Road. None of it is attributed to Google, because no public record we retrieved supports that attribution.
Two records, ten days apart, and the connection nobody has documented
Here is the first record. On November 12, 2024 the Armstrong County Commissioners Court held a public hearing, created Armstrong County Reinvestment Zone 8, and approved a Phase 1 and a Phase 2 tax abatement agreement with GN DC1, LLC. On June 9, 2025 it amended the zone, adding 100 acres out of the northwest portion of Survey 318, Block B4, and rewriting the zone's stated purpose to cover "renewable and wind generated power generation and behind the meter uses for such power, to include data centers." On July 14, 2025 it approved first amendments to both agreements. On October 14, 2025 it approved and authorized execution of the amended, restated and consolidated agreement that the county now posts. The electronic contract record on the last page of that posted PDF gives a contract title of "Real Estate or Property Agreement (Armstrong County, Texas and Crusoe)" and a signature timestamp of November 4, 2025 at 12:11 a.m. UTC, from an email address at the crusoe.ai domain. The signature block on page 25 is dated November 3, 2025.
Here is the second record. On November 14, 2025, Google announced a $40 billion Texas data center investment naming Armstrong County and Haskell County. As the Texas Tribune reported it that day, the announcement covered one data center in Armstrong County and two in Haskell, with statewide workforce commitments and a solar and battery pairing described for one of the Haskell sites. No site specific investment figure, workforce figure or timeline for Armstrong County appeared in that coverage, and none appears on Google's own locations page, which lists Armstrong County alongside Haskell County, Pampa and Wilbarger County as in development with no accompanying detail. No developer or partner was named.
Nothing in either record refers to the other. Google's locations page does not name GN DC1, LLC or Crusoe. Crusoe's own website, which we checked, describes Texas campuses at Abilene and a joint venture at Childress and makes no mention of Goodnight, Armstrong County, or Claude. The county's agreements never mention Google. Trade press has used the name Goodnight Campus for the Armstrong County project; the county's own exhibit calls it Llano, and the federal permit file calls it Project Llano.
The agreement itself is worth reading on this point, because it is built for exactly this ambiguity. Section IX contemplates three ownership structures: GN DC1 building, owning and operating everything; GN DC1 and affiliates owning the buildings while "one or more third parties or Affiliates are lessees of the Building Improvements and equip, own and operate Data Center Equipment Improvements located within the Building Improvements"; or "any other structure that segregates the ownership and operation of the Building Improvements and/or the Data Center Improvements among multiple owners." The parties' stated intent is that the owner "shall have flexibility and a unilateral right to select and implement an ownership and operation structure of its choosing."
Assignment to an affiliate or to what the agreement calls an Other Owner, a defined term that includes a lessee, sublessee or tenant, requires only notice to the county, not consent. Assignment to anyone else requires the county's written consent, which "shall not be unreasonably withheld." Exhibit F is a blank Form of Synthetic Lease Assignment Agreement. In other words, the contract on file is drafted so that the operator on the county's tax records and the company whose servers run in the buildings need not be the same entity, and so that a change of that kind would reach the county as a notice rather than a hearing. That is a structural fact about the document, not an allegation about anyone's plans.
What the county actually signed, in figures
Reinvestment Zone 8 is large. The legal description attached to the November 12, 2024 resolution runs 45 tracts across Blocks 1, 4, B4, B6, C, E3, E4, W, Z-6, Z-7 and Z-8, and the acreages in it sum to 42,562.79 acres. The June 9, 2025 amendment adds 100 acres. That is about 42,663 acres, or 66.7 square miles. The Census Bureau's 2024 gazetteer puts Armstrong County's land area at 909.123 square miles, so the zone covers roughly 7.3 percent of the county. The city of Claude covers 1.716 square miles, so the zone is about 39 times the land area of the county seat.
The project site inside it is smaller and specific. Exhibit E, headed "Possible Site Plan," is a Kimley-Horn drawing titled Project Llano, Building 1 and 2, at 10001 Lima Road, Claude, TX 79019, showing a project site boundary across Section 284 at 652.83 acres and Section 283 at 384.77 acres, plus a 100 acre expanded utility easement. The two sections total 1,037.6 acres, about 1.62 square miles, which is roughly 94 percent of the land area of the city of Claude. The drawing's title block carries the consultant and contractor names Crusoe, AlfaTech, HKS, Rosendin, Brandt, Kimley-Horn and BW Design Group.
The commercial terms are these.
| Term | What the agreements say |
|---|---|
| Owner | GN DC1, LLC, a Delaware limited liability company, 255 Filmore St., Denver, CO 80206. Notices to Crusoe Energy Systems, LLC at the same address |
| Phases | Up to eight, four currently anticipated, each expected to require about $1,000,000,000 of initial capital investment in building and data center equipment improvements |
| Abatement | 100 percent of all county property taxes, M&O, I&S, road and other, on eligible property in each phase, for ten calendar years beginning the year after commercial operations. Base year 2024 |
| Second abatement | A separate agreement grants a further ten year, 100 percent abatement on property first placed on a phase area after the first abatement period ends |
| Payment in lieu of taxes | $1,360,375 per year per phase under the first agreement. Under the second agreement, 15 percent of the county taxes that would otherwise have been imposed |
| Phase 1 deadline | Commercial operations by December 31, 2027, with five unilateral one year extensions available: the first free, then $100,000, $200,000, $350,000 and $500,000, carrying the deadline to December 31, 2032 |
| Jobs | 19 full time jobs multiplied by the number of phases in abatement, counted only from the third calendar year of each phase's abatement period, measured campus wide, and satisfiable by the owner, its tenants, or their contractors and affiliates |
| Buildings stay | Each data center building remains in place at least 15 calendar years after that phase's commercial operation date, with liquidated damages if it is removed |
| Noise | Noise at the project site boundaries shall not exceed 80 dBA during normal commercial operations |
| Roads | Owner repairs damage beyond ordinary wear and tear and bears the cost of any required upgrade. The clause is void once a separate Agreement for Road Use, Repair and Improvement is executed |
| Safety training | Annual safety training for county emergency services personnel at the owner's cost, plus a map of project locations given to responders at the start of construction |
Set the investment figure against the county. The Armstrong County Appraisal District certified the county's 2025 taxable value for the general fund at $350,494,230. One phase at the anticipated $1,000,000,000 would be about 2.9 times that entire roll. Four phases would be about 11.4 times it. Against the 19 jobs a phase must produce, the anticipated capital works out to roughly $52.6 million per required job, and no job is counted until the third calendar year of that phase's ten year abatement. Four phases running would produce $5,441,500 a year in payments in lieu of taxes, and $13,603,750 over each phase's ten year term.
The words that are not in either agreement
We ran both posted agreements through optical character recognition at 350 dots per inch, because every page is a scanned image with no text layer, and then searched them. Here is what is absent from both.
- Water. The word does not appear in either agreement except inside the force majeure list, as "high water washouts." There is no water supply commitment, no source, no volume, no cooling method, no reuse or replenishment obligation, no wastewater provision and no baseline testing requirement.
- Power. There is no megawatt or gigawatt figure anywhere in either document. The definitions describe power delivery systems, power generation equipment and standby generators as abatable improvements, and a Cooperation section states that the reinvestment zone "is in proximity to a major ERCOT point of interconnection," but the campus's own load is never stated.
- Air. No emissions term, no limit on generator hours, no restriction on running generators during grid peaks. Compare Barber County, Kansas, where the development agreement bars operating generators to reduce electrical usage during peak hours.
- Environmental monitoring. No baseline or periodic soil, water or wastewater testing, and no obligation to give the county any environmental results. The only representation is that the project will not be built without obtaining necessary permits.
- An estimate of future taxes. Armstrong County's own Guidelines and Criteria, adopted August 26, 2024, require that any tax abatement agreement include "an estimate of the amount of ad valorem property taxes to be paid to Armstrong County after expiration of the abatement agreement." The word estimate does not appear in either agreement. Section XIV resolves this: to the extent the agreement modifies any requirement in the Guidelines, "those Guidelines are deemed amended for purposes of this Agreement only," and the agreement controls.
The county's Guidelines are worth quoting on their own terms, because they set a standard the file does not then measure anything against. They state that it is "the express intent of the Armstrong County Commissioners Court to promote economic development, but not at the expense of the County's natural resources or services provided to the general public," and that "no application submitted under the following schedule deemed to have a substantially adverse effect on natural resources in the County or on County infrastructure (including roads and bridges) will be approved, unless the applicant can demonstrate just cause for such an exception." Among the criteria the court is directed to weigh are "any costs to be incurred by Armstrong County, if any, to provide facilities or services directly resulting from the new improvements," "the impact upon County infrastructure including roads, bridges and the use of County services," "the impact upon depletion of natural resources of the County," and "the potential impact upon neighboring landowners." No analysis of any of those four is posted with the agreements.
One further timing point, offered as a records observation and nothing more. Texas Tax Code Section 312.002 provides that abatement guidelines and criteria "are effective for two years from the date adopted," may be amended or repealed during that period only by a three fourths vote, and must be posted on the taxing unit's website. Armstrong County's posted Guidelines were adopted August 26, 2024 and say on their face that they "remain in force for two (2) years." As of September 3, 2026 the county's website posts no reauthorized or amended version. It also posts no 2026 commissioners court minutes at all, so whether the court has reauthorized them cannot be determined from the website either way.
What the federal record shows about the site itself
The county file names a project. The federal file gives it coordinates. EPA's Enforcement and Compliance History Online returns 24 Clean Water Act permitted facilities in Armstrong County, FIPS 48011. Four of them are the story.
| Facility name in EPA records | Permit | Address | Classification | Coordinates |
|---|---|---|---|---|
| PROJECT LLANO | TXR1598UW, construction stormwater, effective, expires 03/04/2028 | 10001 Lima Road, Claude | SIC 1541 industrial buildings and warehouses; SIC 1629 heavy construction | 35.017015, -101.312006 |
| WEST LLANO | TXR1568YF, construction stormwater, effective, expires 03/04/2028 | 10001 Lima Rd, Claude | SIC 1541; SIC 1629 | 35.02433, -101.316449 |
| GOODNIGHT POWER PLANT PROJECT | TXR1529XT, construction stormwater, effective, expires 03/04/2028 | 9921 Lima Road, Claude | SIC 4911 electric services; NAICS 518210, computing infrastructure providers, data processing, web hosting and related services | 35.016961, -101.319614 |
| GOODNIGHT I WIND SUBSTATION EXPANSION | TXR1535VX, construction stormwater, effective, expires 03/04/2028 | 10001 Lima Rd, Claude | SIC 1629 heavy construction | 35.014633, -101.312258 |
Every one of them is assigned to the same hydrologic unit, coded 111201030505 and named, in EPA's own watershed vocabulary, "Town of Claude-Mulberry Creek." The receiving water listed for Project Llano and West Llano is Mulberry Creek. Measured from the Census Bureau's coordinates for the city of Claude, the Project Llano permit point is about 6.9 miles away and the Goodnight Power Plant Project point about 6.7 miles. Two points are worth making carefully. A hydrologic unit is a surface drainage boundary, not a groundwater boundary, so shared watershed does not by itself say anything about wells. And a construction stormwater general permit is a routine authorization for disturbing land, not a finding about anything. What it does establish is that grading is authorized and under way at those coordinates, under those industrial classifications, through March 2028.
Now the drinking water. EPA's Safe Drinking Water Information System lists exactly three public water systems in Armstrong County, and all three run on groundwater.
| System | PWSID | Population served | Connections | Source |
|---|---|---|---|---|
| Claude Municipal Water System | TX0060001 | 1,300 | 700 | Groundwater. Seven active primary wells, on SH 207 south of town, at Byrd and CR 14, at Finney, off Golf Road and CR 14, and two off Hotel Road and CR 16 |
| Washburn Community Water Supply Corporation | TX0060002 | 150 | 59 | Groundwater. One primary well east of town off US 287 and one emergency well in the center of town |
| Hidden Falls Ranch Youth Camp | TX0060003 | Not a community system | Not applicable | Groundwater |
That is the entire public drinking water infrastructure of the county: one town system with 700 connections, one water supply corporation with 59, and a camp. There is no surface water supply and no regional pipeline.
Part of Armstrong County sits inside the Panhandle Groundwater Conservation District, which covers all of Carson, Donley, Gray, Roberts and Wheeler counties and parts of Armstrong, Hutchinson and Potter. Inside the district, the rules adopted July 9, 2026 cap an operating permit's total annual production at "the total number of acres of land included in the application x 1 acre-foot per year for all aquifers combined," and the district's management standard, the 50/50 Standard, is meant to leave at least half the current volume of the Ogallala after 50 years. The district's 2024 to 2029 management plan reports modeled available groundwater for the Armstrong County portion of the district at 56,940 acre feet a year in 2020 for the Ogallala, declining to 27,137 by 2080, and 5,313 acre feet a year for the Dockum, rising to 8,914. Reported current use in the Armstrong County portion totals 6,268 acre feet a year: 5,458 irrigation, 546 livestock, 264 municipal, and zero for manufacturing, mining and steam electric power. For scale, 264 acre feet is about 86 million gallons a year, roughly what a single mid sized data center cooling tower can consume in a matter of months. We could not determine from the records we retrieved whether the Lima Road site falls inside or outside the district's Armstrong County boundary, and that single question changes whether a large new well there would need a district permit at all.
Because the number is unpublished, the useful exercise is a conversion rather than an estimate. Using the Energy Information Administration's Texas electricity profile for 2024, which reports 168,317 megawatts of net summer capacity and 566,502,688 megawatthours of net generation, and EIA's figure of 10,791 kilowatthours a year for the average U.S. residential utility customer, here is what various loads would mean. These are arithmetic conversions of hypothetical loads, not claims about this project.
| If the campus drew | Annual energy at full utilization | Equivalent U.S. households | Share of Texas net summer capacity | Share of Texas 2024 net generation |
|---|---|---|---|---|
| 100 MW | 0.88 terawatthours | About 81,000 | About 0.06 percent | About 0.15 percent |
| 250 MW | 2.19 terawatthours | About 203,000 | About 0.15 percent | About 0.39 percent |
| 500 MW | 4.38 terawatthours | About 406,000 | About 0.30 percent | About 0.77 percent |
| 1,000 MW | 8.76 terawatthours | About 812,000 | About 0.59 percent | About 1.55 percent |
| 2,000 MW | 17.52 terawatthours | About 1.62 million | About 1.19 percent | About 3.09 percent |
One more figure for context, and it is the county's own framing. Armstrong County's abatement guidelines make a data center eligible for abatement only as a "behind the meter" use of renewable power generated or stored under the same guidelines, and the amended reinvestment zone resolution designates Zone 8 for "renewable and wind generated power generation and behind the meter uses for such power, to include data centers." All 531 megawatts of wind nameplate capacity currently operating or under construction in the county, running at a generous 40 percent capacity factor, would produce about 1.86 terawatthours a year. Our guide to who pays for data center power covers what happens when a load like this arrives on a grid, and how the cost lands on other customers.
The traffic is the part residents can already measure
Everything above is prospective. The roads are not. The Texas Department of Transportation publishes crashes and injuries by county, and commercial motor vehicle involved crashes by county, and the three most recent published years for Armstrong County read like this.
| Armstrong County | 2023 | 2024 | 2025 |
|---|---|---|---|
| Total crashes | 52 | 44 | 71 |
| Fatal crashes | 3 | 2 | 3 |
| Fatalities | 3 | 2 | 3 |
| Suspected serious injury crashes | 6 | 9 | 3 |
| Commercial vehicle involved crashes | 18 | 18 | 32 |
| Commercial vehicle share of all crashes | 35 percent | 41 percent | 45 percent |
Total crashes rose 61 percent from 2024 to 2025. Truck involved crashes rose 78 percent. In the same 2025 tables, Texas as a whole recorded 538,860 crashes and 38,533 commercial vehicle involved crashes, a statewide share of 7.2 percent. Armstrong County's 2025 share was 45 percent. These are counts in a county of about 1,809 people, so year to year swings are expected and a single year is not a trend. The 2026 tables, which would cover the year residents describe as the difficult one, are not published and will not be until roughly June 2027.
The county's own posted documents show the road work that anticipated this. In May 2025 the Commissioners Court packet included two exhibits. One, dated April 14, 2025 and titled "Lima Rd & Hwy 207 Roadway Adjustments," lists Lima Road changes: "widen road to ~50 ft. (2 lanes each way, East & West) from Hwy to east termination point," pave it in asphalt, build to "TXDOT specs to accommodate all construction traffic, equipment deliveries, etc.," level it and add water swale drainage, and "create semi-truck turn-around on Lima Rd @ Hwy 207 near intersection to redirect traffic immediately back to Hwy 207." It lists three Highway 207 changes: a turn lane onto Lima Road, an acceleration lane for right turns from Lima Road onto the highway, and a transitioned corner "for semi-truck right turn onto Hwy." The second exhibit, a Kimley-Horn TxDOT access drawing dated April 30, 2025, shows a 700 foot left turn lane.
Set against that, the county's 2025 Annual Road Report, generated April 4, 2025 and posted with the April packet, runs ten pages listing every county road by precinct, including Lima Road in precincts 2, 3 and 4. It has columns for road condition ranked one to five, cause of degradation, culverts needing repair or replacement, bridges needing repair or replacement, control devices needing repair, new roads needed, average maintenance cost for the coming year, and extra cost of identified repairs. Every one of those cells is blank on every page.
What the county's own officials have said on the record. NewsChannel 10 in Amarillo has reported the consequences repeatedly, quoting named public officials, and their accounts are the clearest measure of what construction at this scale does to a county of about 1,800 people.
Armstrong County Sheriff Melissa Anderson told the station on August 13, 2026 that thousands of workers travel to and from the construction site Monday through Friday, with the heaviest traffic between 3 a.m. and 6 a.m. and again between 3 p.m. and 6 p.m. She said vehicle wrecks in the county had risen from about two to three a month to as many as two to three a day, most of them minor. She repeated the same figures to the station on August 21. That is the single most important number in this piece, and it comes from the county's chief law enforcement officer rather than from an estimate of ours.
It also explains a gap in the state data. The TxDOT county tables above end with 2025 and show 71 crashes for that year, roughly six a month. The sheriff is describing 2026, the first full year of heavy construction, and TxDOT will not publish the 2026 county table until about June 2027. Both accounts can be true, and the state record simply has not caught up.
The response is documented too. Sheriff Anderson said the data center signed a contract to fund an additional deputy for her department for two years, that a fifth deputy would be added in mid September, and that a sixth was under discussion in budget season. Her office asked for volunteers to help with school crossings. TxDOT public information officer Jason Britsch said the agency reduced speed limits on State Highway 207 and FM 1151, funded radar trailers, repainted striping, and worked with the developer to add a turn only lane at the construction entrance. Claude ISD Superintendent Brent Kirkland said a new school zone was established on FM 1151, with classes beginning August 20.
Emergency response is the strain that gets least attention. On August 28, 2026 the station reported that Armstrong County's three volunteer fire departments, in Washburn, Claude and Wayside, have 18 members between them and are recruiting. County Fire Chief Jerry Johnson said the county has seen an increase in population and construction, that the increase can lead to more accidents and other situations the county does not have the manpower to handle, and that the decline in volunteers has been under way for years. A county with 18 volunteer firefighters is absorbing thousands of daily commuters on two lane roads.
The economic side is also on the record. On June 10, 2026 the station reported that construction workers had filled local short term rentals outside Amarillo, pushing other visitors into hotels and lifting hotel and motel tax revenue by 16 percent that year, and that Amarillo National Bank expected data center construction across the Panhandle to continue for about two more years. Officials at the data center have told the county that construction could continue for up to two years.
Two things in the abatement bear directly on all of this, and both cut toward mitigation. Section XVII makes the owner responsible for repairing damage beyond ordinary wear and tear to county roads, culverts and bridges, for leaving them in equal or better condition after construction, and for the entire cost of any required upgrade, with the county responsible only for normal routine maintenance afterward. And the safety training section requires the owner to provide annual training for county emergency management, emergency medical, law enforcement, dispatch and volunteer fire personnel at its own cost, and to give responders a map of project locations at the start of construction so that "location information may be quickly and accurately conveyed."
The road clause carries an important condition. It "shall become void and shall have no further effect upon the execution of a separate Agreement for Road Use, Repair and Improvement by and between Owner and County relating to the Project." No such separate road use agreement is posted anywhere on the county's website. Whether one exists, and what it says, is the single most consequential open document for anyone living on a haul route. It is also, unlike most of what is missing here, a document a resident can simply ask the county for.
The record that went quiet, and what would answer the rest
Armstrong County's Commissioners Court page is well organized. It has an accordion for each year back to 2021 and, inside each year, one for each month, and inside each month a list of the county's standard document set: agenda, activity building report, AgriLife reports, commissioners court minutes, county clerk report, district clerk report, elections administrator report, emergency manager report, justice of the peace report, JP OCA report, sheriff's report, tax assessor collector report and two treasurer reports. For 2023 and 2024 those headings carry files.
For 2025, January through July carry files. August, September, October, November and December of 2025 carry the same headings with no files beneath them. Every month of 2026, January through December, carries the same headings with no files beneath them. The county's public notices calendar for September 2026 is empty. The last commissioners court document posted to the county's website is from the July 2025 packet.
That is a description of a website, not an accusation. Texas law requires agendas to be posted and minutes to be kept regardless of what a county's website shows, and small county offices lose the person who does the uploading all the time. But the practical effect is real: the period in which this project moved from a pair of phase agreements to a consolidated eight phase abatement, in which construction began, in which crashes rose 61 percent and in which the county's abatement guidelines reached their two year expiry, is the period for which no agenda, no minute, no sheriff's report, no emergency manager report and no road report is on the county website. The county's tax abatement documents are still posted, and they are the reason this article could be written at all.
Eight records would answer nearly everything this page could not, and every one of them is obtainable from a county or state office by written request.
- The separate Agreement for Road Use, Repair and Improvement, if it has been executed, plus the pre-construction road inventory and any security posted with it.
- Commissioners court agendas and minutes from August 2025 forward, which would show every action taken on this project since the consolidated agreement.
- The monthly Sheriff's Reports and Emergency Manager Reports for 2026, which are where call volumes, wreck responses and mutual aid actually appear before TxDOT publishes anything.
- Exhibits B-1 through B-4, the survey depictions and legal descriptions of the Phase 1 through Phase 4 abatement areas, which the agreement requires the owner to deliver within one year of the effective date, so on or about November 2026.
- Any recorded assignment of either abatement in the Armstrong County real property records, and any Annual Compliance Certificate, the first of which is due March 31 following the first certificate. That is the document class most likely to name an Other Owner.
- The tax abatement application GN DC1, LLC filed, which the county's guidelines require to include a time schedule, estimated taxable values and financial information, and which Texas Tax Code Section 312.003 makes confidential only until the agreement is executed.
- Panhandle Groundwater Conservation District records: whether the site is inside the district, and any drilling or operating permit application tied to it.
- Any reauthorization of the county's abatement guidelines after August 26, 2026, and the TCEQ notices of intent behind construction stormwater permits TXR1598UW, TXR1568YF and TXR1529XT, which name the operator and the acreage disturbed.
The honest summary is that Armstrong County obtained real things in these contracts and left out real things. It obtained a 15 year building in place covenant with liquidated damages, full recapture rights, annual sworn compliance certification, inspection access, an indemnity, a local hiring and spending plan, annual safety training for its responders, and road repair obligations that run to the owner rather than the taxpayers. It did not obtain a water commitment, a power figure, a cooling method, an emissions term, an environmental testing requirement, a defensible noise standard, or the estimate of post abatement tax revenue its own guidelines call for. Both halves of that are true, and neither cancels the other.
If you live near this site, the useful work right now is documentary and cheap. Get a water test from a certified laboratory, dated before the buildings operate, covering at minimum nitrates, chloride, sulfate, total dissolved solids and bacteria, and keep the report. Pull your own well's state well report. Photograph and date your property, your wellhead, your fence lines and the road surface in front of your place. If sound becomes an issue, take readings at your property line with the date, time, weather and instrument recorded, because the 80 dBA term in the county's contract has no measurement method and someone will have to supply one. Our evidence guide explains what documentation actually gets used later, and our guide to fighting a proposed data center covers the leverage points that exist in a county with no zoning.
Nothing on this page describes harm that has been adjudicated, because nothing has been. No lawsuit has been filed over this project in anything we retrieved. In Texas, where counties generally lack zoning authority in unincorporated areas, neighbors of industrial facilities have gone straight to common law: the pending Granbury cases against a crypto mining operation were brought as private nuisance claims seeking an injunction, with negligence and property damage theories alongside. Those claims carry filing deadlines, commonly a statute of limitations of two to four years in Texas depending on the claim, and an attorney will confirm which applies to yours. Our Texas page covers the state's litigation record, and if a facility is already affecting your home, our free case review connects you with an independent attorney in our network who handles these matters in Texas, at no cost and with no obligation.
Frequently asked questions
Who is building the data center in Armstrong County, Texas?
The only operator on Armstrong County's tax records is GN DC1, LLC, a Delaware limited liability company with a Denver address, whose notice provisions run to Crusoe Energy Systems, LLC. The county's tax abatement page labels its two posted agreements Crusoe DC1 LLC A and Crusoe DC1 LLC B, and the electronic signature record on the posted agreement is from a crusoe.ai email address dated November 3 and 4, 2025. Google separately announced Armstrong County as a data center location on November 14, 2025, but Google is not named in either county agreement and no public record we retrieved establishes a relationship between the two.
Is Google building the data center near Claude, Texas?
That is not established by the public record. Google's own data center locations page lists Armstrong County, Texas as in development with no investment figure, workforce number, timeline, water figure or power figure, and names no partner. The county's executed abatements name GN DC1, LLC. Whether Google's Armstrong County project is the same campus as the Lima Road site, a tenancy inside it, or a separate parcel cannot be determined from anything either company or the county has published. The abatement does contemplate third party lessees who own and operate the equipment inside buildings the owner holds, but that is a structural provision, not evidence about any particular company.
How much water will the Armstrong County data center use?
No public record we retrieved states a water figure, a water source, or a cooling method. The word water does not appear in either of the county's two posted tax abatement agreements except inside the force majeure clause. Armstrong County has only three public water systems and all of them run on groundwater: Claude Municipal Water System serving about 1,300 people from seven wells, Washburn Community Water Supply Corporation serving about 150, and a youth camp. Part of the county lies inside the Panhandle Groundwater Conservation District, whose rules cap an operating permit at one acre foot per contiguous acre per year, but we could not determine whether the Lima Road site is inside that boundary.
How much is the Armstrong County data center tax abatement worth?
The county abates 100 percent of its own property taxes on each phase for ten calendar years beginning the year after that phase begins commercial operations, with base year 2024, and a second agreement grants a further ten years on equipment placed after the first period ends. Up to eight phases are authorized and four anticipated, each expected to require about one billion dollars of initial capital investment. In exchange the owner pays $1,360,375 a year per phase in lieu of taxes under the first agreement, and 15 percent of what the taxes would have been under the second. Armstrong County's entire 2025 certified taxable value for its general fund was $350,494,230.
How many jobs will the Armstrong County data center create?
The agreement requires 19 full time jobs per phase in abatement, counted only from the third calendar year of each phase's abatement period, measured campus wide, and satisfiable by the owner, its tenants, or their contractors and affiliates. If all four anticipated phases are built and abated, the commitment is 76 jobs. Against the anticipated one billion dollars of capital per phase, that is roughly 52.6 million dollars of investment per required job. The agreement defines a full time job as a position of 1,820 hours or more a year and counts transferred employees as well as new hires.
Has traffic gotten worse in Claude, Texas because of data center construction?
Texas Department of Transportation county tables show Armstrong County recorded 52 total crashes in 2023, 44 in 2024 and 71 in 2025, with commercial vehicle involved crashes of 18, 18 and 32. That is a 61 percent rise in total crashes and a 78 percent rise in truck involved crashes in one year, and trucks were involved in 45 percent of all 2025 crashes against a statewide share of 7.2 percent. Local television stations have reported on backups and wrecks around Claude in 2026, but the 2026 crash tables are not published and will not be available until roughly June 2027. The county's own posted exhibits from May 2025 called for widening and paving Lima Road and adding turn lanes on Highway 207 to handle construction traffic.
What noise limit applies to the Armstrong County data center?
The only limit is a contract term. Both abatement agreements state that noise at the project site boundaries shall not exceed 80 dBA during normal commercial operations, and that noise, light and dust shall be minimal off the site. The clause does not specify a measurement point, an instrument, an averaging period, or any difference between day and night. Texas counties generally have no zoning authority in unincorporated areas, so there is no county noise ordinance behind that number and enforcement would run through the contract rather than through a permit or a code.
Article sources
Our editorial standards require primary sources: government publications, regulator data, company filings, and established industry research.
- 1.NewsChannel 10 (KFDA): Claude prepares for school as data center construction increases traffic, wrecks, law enforcement (August 13, 2026)
- 2.NewsChannel 10 (KFDA): TxDOT makes traffic improvements in Claude as data center construction continues (August 21, 2026)
- 3.NewsChannel 10 (KFDA): Armstrong County volunteer fire departments seeking recruits amid decline (August 28, 2026)
- 4.NewsChannel 10 (KFDA): Data center construction drives Panhandle employment, boosts economy (June 10, 2026)
- 5.Armstrong County, Texas: Amended, Restated, and Consolidated Tax Abatement Agreement between Armstrong County and GN DC1, LLC (posted as Crusoe DC1 LLC A), 55 pages including Reinvestment Zone 8 resolutions, legal descriptions, Exhibit D local spending plan, Exhibit E Project Llano site plan, and Exhibit F form of synthetic lease assignment
- 6.Armstrong County, Texas: Amended, Restated, and Consolidated Second Tax Abatement Agreement between Armstrong County and GN DC1, LLC (posted as Crusoe DC1 LLC B), 50 pages
- 7.Armstrong County Commissioners Court document page, including the Tax Abatements section, the 2026 and 2025 monthly headings, the May 2025 Lima Road exhibits and the 2025 Annual Road Report
- 8.Armstrong County Resolution and Guidelines and Criteria for Granting a Tax Abatement, adopted August 26, 2024
- 9.Armstrong County: Lima Rd and Hwy 207 Roadway Adjustments exhibit, dated April 14, 2025
- 10.Armstrong County: Lima Road TxDOT access exhibit prepared by Kimley-Horn, dated April 30, 2025
- 11.Armstrong County: 2025 Armstrong County Annual Road Report, generated April 4, 2025
- 12.Armstrong County Appraisal District: 2025 certified values letter to the county judge, July 11, 2025, certifying $350,494,230 for the county general fund
- 13.FGE Goodnight I and II: statement of compliance with Chapter 312 agreement filed with the Armstrong County judge, March 31, 2025, certifying operation above the 100 MW required
- 14.Armstrong County emergency management page, listing the county emergency management coordinator and the WENS notification system effective October 1, 2025
- 15.Google: data center locations page, listing Armstrong County, Texas as in development with no accompanying figures
- 16.The Texas Tribune, November 14, 2025: Google to build three new data centers in Texas in $40 billion investment
- 17.NewsChannel 10, September 2, 2026: new workforce hub for data center workers coming to Wheeler County, about 11 miles from the Pampa site in Gray County
- 18.EPA Enforcement and Compliance History Online: Clean Water Act facilities in Armstrong County, Texas, FIPS 48011, including PROJECT LLANO, WEST LLANO and GOODNIGHT POWER PLANT PROJECT
- 19.EPA Detailed Facility Report for construction stormwater permit TXR1598UW, PROJECT LLANO, 10001 Lima Road, Claude, Texas
- 20.EPA Detailed Facility Report for construction stormwater permit TXR1529XT, GOODNIGHT POWER PLANT PROJECT, 9921 Lima Road, Claude, Texas, NAICS 518210
- 21.EPA Safe Drinking Water Information System: public water systems in Armstrong County, Texas
- 22.EPA Envirofacts: Claude Municipal Water System facilities, PWSID TX0060001, listing seven active primary wells
- 23.Panhandle Groundwater Conservation District: Rules approved July 9, 2026, including the 50/50 Standard and the one acre-foot per contiguous acre per year production cap
- 24.Panhandle Groundwater Conservation District: Management Plan 2024 to 2029, including district counties, modeled available groundwater by county, and reported use by category
- 25.U.S. Energy Information Administration: Preliminary Monthly Electric Generator Inventory, July 2026 file, listing Goodnight and Goodnight Wind II in Armstrong County, Texas
- 26.U.S. Energy Information Administration: Texas Electricity Profile 2024, net summer capacity and net generation
- 27.U.S. Energy Information Administration: average annual electricity consumption for a U.S. residential utility customer
- 28.Texas Department of Transportation: Crashes and Injuries by County, 2025
- 29.Texas Department of Transportation: Commercial Motor Vehicle Involved Crashes and Injuries by County, 2025
- 30.Texas Department of Transportation: Crashes and Injuries by County, 2024
- 31.Texas Department of Transportation: Commercial Motor Vehicle Involved Crashes and Injuries by County, 2024
- 32.Texas Department of Transportation: Crashes and Injuries by County, 2023
- 33.Texas Department of Transportation: Commercial Motor Vehicle Involved Crashes and Injuries by County, 2023
- 34.Texas Tax Code Section 312.002, guidelines and criteria effective for two years, three fourths vote to amend, and website posting requirement
- 35.Texas Tax Code Section 312.204, maximum abatement period of ten years and the portion of value that may be exempted
- 36.Texas Tax Code Section 312.205, required provisions of a tax abatement agreement
- 37.U.S. Census Bureau: 2024 Gazetteer files, land area for Armstrong County, Texas and Claude city, Texas
- 38.U.S. Census Bureau: Vintage 2024 population estimates for counties and for incorporated places
- 39.Texas Comptroller of Public Accounts: Chapter 311 and 312 biennial reports and tax abatement registry
Related reading
- What Communities Give Up: Data Center Tax Abatements, Line by Line
A data center is sold to a county on a property tax number, and that number is usually reduced by a statute or a negotiated deal the public never reads. The mechanisms explained, the qualifying thresholds quoted from the Ohio, Texas, Virginia, Georgia, and Iowa statutes, real packages on record from Barber County, Kansas to Effingham County, Georgia, what the states now say the exemptions cost, and the records a resident can request.
- How Loud Is a Data Center Allowed to Be? The Decibel Limits in the Ordinances That Govern Real Campuses
A sourced table of the noise ordinances governing the data centers on our tracker: code section, daytime and nighttime dBA limits, where they are measured, and whether low frequency or dBC limits exist, from Loudoun and Prince William to Mount Pleasant, Southaven and Chandler. Plus why dBA understates the hum.
- How to Fight a Proposed Data Center Before It Breaks Ground
Approval fights are the most successful category of data center litigation. Here is the playbook: reading the rezoning file, spotting notice and open meetings defects, organizing neighbors, referendums and recalls, moratoriums, and the short appeal clocks that decide everything.
- Who Pays for Data Center Power: The Ratepayer Tracker
The numbers behind the electric bill fight: PJM's capacity price rose from $28.92 to $333.44 per megawatt-day in three years, data centers account for $29.4 billion of the last four auctions' capacity costs by the market monitor's count, and the average PJM household faces an estimated $70 a month more by 2028. The running record of what regulators have found, which 23 states have answered with large load tariffs, what those tariffs require, and what a resident can do about a bill.
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us