Sue Data Centers

Data Center Registry

Haven Oak Technology Park

Dinwiddie County County, Virginia · All 19 Tract sites

ProposedContestedRecord updated November 4, 2026

Haven Oak Technology Park is a proposed data center in Virginia (Dinwiddie County County), operated by Tract. The public record puts it at announced July 2026. It is the subject of active public debate, with hearings, petitions, or organized opposition on record.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Proposed

Operator
Tract
Facility type
Data center
Location
Dinwiddie County County, VA
Coordinates
37.1650, -77.5520 (approximate)
Power capacity
Not established from a public source
Land
Not established from a public source
Investment
Not established from a public source
Announced
July 2026
Utility
Not established from a public source
Cooling
Closed loop
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
Contested
Source confidence
Reported by at least one credible outlet or filing

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. July 29, 2026
    Proposed
    Application under Dinwiddie Planning Department review; not approved Source: 12 On Your Side (WWBT)

Opposition and litigation at this site

Yes. Haven Oak Technology Park in Dinwiddie County County, Virginia is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. Part of the roughly 1,000-acre site lies within the White Oak Road Battlefield.

A new status, a permit, a reception finding, or a lawsuit. Nothing else, ever.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: contested means active public debate is on record, with hearings, petitions, or organized opposition, without litigation.

Part of the roughly 1,000-acre site lies within the White Oak Road Battlefield. Residents turned an open house into a de facto public hearing, and developers later moved all buildings away from the core battlefield area.

Source: WTVR CBS 6

Power and water

Developers' revised plans switched to a closed-loop, water-free cooling system and lower noise limits (12 On Your Side, Sept. 22, 2026).

Notes on the record

Nearly 1,000 acres near White Oak Road and Claiborne Road. The coordinates are approximate, placed on Claiborne Road via OSM.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Power capacity in megawatts
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • Land area
  • Which utility serves it
Which document closes each gap
Power capacity in megawatts
The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Land area
The rezoning application, the plat, or the deed recorded with the county.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Tell us about your situation

Living near Haven Oak Technology Park?

Tell us the basics. Where a participating attorney in your state is available, we may share your information with them with your consent. Free, no obligation, and no guarantee anyone will contact you.

Questions people ask about this site

Is there opposition to the Haven Oak Technology Park data center in Dinwiddie County County, Virginia?

Yes. Haven Oak Technology Park in Dinwiddie County County, Virginia is contested. Hearings, public comment, petitions, or organized opposition are on record, and no lawsuit has been filed so far. Part of the roughly 1,000-acre site lies within the White Oak Road Battlefield.

Has anyone filed a lawsuit over the Haven Oak Technology Park data center?

No lawsuit over Haven Oak Technology Park appears in the record we track as of November 4, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Haven Oak Technology Park use?

No water withdrawal figure for Haven Oak Technology Park is on record here. Cooling is recorded as closed_loop, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.

Who operates Haven Oak Technology Park, and how big is it?

Tract is the operator on record. We hold 19 sites for that company across the registry. No capacity figure is on record for this site.

How to cite this page

SueDataCenters.org Data Center Registry, "Haven Oak Technology Park," updated November 4, 2026, https://suedatacenters.org/data-centers/tract-haven-oak-technology-park-dinwiddie-va.

Facility data from Compute Atlas (E. Kubiak), version 1.35.1 (November 2, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/tract-haven-oak-technology-park-dinwiddie-va, retrieved November 5, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Dinwiddie residents demand answers over proposed data center and rural land concerns · WTVR CBS 6 · retrieved November 4, 2026
  2. 2.Data center proposal could end up on part of Civil War battlefield in Dinwiddie · 12 On Your Side (WWBT) · retrieved November 4, 2026
  3. 3.Dinwiddie community invited to public meeting on controversial Haven Oak Tech Park proposal · 12 On Your Side (WWBT) · retrieved November 4, 2026

Is a data center disrupting your home?

Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.

  • Tell us about your situation
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us