Data Center Registry
Simple Mining Manchester
Manchester, Delaware County, Iowa · All 5 Simple Mining sites
Simple Mining Manchester is a permitted crypto mining site in Manchester, Iowa (Delaware County), operated by Simple Mining. The public record puts it at announced January 2025.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Permitted
- Operator
- Simple Mining
- Facility type
- Crypto mining
- Location
- Manchester, Delaware County, IA
- Coordinates
- 42.4842, -91.4515 (approximate)
- Power capacity
- Not established from a public source
- Land
- Not established from a public source
- Investment
- Not established from a public source
- Announced
- January 2025
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Confirmed by multiple independent sources or official documentation
Opposition and litigation at this site
Nothing on record as of August 8, 2026. No lawsuit, organized opposition, or contested hearing over Simple Mining Manchester in Manchester, Delaware County, Iowa appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Notes on the record
Manchester City Council approved the site plan for a crypto-mining facility in Manchester's industrial park. City manager Tim Vick, speaking to Radio Iowa, described 50 modular 8-by-20-foot units on concrete pads, each with two cooling units; he said the site would draw power from a separate grid from the rest of the community, that the servers would not be water-cooled, and that water use would be limited to the office bathroom. Vick put the project at eight full-time jobs. The Telegraph Herald's visible lead calls it the company's largest investment yet; as of October 2026 the body of that article is subscriber-only, so nothing else here rests on it. Construction was reported (as of Jan 2025) scheduled to start 'later this spring' [2025], that's the last independently-confirmed checkpoint that could be sourced; as of Aug 2026 (~19 months later) no later report of construction or opening was found, so the record is left at the last-verified permitted (site-plan-approved) stage. Exact street address (widely reported elsewhere as 1016 Grant Street) is NOT included here because, as of August 2026, it was only ever seen in web-search AI summaries of manchesterpress.com/telegraphherald.com, never on a page that was successfully consulted (manchesterpress.com could not be read on two attempts), Manchester city-seat coordinates are used instead, so the pin is approximate. No MW capacity figure found anywhere.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- Land area
- How the community has received it
- Which utility serves it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Aurum Elk Data Center Project (Central City) · Central City · Aurum Capital Ventures20 mi · Proposed · 4 MW · Mixed reception
- US Secure Hosting Center (USSHC) · Monticello · US Secure Hosting Center23 mi · Operating
- Simple Mining Cascade (Dubuque County) · Cascade · Simple Mining26 mi · Proposed
- Cassville Data Center Campus (Undisclosed Developer) · Cassville · Undisclosed (major tech company, NDA not signed)28 mi · Cancelled · Opposed
Questions people ask about this site
Is there opposition to the Simple Mining Manchester data center in Manchester?
Nothing on record as of August 8, 2026. No lawsuit, organized opposition, or contested hearing over Simple Mining Manchester in Manchester, Delaware County, Iowa appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the Simple Mining Manchester data center?
No lawsuit over Simple Mining Manchester appears in the record we track as of August 8, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Simple Mining Manchester use?
No water withdrawal figure for Simple Mining Manchester is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Simple Mining Manchester, and how big is it?
Simple Mining is the operator on record. We hold 5 sites for that company across the registry. No capacity figure is on record for this site.
How to cite this page
SueDataCenters.org Data Center Registry, "Simple Mining Manchester," updated August 8, 2026, https://suedatacenters.org/data-centers/simple-mining-manchester-ia.
Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/simple-mining-manchester-ia, retrieved October 29, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Manchester official tries to calm fears over incoming crypto-mining operation · Radio Iowa · retrieved August 8, 2026
- 2.Mining in Manchester?: Crypto-currency biz eyes development at city industrial park · Telegraph Herald · retrieved August 8, 2026
Is a data center disrupting your home?
Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.
- Tell us about your situation
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us