Data Center Registry
QTS Phoenix 2
Phoenix, Maricopa County, Arizona · All 41 QTS Data Centers sites · Every QTS and Compass Datacenters case on our tracker
QTS Phoenix 2 is an operating data center in Phoenix, Arizona (Maricopa County), operated by QTS Data Centers. The public record puts it at 210 MW planned, 80 acres.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Operating
- Operator
- QTS Data Centers
- Facility type
- Data center
- Location
- 1400 N 40th St, Phoenix, Maricopa County, AZ, 85008
- Coordinates
- 33.4644, -111.9948 (approximate)
- Power capacity
- 210 MW planned
- Land
- 80 acres
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Closed loop
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- September 10, 2026OperatingQTS lists Phoenix 2 as an 80-acre campus with 210 MW+ of critical power across five buildings (DC1-DC5) at 1200-1500 N 40th Street. Source: QTS Data Centers
Opposition and litigation at this site
Nothing on record as of November 4, 2026. No lawsuit, organized opposition, or contested hearing over QTS Phoenix 2 in Phoenix, Maricopa County, Arizona appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
People and entities in the record
Ann O'Brien · public_official via Phoenix City Council
Member of the Phoenix City Council; voted for the development agreement with QTS Phoenix II, LLC for public open space at its McDowell Road data center site (Ordinance S-50411). Outcome: adopted 9-0 (2023-12-13).
SourceBetty Guardado · public_official via Phoenix City Council
Member of the Phoenix City Council; voted for the development agreement with QTS Phoenix II, LLC for public open space at its McDowell Road data center site (Ordinance S-50411). Outcome: adopted 9-0 (2023-12-13).
SourceDebra Stark · public_official via Phoenix City Council
Member of the Phoenix City Council; voted for the development agreement with QTS Phoenix II, LLC for public open space at its McDowell Road data center site (Ordinance S-50411). Outcome: adopted 9-0 (2023-12-13).
SourceJim Waring · public_official via Phoenix City Council
Member of the Phoenix City Council; voted for the development agreement with QTS Phoenix II, LLC for public open space at its McDowell Road data center site (Ordinance S-50411). Outcome: adopted 9-0 (2023-12-13).
SourceKate Gallego · public_official via Phoenix City Council
Mayor of Phoenix; voted for the development agreement with QTS Phoenix II, LLC for public open space at its McDowell Road data center site (Ordinance S-50411). Outcome: adopted 9-0 (2023-12-13).
SourceKesha Hodge Washington · public_official via Phoenix City Council
Member of the Phoenix City Council; voted for the development agreement with QTS Phoenix II, LLC for public open space at its McDowell Road data center site (Ordinance S-50411). Outcome: adopted 9-0 (2023-12-13).
SourceKevin Robinson · public_official via Phoenix City Council
Member of the Phoenix City Council; voted for the development agreement with QTS Phoenix II, LLC for public open space at its McDowell Road data center site (Ordinance S-50411). Outcome: adopted 9-0 (2023-12-13).
SourceLaura Pastor · public_official via Phoenix City Council
Member of the Phoenix City Council; voted for the development agreement with QTS Phoenix II, LLC for public open space at its McDowell Road data center site (Ordinance S-50411). Outcome: adopted 9-0 (2023-12-13).
SourceYassamin Ansari · public_official via Phoenix City Council
Member of the Phoenix City Council; voted for the development agreement with QTS Phoenix II, LLC for public open space at its McDowell Road data center site (Ordinance S-50411). Outcome: adopted 9-0 (2023-12-13).
Source
Notes on the record
Five-building campus at 1200, 1250, 1400, 1450 and 1500 N 40th Street, Phoenix. The '210 MW+' figure is the campus's stated critical power at full build, recorded as planned rather than operational because the operator does not say how much is energized today. Note that qtsdatacenters.com now redirects to q.com. Coordinates geocoded from 1400 N 40th St via Nominatim.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Tax abatements or other public subsidy
- Permanent jobs promised
- How the community has received it
- Which utility serves it
Which document closes each gap
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- STACK Infrastructure PHX02 Campus · Phoenix · STACK Infrastructureunder 1 mile · Under construction · 250 MW
- Iron Mountain AZP-1 · Phoenix · Iron Mountain1 mi · Operating
- Iron Mountain AZP-2 · Phoenix · Iron Mountain1 mi · Operating
- Iron Mountain AZP-3 · Phoenix · Iron Mountain1 mi · Operating · 36 MW
- phoenixNAP PHX02 · Phoenix · phoenixNAP3 mi · Under construction · 50 MW
- Lumen Phoenix 1 · Phoenix · Lumen Technologies5 mi · Operating
- LKY Real Estate Fund IV data center (617 S. 5th Ave., Phoenix) · Phoenix · Undisclosed (landowner: LKY Real Estate Fund IV Limited Partnership L.L.L.P)5 mi · Proposed
- 5C Data Centers PHX01 · Phoenix · 5C Data Centers7 mi · Under construction · 20 MW
Questions people ask about this site
Is there opposition to the QTS Phoenix 2 data center in Phoenix?
Nothing on record as of November 4, 2026. No lawsuit, organized opposition, or contested hearing over QTS Phoenix 2 in Phoenix, Maricopa County, Arizona appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the QTS Phoenix 2 data center?
No lawsuit over QTS Phoenix 2 appears in the record we track as of November 4, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does QTS Phoenix 2 use?
No water withdrawal figure for QTS Phoenix 2 is on record here. Cooling is recorded as closed_loop, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.
Who operates QTS Phoenix 2, and how big is it?
QTS Data Centers is the operator on record. We hold 41 sites for that company across the registry. Capacity on record is 210 MW. The site is recorded at 80 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "QTS Phoenix 2," updated November 4, 2026, https://suedatacenters.org/data-centers/qts-phoenix-2-az.
Facility data from Compute Atlas (E. Kubiak), version 1.35.1 (November 2, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/qts-phoenix-2-az, retrieved November 5, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Phoenix 2, QTS Data Centers · QTS Data Centers · retrieved September 21, 2026
- 2.Phoenix City Council Formal Meeting, Dec. 13, 2023, item 29 (File 23-2248, Ordinance S-50411) · City of Phoenix · retrieved November 4, 2026
Is a data center disrupting your home?
Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.
- Tell us about your situation
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us