Niagara Digital Campus
Niagara Falls, Niagara County, New York
Niagara Digital Campus is a proposed data center in Niagara Falls, New York (Niagara County), operated by Urbacon Data Centre Solutions. The public record puts it at 135 MW planned, 142 acres, a reported $1.5 billion investment. It has documented support and documented opposition on record.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Proposed
- Operator
- Urbacon Data Centre Solutions
- Facility type
- Data center, AI use likely
- Location
- Niagara Falls, Niagara County, NY
- Coordinates
- 43.0885, -79.0603
- Power capacity
- 135 MW planned
- Land
- 142 acres
- Investment
- $1.5 billion
- Announced
- Not established from a public source
- Utility
- New York Power Authority (NYPA)
- Power source
- Hydro
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- 550 permanent; 5,600 construction
- Public subsidy
- Not established from a public source
- Community reception
- Mixed reception
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- April 2026ProposedNew application incorporating additional Falls Street parcels under review; NFR states construction could begin within six months of approvals Source: Niagara Falls Reporter
- December 2025ProposedPlanning Board rejects modified application; parties reported near resolution including possible two-project accommodation Source: Niagara Falls Reporter
- January 2024ProposedNiagara Falls Redevelopment (NFR) and Urbacon Data Centre Solutions announce $1.5B campus proposal at Rainbow and John B. Daly Boulevards Source: Baxtel
Opposition and litigation at this site
Partly. Both documented support and documented opposition to Niagara Digital Campus in Niagara Falls, Niagara County, New York appear in the record, with no clear majority position. Planning Board rejected modified application in December 2025.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: mixed reception means documented support and documented opposition both exist with no clear majority position on record.
Planning Board rejected modified application in December 2025. By early 2026 Mayor Restaino adopted conciliatory tone, proposing a two-project solution accommodating both data center and Centennial Park. New application incorporating additional Falls Street parcels filed April 2026.
Power and water
Site at 907 Falls St (Rainbow and John B. Daly Blvd); 600,000 sq ft across two phases; new electrical substation planned for the campus.
Notes on the record
Site is near the historic Adams Power Plant and the NYPA Robert Moses Niagara Power Plant (2,675 MW combined capacity). Phase I planned as ~282,000 sq ft over 24 months from groundbreaking. Economic impact estimated at $2B over 20 years per MRB Group analysis commissioned by NFR. Developed by Niagara Falls Redevelopment (NFR, controlled by Milstein family) in partnership with Urbacon. NO STATUS CHANGE. The 4 June 2026 City Council vote settled an eminent-domain lawsuit and transferred 10 acres to the city; the mayor states explicitly it was not a data-center approval and that there is no timeline for work to begin. Remains proposed.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Cooling method and water use
- Tax abatements or other public subsidy
Which document closes each gap
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Blockfusion Niagara Falls Facility (North East Data) · Niagara Falls · Blockfusion1 mi · Operating · 100 MW · Contested
- American Bitcoin, Niagara Falls ("Alpha Site") · Niagara Falls · American Bitcoin (Hut 8)2 mi · Operating · 50 MW · In litigation
- 9LDG Niagara AI Data Center · Niagara Falls · 9 Lives Digital Group (9LDG)3 mi · Proposed · Supported
- Riverview Innovation & Technology Campus · Tonawanda · Riverview Innovation & Technology Campus9 mi · Proposed · 300 MW · Contested
- Digihost / Digi Power X, Fortistar North Tonawanda · North Tonawanda · Digihost (Digi Power X)11 mi · Operating · 120 MW · In litigation
- H5 Data Centers Buffalo I (formerly Yahoo Lockport) · Lockport · H5 Data Centers17 mi · Operating · 15 MW
- Empire AI Beta · Buffalo · Empire AI consortium (hosted by the University at Buffalo, SUNY)17 mi · Operating
- H5 Data Centers Buffalo II · Lockport · H5 Data Centers17 mi · Operating · 7.2 MW
Questions people ask about this site
Is there opposition to the Niagara Digital Campus in Niagara Falls?
Partly. Both documented support and documented opposition to Niagara Digital Campus in Niagara Falls, Niagara County, New York appear in the record, with no clear majority position. Planning Board rejected modified application in December 2025.
Has anyone filed a lawsuit over the Niagara Digital Campus?
The reception note on this record refers to a court proceeding. Read it in full under opposition and litigation above, and check the sources at the foot of the page for the filing itself.
How much water does Niagara Digital Campus use?
No water withdrawal figure for Niagara Digital Campus is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Niagara Digital Campus, and how big is it?
Urbacon Data Centre Solutions is the operator on record. Capacity on record is 135 MW. The site is recorded at 142 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Niagara Digital Campus," updated September 9, 2026, https://suedatacenters.org/data-centers/niagara-digital-campus-niagara-falls-ny.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/niagara-digital-campus-niagara-falls-ny, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Urbacon: Niagara Digital Campus Data Center · Baxtel · retrieved July 6, 2026
- 2.Niagara Falls Can Power Forward With Data Center Opportunity · Niagara Falls Reporter · retrieved July 6, 2026
- 3.135MW data center campus proposed in view of Niagara Falls · Data Center Dynamics · retrieved July 6, 2026
- 4.Contentious Niagara Falls City Council meeting leads to land deal for potential data center · Spectrum News 1 Buffalo · retrieved September 9, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.