Data Center Registry
Hitchcock County Data Mining Site (Sec. 23, T4N, R33W; CUP #2-2024)
Hitchcock County, Nebraska
Hitchcock County Data Mining Site (Sec. 23, T4N, R33W; CUP #2-2024) is a proposed crypto mining site in Nebraska (Hitchcock County), operated by Undisclosed data mining company (CUP applicant). It faces documented, organized local opposition.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Proposed
- Operator
- Undisclosed data mining company (CUP applicant)
- Facility type
- Crypto mining
- Location
- Hitchcock County, NE
- Coordinates
- 40.3000, -101.0300 (approximate)
- Power capacity
- Not established from a public source
- Land
- Not established from a public source
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Southwest Public Power District
- Power source
- Grid
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- Opposed
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- January 16, 2025ProposedConditional use application #2-2024 for a data mining structure (four shipping-container-size structures). The planning commission recommended denial, and the county board outcome was not found. Source: Hitchcock County, NE
Opposition and litigation at this site
Yes. Organized local opposition to Hitchcock County Data Mining Site (Sec. 23, T4N, R33W; CUP #2-2024) in Hitchcock County, Nebraska is documented in the public record, without a lawsuit on file in the sources we track. Several nearby residents opposed the application at the Jan.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: opposed means documented, organized local opposition is the dominant signal on record.
Several nearby residents opposed the application at the Jan. 16, 2025 planning commission hearing, citing noise, security, traffic and internet bandwidth. The commission voted to recommend denial for insufficient information.
Power and water
Per the SWPPD general manager at the hearing, the site would be served from the Beverly substation on its own circuit. It would run October to May and stay off during peak load times. The power agreement was still being negotiated.
Notes on the record
The applicant is a private individual, so the operator is left as undisclosed. The county adopted a data center and crypto mining moratorium on Feb. 3, 2025. The coordinates are a rough PLSS-based placement.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- Land area
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- MB Club / MB Computing Data Center & Crypto Mining Site (south of Trenton) · Trenton · MB Club, LLC16 mi · Proposed
Questions people ask about this site
Is there opposition to the Hitchcock County Data Mining Site (Sec. 23, T4N, R33W; CUP #2-2024) data center in Hitchcock County, Nebraska?
Yes. Organized local opposition to Hitchcock County Data Mining Site (Sec. 23, T4N, R33W; CUP #2-2024) in Hitchcock County, Nebraska is documented in the public record, without a lawsuit on file in the sources we track. Several nearby residents opposed the application at the Jan.
Has anyone filed a lawsuit over the Hitchcock County Data Mining Site (Sec. 23, T4N, R33W; CUP #2-2024) data center?
No lawsuit over Hitchcock County Data Mining Site (Sec. 23, T4N, R33W; CUP #2-2024) appears in the record we track as of October 30, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Hitchcock County Data Mining Site (Sec. 23, T4N, R33W; CUP #2-2024) use?
No water withdrawal figure for Hitchcock County Data Mining Site (Sec. 23, T4N, R33W; CUP #2-2024) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Hitchcock County Data Mining Site (Sec. 23, T4N, R33W; CUP #2-2024), and how big is it?
Undisclosed data mining company (CUP applicant) is the operator on record. No capacity figure is on record for this site.
How to cite this page
SueDataCenters.org Data Center Registry, "Hitchcock County Data Mining Site (Sec. 23, T4N, R33W; CUP #2-2024)," updated October 30, 2026, https://suedatacenters.org/data-centers/hitchcock-county-data-mining-sec23-t4n-r33w-ne.
Facility data from Compute Atlas (E. Kubiak), version 1.35.1 (November 2, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/hitchcock-county-data-mining-sec23-t4n-r33w-ne, retrieved November 5, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Hitchcock County Planning Commission minutes, Jan. 16, 2025 (CUP #2-2024 data mining structure) · Hitchcock County, NE · retrieved October 30, 2026
Is a data center disrupting your home?
Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.
- Tell us about your situation
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us