Data Center Registry
H5 Data Centers Cincinnati I
Cincinnati, Hamilton County, Ohio · All 17 H5 Data Centers sites
H5 Data Centers Cincinnati I is an operating data center in Cincinnati, Ohio (Hamilton County), operated by H5 Data Centers.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Operating
- Operator
- H5 Data Centers
- Facility type
- Data center
- Location
- 360 Gest Street, Cincinnati, Hamilton County, OH, 45203
- Coordinates
- 39.0982, -84.5261 (approximate)
- Power capacity
- Not established from a public source
- Land
- Not established from a public source
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Duke Energy
- Power source
- Grid
- Cooling
- Closed loop
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Confirmed by multiple independent sources or official documentation
Opposition and litigation at this site
Nothing on record as of September 21, 2026. No lawsuit, organized opposition, or contested hearing over H5 Data Centers Cincinnati I in Cincinnati, Hamilton County, Ohio appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Power and water
Operator cites diverse utility feeds from Duke Energy at an average of less than $0.06/kWh.
Notes on the record
Described by the operator as a powered shell adjacent to downtown Cincinnati, with redundant meet-me rooms and on-net AT&T, Inteliquent, Windstream and Zayo. Square footage and MW are not published. Coordinates are a street-address geocode.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Tax abatements or other public subsidy
- Permanent jobs promised
- Land area
- How the community has received it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- DartPoints Cincinnati · Cincinnati · DartPointsunder 1 mile · Operating · 0.18 MW
- CyrusOne CIN2 (Cincinnati) · Cincinnati · CyrusOneunder 1 mile · Operating · 14 MW
- H5 Data Centers Cincinnati II · Cincinnati · H5 Data Centersunder 1 mile · Operating · 2 MW
- Lumen Cincinnati 1 (400 Pike Street) · Cincinnati · Lumen Technologies1 mi · Operating
- CyrusOne CIN6 (Florence) · Florence · CyrusOne9 mi · Operating · 5 MW
- Crane Data Centers Pierce Township Campus (near Beckjord) · New Richmond (Pierce Township) · Crane Data Centers14 mi · Proposed · 300 MW · Contested
- Encore Technologies BLU1 (Blue Ash) · Blue Ash · Encore Technologies15 mi · Operating
- Flexential Cincinnati (CIN01/02) · West Chester Township · Flexential16 mi · Operating
Questions people ask about this site
Is there opposition to the H5 Data Centers Cincinnati I data center in Cincinnati?
Nothing on record as of September 21, 2026. No lawsuit, organized opposition, or contested hearing over H5 Data Centers Cincinnati I in Cincinnati, Hamilton County, Ohio appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the H5 Data Centers Cincinnati I data center?
No lawsuit over H5 Data Centers Cincinnati I appears in the record we track as of September 21, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does H5 Data Centers Cincinnati I use?
No water withdrawal figure for H5 Data Centers Cincinnati I is on record here. Cooling is recorded as closed_loop, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.
Who operates H5 Data Centers Cincinnati I, and how big is it?
H5 Data Centers is the operator on record. We hold 17 sites for that company across the registry. No capacity figure is on record for this site.
How to cite this page
SueDataCenters.org Data Center Registry, "H5 Data Centers Cincinnati I," updated September 21, 2026, https://suedatacenters.org/data-centers/h5-data-centers-cincinnati-gest-oh.
Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/h5-data-centers-cincinnati-gest-oh, retrieved October 29, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.H5 Data Centers, Cincinnati I data center · H5 Data Centers · retrieved September 21, 2026
- 2.Ohio data center location directory · Cloud and Colocation · retrieved August 27, 2026
Is a data center disrupting your home?
Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.
- Tell us about your situation
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us