GW Ranch

Pecos County, Texas · All 2 Pacifico Energy sites

ProposedNo reception on recordAI likelyRecord updated September 10, 2026

GW Ranch is a proposed data center in Texas (Pecos County), operated by Pacifico Energy. The public record puts it at 7.7 GW planned, 8,000 acres. The record for this site rests on a single unverified source and should be read that way.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Proposed

Operator
Pacifico Energy
Facility type
Data center, AI use likely
Location
Pecos County, TX
Coordinates
31.0500, -102.8800
Power capacity
7.7 GW planned
Land
8,000 acres
Investment
Not established from a public source
Announced
Not established from a public source
Utility
Not established from a public source
Power source
On site gas
On site generation
7.7 GW
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
No reception on record
Source confidence
Rumored: a single unverified source

Opposition and litigation at this site

Nothing on record as of September 10, 2026. No lawsuit, organized opposition, or contested hearing over GW Ranch in Pecos County, Texas appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.

Power and water

TCEQ air permit secured (Jan 2026) for up to 7.65GW gas-fired generation - the largest such permit in the US. Includes 1.8GW battery storage + up to 750MWac solar. Off-grid/private-network design, not ERCOT-interconnected. Developer timeline: 1GW online 2028, 5+GW by 2030-31.

Notes on the record

~17 miles north of Fort Stockton. This is fundamentally a power-generation project 'purpose-built to support hyperscale data center operators' (per Data Center Dynamics), but no data center tenant/operator has been named - classified 'rumored' confidence on the data-center use specifically. Distinct from the existing tracked Microsoft/Core Scientific 'Pecos' entries (those are in Reeves County, not Pecos County). Coordinates are approximate. Data center tenant unidentified. Public-reception check (2026-09-10): TCEQ approved the site's air permit (up to 7.65GW gas-fired, authorized to emit 12,000+ tons/yr of regulated pollutants per permitting documents) in early 2026. Checked an oil-and-gas-watchdog outlet (a source that actively covers this project's environmental profile in detail) and it documents no local opposition, hearing record, or resident reaction to GW Ranch specifically -- only industry/regulatory facts. The original DCD source and a second outlet (Inside Climate News) both 403'd on fetch. No community-reception record found in the source actually retrieved.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • How the community has received it
  • Which utility serves it
Which document closes each gap
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
How the community has received it
Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the GW Ranch data center in Pecos County, Texas?

Nothing on record as of September 10, 2026. No lawsuit, organized opposition, or contested hearing over GW Ranch in Pecos County, Texas appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

Has anyone filed a lawsuit over the GW Ranch data center?

No lawsuit over GW Ranch appears in the record we track as of September 10, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does GW Ranch use?

No water withdrawal figure for GW Ranch is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates GW Ranch, and how big is it?

Pacifico Energy is the operator on record. We hold 2 sites for that company across the registry. Capacity on record is 7.7 GW. The site is recorded at 8000 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "GW Ranch," updated September 10, 2026, https://suedatacenters.org/data-centers/gw-ranch-pacifico-energy-pecos-county-tx.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/gw-ranch-pacifico-energy-pecos-county-tx, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Pacifico Energy unveils 5GW off-grid natural gas project in Texas, slated to serve a hyperscale data center · Data Center Dynamics · retrieved July 9, 2026
  2. 2.Developer calls GW Ranch the largest power project in the U.S. · Inside Climate News · retrieved July 9, 2026
  3. 3.Amazon Backs 7.65-GW Gas Plant in Texas to Power New AI Data Center Campus · Construction Review Online · retrieved August 25, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us