Greenidge Underwood (North Dakota) is an operating crypto mining site in Underwood, North Dakota (McLean County), operated by Greenidge Generation. The public record puts it at announced March 11, 2024, 7.5 MW operating.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Operating

Operator
Greenidge Generation
Facility type
Crypto mining
Location
Underwood, McLean County, ND
Coordinates
47.4564, -101.1371 (approximate)
Power capacity
7.5 MW operating
Land
Not established from a public source
Investment
Not established from a public source
Announced
March 11, 2024
Utility
Not established from a public source
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
No reception on record
Source confidence
Confirmed by multiple independent sources or official documentation

Opposition and litigation at this site

Nothing on record as of August 5, 2026. No lawsuit, organized opposition, or contested hearing over Greenidge Underwood (North Dakota) in Underwood, McLean County, North Dakota appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.

Notes on the record

5-year capacity lease entered January 2024, announced Mar 11 2024, providing 7.5 MW of self-mining capacity in Underwood, McLean County, ND; miners deployed ~April 2024. SEC 10-Q filings for both Q3 FY2025 and Q1 FY2026 (most recent found) confirm the 'North Dakota Facility' remains an active leased site - the only other US site besides the New York (Dresden) plant that Greenidge still operates. No street address disclosed; city-level coordinates, approximate.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • Land area
  • How the community has received it
  • Which utility serves it
Which document closes each gap
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Land area
The rezoning application, the plat, or the deed recorded with the county.
How the community has received it
Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the Greenidge Underwood (North Dakota) data center in Underwood?

Nothing on record as of August 5, 2026. No lawsuit, organized opposition, or contested hearing over Greenidge Underwood (North Dakota) in Underwood, McLean County, North Dakota appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

Has anyone filed a lawsuit over the Greenidge Underwood (North Dakota) data center?

No lawsuit over Greenidge Underwood (North Dakota) appears in the record we track as of August 5, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Greenidge Underwood (North Dakota) use?

No water withdrawal figure for Greenidge Underwood (North Dakota) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Greenidge Underwood (North Dakota), and how big is it?

Greenidge Generation is the operator on record. We hold 3 sites for that company across the registry. Capacity on record is 7.5 MW.

How to cite this page

SueDataCenters.org Data Center Registry, "Greenidge Underwood (North Dakota)," updated August 5, 2026, https://suedatacenters.org/data-centers/greenidge-underwood-nd.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/greenidge-underwood-nd, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Greenidge Announces Expansion of Power Capacity with 40 MW of Low-Cost Power in Key Territories · Greenidge Generation Holdings Inc. (SEC 8-K exhibit) · retrieved August 5, 2026
  2. 2.Greenidge Generation Holdings Inc. Form 10-Q, Q3 FY2025 · SEC EDGAR · retrieved August 5, 2026
  3. 3.Greenidge Generation Holdings Inc. Form 10-Q, Q1 FY2026 · SEC EDGAR · retrieved August 5, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us