Google Haskell County Data Center Campus

Haskell, Haskell County, Texas · All 61 Google sites · Every Google case on our tracker

Under constructionMixed receptionAI confirmedRecord updated October 22, 2026

Google Haskell County Data Center Campus is a data center under construction in Haskell, Texas (Haskell County), operated by Google. The public record puts it at announced November 14, 2025. It has documented support and documented opposition on record.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Under construction

Operator
Google
Facility type
Data center, AI use confirmed
Location
Haskell, Haskell County, TX
Coordinates
33.1576, -99.7337 (approximate)
Power capacity
Not established from a public source
Land
Not established from a public source
Investment
Not established from a public source
Announced
November 14, 2025
Utility
solar
Power source
Solar
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
Mixed reception
Source confidence
Confirmed by multiple independent sources or official documentation

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. November 14, 2025
    Proposed
    Google and Governor Abbott jointly announced a $40B Texas AI-infrastructure investment including two data center buildings at the Haskell County campus Source: Office of the Texas Governor
  2. November 2025
    Under construction
    Ground broken; Google began engaging subcontractors for active construction Source: Texas Tribune

Opposition and litigation at this site

Partly. Both documented support and documented opposition to Google Haskell County Data Center Campus in Haskell, Haskell County, Texas appear in the record, with no clear majority position. Stamford Mayor James Decker called the buildout 'jarring' and voiced concern about the town being chewed up by the data-center boom; Haskell Mayor Christina Isbell anticipates long-term economic benefit for the ~3,000-resident town.

A new status, a permit, a reception finding, or a lawsuit. Nothing else, ever.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: mixed reception means documented support and documented opposition both exist with no clear majority position on record.

Stamford Mayor James Decker called the buildout 'jarring' and voiced concern about the town being chewed up by the data-center boom; Haskell Mayor Christina Isbell anticipates long-term economic benefit for the ~3,000-resident town. County tax base expected to more than double. Google committed to fund training for 1,700+ TX electrical apprentices by 2030.

Source: KTXS ABC Abilene

Power and water

Dedicated supply is the co-located Quantum Clean Energy Project (Intersect Power / Google subsidiary): 640 MW solar PV + 1.3 GWh BESS, operational target June 2026. Haskell County selected partly for wind and solar availability.

Notes on the record

Two data center buildings at one Haskell County site; treated as a single campus record. Announced Nov 14 2025 as part of Google's $40B Texas investment through 2027 (which also covers Armstrong County and a Wilbarger County/Vernon site); no Haskell-specific investment figure disclosed, so no investment figure is recorded (the $40B is a Texas-wide aggregate). Data-center IT capacity in MW not publicly disclosed. One building is co-located with the Quantum Clean Energy Project (Intersect Power, acquired by Google March 2026): 640 MW solar PV + 1.3 GWh battery storage, scheduled operational June 2026 - this is energy-project capacity, NOT data-center IT load. Job figures cited in press (1,200 construction / up to 11 permanent) come from the co-located Intersect energy project, not the data center, so they are noted here rather than recorded as job counts. Coordinates are the Haskell city centroid (no parcel-level GPS found).

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Power capacity in megawatts
  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • Land area
Which document closes each gap
Power capacity in megawatts
The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Land area
The rezoning application, the plat, or the deed recorded with the county.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Tell us about your situation

Living near Google Haskell County Data Center Campus?

Tell us the basics. Where a participating attorney in your state is available, we may share your information with them with your consent. Free, no obligation, and no guarantee anyone will contact you.

Questions people ask about this site

Is there opposition to the Google Haskell County Data Center Campus in Haskell?

Partly. Both documented support and documented opposition to Google Haskell County Data Center Campus in Haskell, Haskell County, Texas appear in the record, with no clear majority position. Stamford Mayor James Decker called the buildout 'jarring' and voiced concern about the town being chewed up by the data-center boom; Haskell Mayor Christina Isbell anticipates long-term economic benefit for the ~3,000-resident town.

Has anyone filed a lawsuit over the Google Haskell County Data Center Campus?

No lawsuit over Google Haskell County Data Center Campus appears in the record we track as of October 22, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Google Haskell County Data Center Campus use?

No water withdrawal figure for Google Haskell County Data Center Campus is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Google Haskell County Data Center Campus, and how big is it?

Google is the operator on record. We hold 61 sites for that company across the registry. No capacity figure is on record for this site.

How to cite this page

SueDataCenters.org Data Center Registry, "Google Haskell County Data Center Campus," updated October 22, 2026, https://suedatacenters.org/data-centers/google-haskell-county-tx.

Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/google-haskell-county-tx, retrieved October 29, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Google data centers totaling $40 billion coming to Texas · Texas Tribune · retrieved July 7, 2026
  2. 2.Governor Abbott, Google Announce $40 Billion Investment In Texas · Office of the Texas Governor · retrieved July 7, 2026 · original offline, archived copy from October 11, 2026
  3. 3.Google's investment in Haskell and West Central Texas · Google · retrieved July 7, 2026
  4. 4.Quantum Clean Energy Project - Haskell County TX · Intersect Power · retrieved July 7, 2026
  5. 5.Google's $40 billion data center investment to transform Texas town · KTXS ABC Abilene · retrieved July 7, 2026
  6. 6.Data centers bring major investment, growth potential to Haskell County · KAUZ News Channel 6 · retrieved July 7, 2026

Is a data center disrupting your home?

Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.

  • Tell us about your situation
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us