Decimal Digital Monroeville Data Center (Fort Monroe Industrial Park)

Monroeville, Huron County, Ohio

ProposedOpposedRecord updated November 4, 2026

Decimal Digital Monroeville Data Center (Fort Monroe Industrial Park) is a proposed data center in Monroeville, Ohio (Huron County), operated by Decimal Digital. The public record puts it at 100 MW planned, 48 acres, a reported $1 billion investment. It faces documented, organized local opposition.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Proposed

Operator
Decimal Digital
Facility type
Data center
Location
Monroeville, Huron County, OH
Coordinates
41.2442, -82.6960 (approximate)
Power capacity
100 MW planned
Land
48 acres
Investment
$1 billion
Announced
Not established from a public source
Utility
Village of Monroeville municipal electric utility
Power source
Grid
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
50 permanent; 500 construction
Public subsidy
Not established from a public source
Community reception
Opposed
Source confidence
Reported by at least one credible outlet or filing

Opposition and litigation at this site

Yes. Organized local opposition to Decimal Digital Monroeville Data Center (Fort Monroe Industrial Park) in Monroeville, Huron County, Ohio is documented in the public record, without a lawsuit on file in the sources we track. In unofficial Nov.

A new status, a permit, a reception finding, or a lawsuit. Nothing else, ever.

How the community has taken it

Reception is a sourced signal, not an editorial judgment: opposed means documented, organized local opposition is the dominant signal on record.

In unofficial Nov. 3, 2026 results, about 87.75% of voters opposed an advisory question on allowing data center development in the village. A yearlong moratorium runs until March.

Source: Cincinnati Enquirer (via Yahoo News)

Power and water

The plan includes an on-site substation. The developer proposed 'rider fees' above the power rate, paid into a village-controlled fund.

Notes on the record

100 MW, single-hall data center proposed on a 48-acre site the developer bought in the Fort Monroe Industrial Park. The developer requested a 100% property tax abatement with replacement payments; these are proposals only. The site is across the street from a troubled bitcoin mining property now under a court-appointed receiver.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Cooling method and water use
  • Tax abatements or other public subsidy
Which document closes each gap
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Tell us about your situation

Living near Decimal Digital Monroeville Data Center (Fort Monroe Industrial Park)?

Tell us the basics. Where a participating attorney in your state is available, we may share your information with them with your consent. Free, no obligation, and no guarantee anyone will contact you.

Questions people ask about this site

Is there opposition to the Decimal Digital Monroeville Data Center (Fort Monroe Industrial Park) in Monroeville?

Yes. Organized local opposition to Decimal Digital Monroeville Data Center (Fort Monroe Industrial Park) in Monroeville, Huron County, Ohio is documented in the public record, without a lawsuit on file in the sources we track. In unofficial Nov.

Has anyone filed a lawsuit over the Decimal Digital Monroeville Data Center (Fort Monroe Industrial Park)?

No lawsuit over Decimal Digital Monroeville Data Center (Fort Monroe Industrial Park) appears in the record we track as of November 4, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Decimal Digital Monroeville Data Center (Fort Monroe Industrial Park) use?

No water withdrawal figure for Decimal Digital Monroeville Data Center (Fort Monroe Industrial Park) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Decimal Digital Monroeville Data Center (Fort Monroe Industrial Park), and how big is it?

Decimal Digital is the operator on record. Capacity on record is 100 MW. The site is recorded at 48 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Decimal Digital Monroeville Data Center (Fort Monroe Industrial Park)," updated November 4, 2026, https://suedatacenters.org/data-centers/decimal-digital-monroeville-huron-oh.

Facility data from Compute Atlas (E. Kubiak), version 1.35.1 (November 2, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/decimal-digital-monroeville-huron-oh, retrieved November 5, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.A small Huron County village is weighing a big data center, with voter sentiment on the ballot · News 5 Cleveland · retrieved November 4, 2026
  2. 2.Ohioans overwhelmingly pass data center bans, restrictions on ballot · Cincinnati Enquirer (via Yahoo News) · retrieved November 4, 2026

Is a data center disrupting your home?

Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.

  • Tell us about your situation
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us