Centersquare PHX3 is an operating data center in Mesa, Arizona (Maricopa County), operated by Centersquare (Cyxtera/Evoque).
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Operating
- Operator
- Centersquare (Cyxtera/Evoque)
- Facility type
- Data center
- Location
- 1301 West University Drive, Mesa, Maricopa County, AZ, 85201
- Coordinates
- 33.4213, -111.8590
- Power capacity
- Not established from a public source
- Land
- Not established from a public source
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Reported by at least one credible outlet or filing
Opposition and litigation at this site
Nothing on record as of October 28, 2026. No lawsuit, organized opposition, or contested hearing over Centersquare PHX3 in Mesa, Maricopa County, Arizona appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Notes on the record
Operator's own directory (csquare.com/data-centers/phoenix) lists two distinct Phoenix-market facilities: PHX1 (Phoenix proper, ~40,456 sqft, 13.3 MW of UPS capacity) and PHX3 (Mesa, 1301 W University Dr, ~154,000 sqft total / 50,256 sqft raised floor, 17.3 MW of utility power alongside 8 MW of UPS capacity and 11.5 MW of generator capacity; as of October 2026, no IT capacity is stated, so none is recorded). The OSM candidate's name 'PHX1 - Mesa' conflates the two -- the Mesa facility is officially PHX3, not PHX1. Corrected the official name accordingly. Confirmed via csquare.com directory + corroborated by datacenters.com and PeeringDB listings for Centersquare PHX3 at the same address.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- Land area
- How the community has received it
- Which utility serves it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Digital Realty PHX (Tempe) · Tempe · Digital Realty6 mi · Operating · 33.8 MW
- Iron Mountain AZP-3 · Phoenix · Iron Mountain7 mi · Operating · 36 MW
- Iron Mountain AZP-1 · Phoenix · Iron Mountain7 mi · Operating
- Iron Mountain AZP-2 · Phoenix · Iron Mountain7 mi · Operating
- STACK Infrastructure PHX02 Campus · Phoenix · STACK Infrastructure8 mi · Under construction · 250 MW
- phoenixNAP PHX02 · Phoenix · phoenixNAP9 mi · Under construction · 50 MW
- Digital Realty PHX15 · Chandler · Digital Realty10 mi · Operating
- CyrusOne Chandler Campus (PHX1-PHX8) · Chandler · CyrusOne10 mi · Operating · 169 MW
Questions people ask about this site
Is there opposition to the Centersquare PHX3 data center in Mesa?
Nothing on record as of October 28, 2026. No lawsuit, organized opposition, or contested hearing over Centersquare PHX3 in Mesa, Maricopa County, Arizona appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the Centersquare PHX3 data center?
No lawsuit over Centersquare PHX3 appears in the record we track as of October 28, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Centersquare PHX3 use?
No water withdrawal figure for Centersquare PHX3 is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Centersquare PHX3, and how big is it?
Centersquare (Cyxtera/Evoque) is the operator on record. We hold 15 sites for that company across the registry. No capacity figure is on record for this site.
How to cite this page
SueDataCenters.org Data Center Registry, "Centersquare PHX3," updated October 28, 2026, https://suedatacenters.org/data-centers/centersquare-phx3-az.
Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/centersquare-phx3-az, retrieved October 29, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Centersquare (Cyxtera/Evoque) facility directory · Centersquare (Cyxtera/Evoque) · retrieved July 22, 2026
- 2.OpenStreetMap way/543117031 · OpenStreetMap · retrieved July 22, 2026
Is a data center disrupting your home?
Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.
- Tell us about your situation
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us