Sue Data Centers

Data Center Registry

Bitzero Nekoma Data Center (Stanley R. Mickelsen Safeguard Complex)

Nekoma, Cavalier County, North Dakota · All 2 Bitzero sites

OperatingNo reception on recordRecord updated October 10, 2026

Bitzero Nekoma Data Center (Stanley R. Mickelsen Safeguard Complex) is an operating crypto mining site in Nekoma, North Dakota (Cavalier County), operated by Bitzero. The public record puts it at announced July 25, 2022, 300 MW planned, a reported $500 million investment.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Operating

Operator
Bitzero
Facility type
Crypto mining
Location
Nekoma, Cavalier County, ND
Coordinates
48.5894, -98.3567
Power capacity
2.5 MW operating; 300 MW planned
Land
Not established from a public source
Investment
$500 million
Announced
July 25, 2022
Utility
Not established from a public source
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
50 permanent
Public subsidy
Not established from a public source
Community reception
No reception on record
Source confidence
Reported by at least one credible outlet or filing

Opposition and litigation at this site

Nothing on record as of October 10, 2026. No lawsuit, organized opposition, or contested hearing over Bitzero Nekoma Data Center (Stanley R. Mickelsen Safeguard Complex) in Nekoma, Cavalier County, North Dakota appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.

A new status, a permit, a reception finding, or a lawsuit. Nothing else, ever.

Notes on the record

Bitzero acquired the Cold War-era Stanley R. Mickelsen Safeguard Complex ('the Pyramid') near Nekoma, Cavalier County, ND from the Cavalier County Job Development Authority (signed July 2022, closed Dec 2022) and is redeveloping the ~184-193 acre site into a data center, up to $500M planned. Bitzero's June 2025 press release states 2.5MW currently live, 30MW prepped, up to 300MW potential. A Feb 2024 Bleeding Heartland investigation flagged due-diligence concerns (2023 CEO resignation, foreign-ownership ties, unpaid CCJDA bills); site is real and multi-source confirmed, but self-reported operational MW is company-sourced, hence confidence=reported. ~90mi NW of Grand Forks in Cavalier County (built to defend Grand Forks AFB).

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Land area
  • How the community has received it
  • Which utility serves it
Which document closes each gap
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Land area
The rezoning application, the plat, or the deed recorded with the county.
How the community has received it
Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Tell us about your situation

Living near Bitzero Nekoma Data Center (Stanley R. Mickelsen Safeguard Complex)?

Tell us the basics. Where a participating attorney in your state is available, we may share your information with them with your consent. Free, no obligation, and no guarantee anyone will contact you.

Questions people ask about this site

Is there opposition to the Bitzero Nekoma Data Center (Stanley R. Mickelsen Safeguard Complex) in Nekoma?

Nothing on record as of October 10, 2026. No lawsuit, organized opposition, or contested hearing over Bitzero Nekoma Data Center (Stanley R. Mickelsen Safeguard Complex) in Nekoma, Cavalier County, North Dakota appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

Has anyone filed a lawsuit over the Bitzero Nekoma Data Center (Stanley R. Mickelsen Safeguard Complex)?

No lawsuit over Bitzero Nekoma Data Center (Stanley R. Mickelsen Safeguard Complex) appears in the record we track as of October 10, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Bitzero Nekoma Data Center (Stanley R. Mickelsen Safeguard Complex) use?

No water withdrawal figure for Bitzero Nekoma Data Center (Stanley R. Mickelsen Safeguard Complex) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Bitzero Nekoma Data Center (Stanley R. Mickelsen Safeguard Complex), and how big is it?

Bitzero is the operator on record. We hold 2 sites for that company across the registry. Capacity on record is 300 MW.

How to cite this page

SueDataCenters.org Data Center Registry, "Bitzero Nekoma Data Center (Stanley R. Mickelsen Safeguard Complex)," updated October 10, 2026, https://suedatacenters.org/data-centers/bitzero-nekoma-nd.

Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/bitzero-nekoma-nd, retrieved October 29, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Burgum: Bitzero signs agreement to acquire Nekoma pyramid, develop it into highly secure data center · North Dakota Office of the Governor · retrieved August 5, 2026
  2. 2.Bitzero Announces Expansion of Global Data Center Network · PR Newswire (Bitzero) · retrieved August 5, 2026 · original offline, archived copy from October 1, 2026
  3. 3.North Dakota Bitzero project raises management, ownership questions · Bleeding Heartland · retrieved August 5, 2026
  4. 4.Bitzero to Redevelop Cold War-Era Missile Defense Site in North Dakota into Secure Data Center for $500M · REBusinessOnline · retrieved October 10, 2026
  5. 5.Cold-War missile defense site heats up state's data center economy, onsite gardens · Route Fifty · retrieved October 10, 2026

Is a data center disrupting your home?

Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.

  • Tell us about your situation
  • Independent attorneys
  • No obligation