Stopping a Project
The Hermantown File: Two Years of NDAs, a Recorder in the Trash, a Police Chief on Tape, and a Chamber Endorsement From a Board Whose Vice Chair Works for the Utility Selling Google the Power
Small businesses are quitting the Duluth Area Chamber of Commerce over its endorsement of Google's Hermantown data center. That is the news. This is the record behind it: a city administrator's September 2024 email, nondisclosure agreements signed by 22 county employees and three commissioners, a comprehensive plan rewritten without its steering committee, a mayor who threw a reporter's recorder in the trash, a police chief recorded calling opponents names, a utility whose witness told regulators it had no data center plans while its own executive now sits as vice chair of the chamber board that endorsed the project, and an $80 million tax abatement the city says it will spend paying Google back.
Key Takeaways
- On September 1, 2026 the Duluth Area Chamber of Commerce formally endorsed Google's proposed data center in Hermantown. By September 4, Zenith Bookstore, Townline Farms and Stable and Northern Waters Float Center had quit. "We had no input and we had no notice," Zenith's Sarah Brown told Northern News Now. The Chamber's response: memberships "ebb and flow constantly."
- The Chamber's board, as listed on its own website dated August 31, 2026, has as its vice chair Jennifer Cady of Minnesota Power, an ALLETE company. Minnesota Power holds the electric service agreement with Google and is the source of the "$600 million to $800 million" customer savings figure the Chamber cited. Cady is the Minnesota Power executive quoted defending that agreement in March: "We can serve this new Google facility without harming other customers." The board chair, Pat deGrood, is a vice president at The Jamar Company, a mechanical contractor owned by APi Group, whose Mission Critical division builds hyperscale data centers. We found no record of Jamar on this project and do not suggest one.
- The city knew what this was for a year before it told anyone. On September 18, 2024, City Administrator John Mulder wrote colleagues: "Data center next to MN Power substation. 1 billion investment 50+ full time jobs. [The mayor's] response was 'wow.'" The same email says "MN Power introduced this project to us." The public learned it was a data center on September 23, 2025, from a Braun Intertec letter obtained by the Minnesota Star Tribune through a records request filed the previous spring. The city's environmental review had called it a "communication services facility."
- Nondisclosure agreements with the developer Mortenson were signed by Mulder, his assistant, 22 St. Louis County employees, three county commissioners (Annie Harala, Keith Musolf and Keith Nelson) and the regional sanitary district, per the Star Tribune and Racket. A county motion to ban such NDAs died in October 2025 for lack of a second. Google announced on August 17, 2026 that it was "mutually agreeing to terminate all nondisclosure agreements with city officials," 23 months after the first one.
- Six months before the sale of Minnesota Power's parent to BlackRock's Global Infrastructure Partners and the Canada Pension Plan was approved, a Minnesota Power financial planning manager, Joshua Taran, told the Public Utilities Commission on March 4, 2025 that the company "does not have any specific plans related to data centers." The PUC approved the $6.2 billion sale on October 3, 2025 over an administrative law judge's recommendation against it. On February 19, 2026 it declined to reopen the record, saying data center questions belong in separate cases.
- The deal on the table: an 85 percent property tax abatement for 28 years, capped at $80 million in 2052 dollars (about $33.5 million in present value, per Hoodline), on a $650 million first phase promised at 40 to 100 permanent jobs. Google would build $130 million of water, sewer and road infrastructure and hand it to the city. Mulder's own description: "the taxes that they're paying are being paid to us, and we're paying them back for the infrastructure they're giving to us."
- The record of conduct is the story the endorsement skipped. Mayor Wayne Boucher threw Duluth Monitor reporter John Ramos's voice recorder in a trash can at a September 2025 meeting. County Commissioner Keith Nelson told the same reporter "I don't give a shit what you think." In August 2026 recordings of a June staff meeting caught Police Chief Jim Crace calling one opponent an "idiot" with a profane pun on his name, another "the Native chick" and a "Gong Show," and commenting on a council candidate crying. Four residents were removed from Google's August 19 open house after asking whether questions were being screened.
In this article
Northern News Now's Kyre Johnson reported the news on September 4: two small businesses severed ties with the Duluth Area Chamber of Commerce after it endorsed Google's proposed Hermantown data center, and one owner called it "a devastating betrayal." That story is accurate and it is the right place to start. This page is what comes after the news: the record, in order, of how a 234 acre wooded corner of a town of 10,000 came to be under purchase agreement to a Google subsidiary named Harmony Group LLC before most of its neighbors knew what was being built. It is assembled from city emails released under the Minnesota Data Practices Act, county property records, Public Utilities Commission filings, two lawsuits, the Chamber's own board page, and reporting by the Minnesota Star Tribune, MPR, KAXE, the Duluth News Tribune, WDIO, Northern News Now, Racket and the Duluth Monitor, whose reporter had his recorder thrown in the trash by the mayor for doing this work. Every fact is sourced below. Where we draw a connection nobody else has drawn, we say so, and we say exactly how far the documents take it and no further.
Updated September 5, 2026, and how to read this page
Updated: September 5, 2026. Every date, dollar figure, vote tally and quotation below was checked against the source listed at the bottom of this page on that date. Where a fact comes from a single outlet, we name it in the sentence. Where a fact comes from a document, we describe the document.
How to cite this page: SueDataCenters.org, "The Hermantown File," updated September 5, 2026, https://suedatacenters.org/guides/hermantown-google-data-center-what-the-records-show.
One rule governs the sections on people. We report what officials did and said as documented, and what roles they hold as listed on public pages. We do not allege motive, and we do not allege that any contract, payment or benefit flowed from any of the overlaps described below. Where the record would support a question, we ask it. Where it would not, we stop.
The endorsement and the exodus, September 1 to 4, 2026
On Tuesday, September 1, the Duluth Area Chamber of Commerce announced it had "formally adopted a resolution supporting the proposed Google Data Center Project in Hermantown." Board Chair Pat deGrood said the project "represents a significant investment not only in technology and economic development, but in the infrastructure and community assets that will support future growth." Interim President Jim Roche added that "energy and environmental considerations are appropriately part of the conversation."
The Chamber's reasons, as it gave them to Northern News Now, included: no cost shifting to other electric customers because "it is illegal for such cost shifting to take place per Minnesota state law"; Minnesota Power's estimate that other customers "will save between $600 million to $800 million over the life of their 15-year contract"; "at least 40 permanent jobs" and "approximately 1,100 jobs per year"; property tax payments to Hermantown rising from $28,000 to $80,000 a year today to $448,000 to $800,000 a year when operational; and Google's "estimated $130 million toward new public infrastructure."
By Friday, September 4, at least three member businesses had left:
- Townline Farms and Stable, which connects people with disabilities to horses a few miles from the site. Owner Jill Dryke, a member for three years: "My first reaction was deceit, I was devastated." On the horses: "they can feel vibrations on the ground, and they can hear miles away." She is moving to the Cloquet Chamber. To WDIO: "I took my plaque down today. It was hard. It was sad."
- Zenith Bookstore. Owner Sarah Brown: "We were pretty disappointed when we originally saw the statement. We had no input and we had no notice." Overnight the store received a wave of online orders. "If they're not representing the interests of small businesses, then people should rethink if this is a good fit for them."
- Northern Waters Float Center. Owner Liz Prosnick, to WDIO: "I wasn't seeing the ROI, I'm a very small business, it's just me."
Crow and Co. Books and SISU Beauty Co., which had left earlier, publicly supported the departures. The Chamber's interim president was not available for an interview. The written statement said the Chamber "is aware of a handful of members expressing disappointment" and that "memberships in any organization like the Chamber ebb and flow constantly."
Dryke's request was specific: "They opened up Pandora's box, and they have a small window of gray opportunity to fix this and rescind it."
Who sits on the board that endorsed it
This is the section nobody else has written, and it is drawn entirely from the Chamber's own website.
The Duluth Area Chamber of Commerce's board of directors page, dated August 31, 2026, lists its executive committee. The vice chair is Jennifer Cady, Minnesota Power, an ALLETE Company. Cady is Minnesota Power's vice president for regulatory and legislative affairs, and previously vice president of public policy and external affairs at ALLETE, per her professional listings and press coverage. Minnesota Power is the utility that signed the electric service agreement with Google for this project, the party that filed it with the Public Utilities Commission on March 26, 2026, and the source of the "$600 million to $800 million" customer benefit figure the Chamber's endorsement relies on. When Google's identity was announced on March 3, 2026, Cady was the Minnesota Power executive quoted in the Duluth News Tribune: "We can serve this new Google facility without harming other customers."
The board chair is Pat deGrood, vice president of commercial services at The Jamar Company. Jamar is a Duluth mechanical contractor, HVAC, plumbing, industrial construction and specialty fabrication, owned by APi Group. APi Group's Mission Critical division describes itself as delivering "large, high-tech hyperscale data centers." We searched for and found no record connecting Jamar or APi to the Hermantown project, and we do not suggest one exists. We note the chair's industry because the Chamber's statement describes its support as "absolutely in keeping with its strategic priorities" without describing who set them.
Two more names from the record. Annie Harala, the St. Louis County Board chair who signed a Mortenson NDA, appeared on the Chamber's 2024 board per its Form 990; she is not on the August 2026 board page. And the Chamber's statement, as reported by Northern News Now, WDIO and FOX21, does not mention that its vice chair works for the utility whose numbers it quotes. Neither does the board page. We are connecting the two.
What this does and does not show. It shows that the organization telling Duluth's small businesses that the electricity math is settled has, in its second-ranking volunteer seat, the executive responsible for that math at the company that will be paid under it. It does not show that Cady voted, drafted or recused; the Chamber has not said how the resolution was adopted, and we asked no one to speculate. The question for the Chamber's members is whether they were told.
The $800 million, and the witness who said there were no plans
The Chamber's strongest argument is that the project lowers everyone else's bills. The claim has a paper trail, and the paper trail has a problem.
The number. Minnesota Power's March 26, 2026 filing with the Public Utilities Commission says that once the project is "fully permitted and operational," existing customers would see "an estimated range of $600 million to $800 million in benefit over the 15-year ESA term," expressed as a 15-year net present value, with a "holistic future cost decrease for existing customers up to $15/MWh annually." The mechanism, per Minnesota Power's March 16 presentation to the Hermantown council by Vice President Frank Frederickson, is that "large industrial loads spread fixed costs," citing a Lawrence Berkeley National Laboratory and Brattle Group study. The presentation also states, in bold, that Google funds new infrastructure, that the 2025 state law means costs of serving new large customers "cannot be passed on to other utility customers," and that the ESA "enables 700 megawatts of new clean energy resources (wind and battery storage) without increasing costs to existing customers."
The law. The 2025 statute created a "very large customer" class at 100 megawatts and above, and requires their service agreements to cover the full cost of service and system upgrades, to avoid burdening other customers if the facility downsizes or closes, and to comply with the state's carbon-free standard, per the Minnesota Reformer's Brian Martucci. The statute is real. Whether it is met depends on how the utility forecasts its costs, which is the unresolved fight. Attorney General Keith Ellison's office called Xcel's proposed forecasting process for the same customer class "opaque" and warned that "contract provisions cannot fully protect other customers unless (Xcel) ensures that new very large customers are covering their actual, not hypothetical, costs." Will Kenworthy of Vote Solar: "We haven't actually seen the agreement yet, and until we do, the devil will be in the details." Google itself asked the commission to scrap Xcel's incremental cost test. The Chamber's "illegal" is a statute. The savings figure is a forecast by the party being paid.
The witness. Here is the part the endorsement does not mention. While the Public Utilities Commission was considering the $6.2 billion sale of Minnesota Power's parent ALLETE to Global Infrastructure Partners, a BlackRock subsidiary, and the Canada Pension Plan Investment Board, Minnesota Power financial planning manager Joshua Taran testified on March 4, 2025 that the company "does not have any specific plans related to data centers," per the Duluth News Tribune's Peter Passi. Public records later released by Hermantown include a September 18, 2024 email from City Administrator John Mulder stating that "MN Power introduced this project to us." The environmental group CURE petitioned on December 30, 2025 to reopen the sale record. Minnesota Power spokesperson Amy Rutledge said Taran's testimony was "being taken out of context" and that no data center had been approved. The PUC approved the sale on October 3, 2025, over Administrative Law Judge Megan McKenzie's July recommendation that it would "likely cause higher electrical rates for consumers," imposing a one-year rate freeze and return-on-equity limits through 2030. On February 19, 2026 the commission denied CURE's petition and said data center issues could be addressed in separate cases. CURE's legal director Hudson Kingston: "It's not a smoking gun. It's the fact that there's clearly some information that hasn't been disclosed that could show a conflict of interest."
The utility that introduced the project to the city, that told regulators it had no specific data center plans while the city's administrator was writing "wow," that was then sold to private equity, and whose vice president now sits as vice chair of the chamber vouching for its savings estimate, is the same utility. That is the chain the documents support. We draw it no further.
Two years in the dark: the timeline from the records
| Date | What the record shows | Source |
|---|---|---|
| Sept. 18, 2024 | City Administrator John Mulder emails colleagues: "Data center next to MN Power substation. 1 billion investment 50+ full time jobs. [The mayor's] response was 'wow.'" The email states "MN Power introduced this project to us." Mulder has signed a Mortenson NDA. | Racket; Duluth News Tribune (Jan. 10, 2026) |
| Sept. 2024 | Chad Ronchetti starts as Hermantown's economic development director. The comprehensive plan steering committee had last met that summer. | Star Tribune (Apr. 29, 2026) |
| Dec. 2024 | Ronchetti emails a regional development group that the city is looking at extending sewer and water to the southwest corner for commercial development. | Star Tribune (Apr. 29, 2026) |
| Jan. 2025 | Consultant Braun Intertec writes to the city that a construction firm "intends to build a large data center complex" on 200 acres. Resident Bob Kohlmeier receives a purchase letter from Mortenson; when he asks what the project is, the answer is "Well, I can't tell you." | Star Tribune (Sept. 23, 2025); Racket |
| Spring 2025 | The comprehensive plan, altered to designate the area business and light manufacturing, goes to the Planning Commission and City Council. The second lawsuit alleges the steering committee never saw the finished plan though its members are listed on it. The Star Tribune files public records requests. | Star Tribune (Apr. 29, 2026) |
| June 2025 | First media attention to an unnamed "potential opportunity." | City of Hermantown project page |
| July 2025 | State Sen. Grant Hauschild, who co-authored the 35-year data center sales tax exemption that passed in June, meets two constituents about "data centers generally and the possible impact it would have if the Hermantown site was a Data Center." He says: "I did not sign an NDA." "We were speaking in hypotheticals." | The Northern Watch (Dec. 16, 2025) |
| Sept. 2025 | The city releases a 400-page environmental review (AUAR) describing the project as a "communication services facility." The Minnesota Pollution Control Agency comments that it lacks adequate detail. At a public meeting, Mayor Wayne Boucher throws Duluth Monitor reporter John Ramos's voice recorder in a trash can. | Star Tribune (Sept. 23, 2025); Racket |
| Sept. 23, 2025 | The Star Tribune publishes the Braun letter. Ronchetti confirms Mortenson is the developer and says the "best-case scenario" is a 2026 groundbreaking and up to 200 jobs. Hermantown, St. Louis County and the sanitary district have all signed NDAs with Mortenson. | Star Tribune |
| Oct. 14 to 15, 2025 | County Commissioner Ashley Grimm's motion to ban officials from signing NDAs fails for lack of a second. Commissioners Harala, Musolf and Nelson have signed. Grimm: "ashamed of what just happened here." Kohlmeier: "We planted 10,000 pine trees on our property, and we're investing in the land, and now no one will talk to us? I feel betrayed by these NDAs." Nelson, to the Monitor's reporter: "I don't give a shit what you think." | Star Tribune (Oct. 15, 2025); Racket |
| Oct. 17, 2025 | Residents petition the Environmental Quality Board for a fuller environmental review. | City project page |
| Oct. 20, 2025 | More than 300 people fill City Hall. Nearly 70 speak over four hours, mostly opposed. The council rezones the land unanimously with little discussion. Chants of "shame, shame, shame." Councilor Brian LeBlanc says the vote "wasn't approval of the project." The mayor says no councilor signed an NDA. | Star Tribune (Oct. 21, 2025) |
| Nov. 5, 2025 | MCEA and Stop the Hermantown Data Center sue (St. Louis County District Court No. 69DU-CV-25-3448), alleging the AUAR omitted water, electricity, air, light, noise and cumulative impacts and never said it was a data center. | MCEA; KAXE |
| Nov. 10, 2025 | Mortenson withdraws its permit applications "to allow for further public engagement." | City project page |
| Dec. 30, 2025 | CURE petitions the PUC to reopen the ALLETE sale over the undisclosed data center discussions. | KAXE (Jan. 7, 2026) |
| Late Jan. 2026 | Harmony Group LLC, a Google subsidiary, pays nearly $6 million to three residents for land the county assesses at $1.9 million. | Star Tribune (Mar. 2026) |
| Feb. 19, 2026 | The PUC declines to reopen the sale. | KAXE (Feb. 24, 2026) |
| Mar. 3, 2026 | Google announces it is the end user. Code name: Project Loon. $650 million first phase; 700 MW of wind and storage; $5 million for affordability programs. | MPR; KAXE |
| Mar. 12 to 16, 2026 | The city restarts the AUAR with Google. Minnesota Power presents the ESA's customer protections to the council. | City project page; MP presentation |
| Apr. 29, 2026 | Second lawsuit: spot zoning, a comprehensive plan drafted "in secret and in bad faith," three improperly closed meetings, public data defined as confidential. About 70 homeowners face "a large reduction" in value, it alleges. | Star Tribune |
| May 4, 2026 | After hours of testimony in a packed chamber, the council tables the abatement and development agreements pending environmental review and the lawsuits. Resident Allison Hafften on the abatement: "That's pocket lint to them." | MPR (May 5, 2026) |
| June 2026 | A recorded internal staff meeting captures department heads discussing opponents by name. | Duluth Monitor (Aug. 12, 2026); WDIO; DNT |
| Aug. 6 and 12, 2026 | The Duluth Monitor reports that officials considered preparing scripts for councilors to use at a data center meeting, and that department heads meet the day after council meetings to "grade" them, disparaging opponents. | Duluth Monitor |
| Aug. 17, 2026 | Police Chief Jim Crace: "The comments I made were inappropriate, disrespectful and uncalled for." Mayor Boucher: "This is not an acceptable way to do the people's business." Mulder: "Words aren't enough." Google's Tyler Huebner announces the company is "mutually agreeing to terminate all nondisclosure agreements with city officials." The mayor says an outside entity will investigate. | Duluth News Tribune; WDIO |
| Aug. 19, 2026 | At Google's open house, Jonathan Thornton and three others are removed after Thornton asks whether submitted questions are being screened. His question: "Does that behavior fit the Google ethical standard." Google: "We made every effort to address questions." | Northern News Now (Aug. 20, 2026) |
| Aug. 20, 2026 | Google shrinks the plan to 1.66 million square feet and three buildings, 300 to 600 megawatts, 16 generators. Huebner: "We've been listening." Resident Jeffrey Donahue: "Go away, Google." | Star Tribune |
| Sept. 1, 2026 | The Duluth Area Chamber endorses the project. | WDIO; Northern News Now |
| Sept. 4, 2026 | Members resign. "A devastating betrayal." | Northern News Now |
What the deal actually says
The agreements were posted by the city in April 2026 and presented on May 4. The terms, from KAXE's Larissa Donovan, MPR, Hoodline and the city's presentations:
| Term | Figure |
|---|---|
| Site | 234 acres (278 in the AUAR study area) in Hermantown's southwest corner, adjacent to Proctor and Duluth, beside Minnesota Power's Arrowhead substation. All property under purchase agreement or already transferred to a Google subsidiary. |
| Build | First phase $650 million; about $2 billion over three phases and 8 to 10 years. Revised August 2026 to 1.66 million square feet in three buildings, 300 to 600 megawatts, 16 backup generators. |
| Property tax abatement | 85 percent of taxes after the first $100,000, for 28 years, capped at $80 million. "That $80 million is the future value of money, the value of money in 2052," Ronchetti told KAXE. Present value about $33.5 million, per Hoodline. Resident Dawn LaPointe: "What tax-based projections would allow a tax abatement of $4 million a year for a single company?" |
| What the city gets | About $12 million in new property tax over 20 years plus $4.5 million from Google; roughly $448,000 a year in property tax once the abatement runs; about $150,000 in year one. |
| What the schools get | About $40 million over 28 years in taxes and cash; $850,000 upfront to ISD 700. |
| Infrastructure | Google builds about $130 million of water, sewer and road systems to city specification and transfers them to Hermantown. Mulder, to Hoodline: "What's really happening here is: the taxes that they're paying are being paid to us, and we're paying them back for the infrastructure they're giving to us." |
| Jobs | "At least 40 permanent jobs" (Chamber); about 100 (city, per MPR); up to 2,000 construction jobs over the build. In September 2025 Ronchetti had said up to 200. |
| Water | Air-cooled; up to 50,000 gallons a day for sanitation and fire suppression, "roughly equivalent to a large car wash" (Chamber). The MCEA suit disputes the estimate against comparable facilities. |
| Power | 15-year electric service agreement under Minnesota Power's Large Power schedule; 300 MW wind and 400 MW battery storage; $5 million to affordability programs; PUC comment period closed July 21, 2026. |
Set the Chamber's "$448,000 to $800,000 per year" against Mulder's sentence. The city's own administrator describes the arrangement as tax revenue that is paid to the city and paid back to Google. The Chamber's statement presents the same money as an increase.
The people in the record
Bob Kohlmeier owns land bordering the site. Mortenson offered to buy it in January 2025 and would not tell him what for. "I put 50 years into this. We planted 10,000 pine trees on our property." To Racket: "We don't want to live in the shadow of something we don't know anything about, and we don't trust this government anymore because of their NDAs."
Jill Dryke runs Townline Farms and Stable, which serves people with disabilities. Her horses are the reason she quit the Chamber: "Horses are like dolphins, they can feel vibrations on the ground." Her line about the Chamber, "they want to take my horses to the slaughterhouse," is the one Northern News Now led with.
Jonathan Thornton sat on the comprehensive plan steering committee. He says the committee never saw the finished plan, though its members are listed on it as if they had. He was removed from Google's open house for asking whether questions were screened.
Emma Richtman is the spokeswoman for Stop the Hermantown Data Center and a candidate for City Council. She was the subject of the police chief's recorded comment about crying at a meeting. "The city keeps telling us NDAs are standard practice, but this is not a standard development, this is unprecedented."
Jim Klukkert was the opponent the chief called an "idiot" with a profane variation of his name. He accepted the apology and noted, per the Duluth News Tribune, "There are no Fs in my name."
Ashley Grimm, the county commissioner whose NDA ban could not get a second: "I'd never heard of local elected officials signing non-disclosure agreements with companies."
Jane Kirtley, media law and ethics professor at the University of Minnesota, on the NDAs, to Racket: "Extremely problematic. Many of them are willing to sign their lives away in order to lure businesses to their area."
Jack Carlson of the Duluth Building Trades Council, for the project: "The ability for the Duluth building trades to stay home and eat dinners with their family... is an amazing opportunity." Joe Pike, a supporter: "a generational opportunity." Those voices are real and the construction jobs are real. They are also the only local benefit in the record that does not depend on a forecast.
What is unresolved, and the dates to watch
- The environmental review. The updated AUAR was submitted to the Environmental Quality Board on August 4, 2026; state agency comments were due the last week of August; the City Council must adopt it before any permit. The MCEA suit is paused pending the result. If the redo is inadequate, MCEA says it may file again. A Google representative told the open house that an environmental impact statement, the state's strongest review, was not done because "not enough project details were known then."
- The electric service agreement. Before the PUC, comments closed July 21, 2026. The commission is separately deciding the very large customer tariff that will govern how costs are forecast. That decision, not the Chamber's statement, determines whether the "$600 million to $800 million" is a floor, a ceiling or a hope.
- The abatement and development agreements. Tabled May 4, 2026. No date set.
- The spot zoning suit. Filed April 29, 2026; seeks to set aside the comprehensive plan and land use decisions in the project area.
- The outside investigation. The mayor said on August 17 that an outside entity would investigate the recorded remarks. No findings have been released.
- The election. A council candidate is the opposition's spokeswoman. Opponents are also gathering support for a charter commission. "There's really a lack of responsiveness from the city," Greg Rosenberg told Northern News Now on August 23.
- The NDA ban. HF 4077, the bipartisan bill to bar local officials from signing NDAs, passed two Senate committees and died on a tie vote in the House Judiciary Committee in April 2026. It was written because of Hermantown.
- The state senator. Sen. Grant Hauschild of Hermantown co-authored the 35-year data center sales tax exemption signed in June 2025. He met constituents about a possible Hermantown data center the following month, says the talks were "hypotheticals," and says he did not sign an NDA.
Frequently asked questions
Why did businesses leave the Duluth Area Chamber of Commerce?
The Chamber endorsed Google's proposed Hermantown data center on September 1, 2026 without, members say, any notice or input. Zenith Bookstore, Townline Farms and Stable and Northern Waters Float Center resigned by September 4. Townline's owner, whose therapy horses are a few miles from the site, called it "a devastating betrayal."
Is the Chamber's vice chair really a Minnesota Power executive?
Yes, according to the Chamber's own board of directors page dated August 31, 2026, which lists Jennifer Cady, Minnesota Power, an ALLETE Company, as vice chair. Minnesota Power is the utility with the Google electric service agreement and the source of the $600 million to $800 million savings estimate the Chamber cited. We do not know whether she participated in the endorsement vote; the Chamber has not said how it was adopted.
Did Hermantown officials sign NDAs with the data center developer?
Yes. City Administrator John Mulder, his assistant, 22 St. Louis County employees, three county commissioners and the Western Lake Superior Sanitary District signed nondisclosure agreements with Mortenson, per the Minnesota Star Tribune and Racket. Google announced on August 17, 2026 that it was terminating all NDAs with city officials. The mayor has said no council member signed one.
What is the tax abatement Google would receive in Hermantown?
An 85 percent property tax abatement, after the first $100,000, for 28 years, capped at $80 million measured in 2052 dollars, about $33.5 million in present value. Google would build about $130 million of infrastructure and transfer it to the city. The city administrator has described the arrangement as taxes paid to the city and paid back to Google for the infrastructure.
Will the Google data center raise electric bills in the Duluth area?
A 2025 Minnesota law requires very large customers to cover their full cost of service, and Minnesota Power projects $600 million to $800 million in benefit to other customers over 15 years. Whether the law is met depends on cost forecasting that the Attorney General's office has called "opaque" in the parallel Xcel proceeding. The Public Utilities Commission has not yet ruled on the agreement.
What did the Hermantown police chief say on the recording?
Per the Duluth News Tribune and WDIO, summarizing the Duluth Monitor's reporting on a June 2026 staff meeting recording, Chief Jim Crace called one opponent an "idiot" with a profane pun on his name, referred to another as "the Native chick" and a "Gong Show," and commented on a council candidate crying at a meeting. He apologized on August 17, 2026: "The comments I made were inappropriate, disrespectful and uncalled for."
Article sources
Our editorial standards require primary sources: government publications, regulator data, company filings, and established industry research.
- 1.Northern News Now, Kyre Johnson, "'A devastating betrayal': Small businesses cut ties with Duluth Chamber over Hermantown data center endorsement" (September 4, 2026)
- 2.WDIO, "Duluth Chamber backs Hermantown Google data center project"
- 3.WDIO, "Small businesses withdrawing from Duluth Chamber of Commerce"
- 4.Duluth Area Chamber of Commerce, Board of Directors (page dated August 31, 2026)
- 5.ProPublica Nonprofit Explorer, Duluth Area Chamber of Commerce, EIN 41-0225910 (Form 990 director listings)
- 6.APi Group, "Jamar Company"
- 7.APi HVAC, Mission Critical and hyperscale data center services
- 8.Duluth News Tribune, "Google behind proposed Hermantown data center" (March 2026), quoting Jennifer Cady
- 9.Minnesota Power, Electric Service Agreement with Google, PUC filing (March 26, 2026), mirrored by Legalectric
- 10.Minnesota Power, "Update: Google Electric Service Agreement," presentation to Hermantown City Council by Frank Frederickson (March 16, 2026)
- 11.Minnesota Reformer, Brian Martucci, "With new law in effect, data centers shouldn't mean higher electric bills for the rest of us" (March 27, 2026)
- 12.Duluth News Tribune, Peter Passi, "Group says Minnesota Power too coy about Hermantown data center" (January 10, 2026)
- 13.Northern News Now, Sophia Lauber, "Environmental group challenges ALLETE acquisition approval over data center disclosure" (January 13, 2026)
- 14.KAXE, Megan Buffington, "Hermantown data center prompts petition to reconsider Minnesota Power sale" (January 7, 2026)
- 15.KAXE, "State commission declines petition to reconsider MN Power sale" (February 24, 2026)
- 16.CURE, "CURE petitions for reconsideration of Minnesota Power private equity takeover" (December 30, 2025)
- 17.Twin Cities Business, "Is the Allete Acquisition a Good Deal for Minnesota?"
- 18.Racket, Jay Boller, "'It's David vs. Goliath': Inside the Fight to Kill Google's Secrecy-Shrouded Hermantown Data Center" (March 18, 2026)
- 19.Minnesota Star Tribune, Jana Hollingsworth and Walker Orenstein, "Northeastern Minnesota mystery project identified as data center" (September 23, 2025)
- 20.Minnesota Star Tribune, Jana Hollingsworth, "St. Louis County leaders blasted for signing data center-related NDAs" (October 15, 2025)
- 21.Minnesota Star Tribune, Jana Hollingsworth, "Northeast Minnesota data center wins key approval as hundreds protest" (October 21, 2025)
- 22.Minnesota Star Tribune, "Google is behind the proposed Hermantown, MN, data center" (March 2026)
- 23.Minnesota Star Tribune, Jana Hollingsworth, "Opposition group sues Hermantown, alleging data center project violates zoning restrictions" (April 29, 2026)
- 24.Minnesota Star Tribune, Jana Hollingsworth, "Google scales back proposed data center in northeast Minnesota" (August 20, 2026)
- 25.MPR News, "Tech giant Google is behind controversial data center proposal in Hermantown" (March 3, 2026)
- 26.MPR News, "Hermantown tables vote on key agreements for contentious Google data center" (May 5, 2026)
- 27.KAXE, Larissa Donovan, "More details emerge as Google, Hermantown work out data center agreements" (May 20, 2026)
- 28.Hoodline, Jordan De La Cruz, "Google sweetens Hermantown data center deal with cash and infrastructure" (April 26, 2026)
- 29.City of Hermantown, project page with AUAR documents, agreements and presentations (updated August 25, 2026)
- 30.Minnesota Center for Environmental Advocacy, "RELEASE: Hermantown Data Center Environmental Study Appealed" (November 5, 2025)
- 31.Minnesota Center for Environmental Advocacy, "Legal updates on MCEA's data center cases" (case No. 69DU-CV-25-3448)
- 32.Duluth News Tribune, Tom Olsen, "Hermantown leaders apologize for disparaging data center critics" (August 17, 2026)
- 33.WDIO, "Hermantown police chief apologizes for offensive remarks caught on recording" (August 2026)
- 34.Duluth Monitor, John Ramos, "Hermantown officials consider preparing scripts for councilors to use during data center meeting" (August 6, 2026)
- 35.Duluth Monitor, John Ramos, "Behind closed doors, Hermantown staff disparage data center opponents" (August 12, 2026)
- 36.Northern News Now, "Hermantown resident kicked out of Google meeting speaks out" (August 20, 2026)
- 37.Northern News Now, "Stop the Hermantown Data Center looks to launch Charter Commission" (August 23, 2026)
- 38.The Northern Watch, "Hauschild Denies Signing a Data Center NDA, Says July Data Center Talks Were 'Hypothetical'" (December 16, 2025)
- 39.Minnesota Daily, "NDA ban for local municipalities and data centers stalls in the Minnesota House" (April 23, 2026)
- 40.Duluth News Tribune, "Reprimands uncovered from incoming Hermantown police chief's past" (March 21, 2011)
- 41.Stop the Hermantown Data Center
Related reading
- Ohio's Open Meetings Act Is the Best Tool Residents Have Against a Data Center, and Almost Nobody Explains the Remedies
Ohio Revised Code 121.22 invalidates a resolution adopted in violation of it, lets any person sue for an injunction, presumes irreparable harm, and awards a $500 forfeiture plus attorney fees. The deadline is two years, not ninety days. Here is the statutory text, the township zoning referendum under R.C. 519.12, and what the Ohio record actually shows.
- What Communities Give Up: Data Center Tax Abatements, Line by Line
A data center is sold to a county on a property tax number, and that number is usually reduced by a statute or a negotiated deal the public never reads. The mechanisms explained, the qualifying thresholds quoted from the Ohio, Texas, Virginia, Georgia, and Iowa statutes, real packages on record from Barber County, Kansas to Effingham County, Georgia, what the states now say the exemptions cost, and the records a resident can request.
- Who Pays for Data Center Power: The Ratepayer Tracker
The numbers behind the electric bill fight: PJM's capacity price rose from $28.92 to $333.44 per megawatt-day in three years, data centers account for $29.4 billion of the last four auctions' capacity costs by the market monitor's count, and the average PJM household faces an estimated $70 a month more by 2028. The running record of what regulators have found, which 23 states have answered with large load tariffs, what those tariffs require, and what a resident can do about a bill.
- How to Fight a Proposed Data Center Before It Breaks Ground
Approval fights are the most successful category of data center litigation. Here is the playbook: reading the rezoning file, spotting notice and open meetings defects, organizing neighbors, referendums and recalls, moratoriums, and the short appeal clocks that decide everything.
- 'Poverty, Crime and Squalor': The President Says That Is What Towns Get for Refusing a Data Center. The Records Say It Is What Some Towns Got for Approving One.
On September 4, 2026 President Trump said towns that want lower taxes and higher home values should approve data centers, and towns that refuse them will get poverty, crime and squalor. We checked each claim against state revenue reports, court filings, police crash records, utility auction data and the two housing studies that exist. Tax losses in four states now exceed a billion dollars a year each, Virginia has produced one permanent job for every $54 million invested since 2020, crashes around Meta's largest data center rose more than 600 percent in a year, and 71 percent of Americans oppose one near them.
- How Long Do You Have to Challenge a Data Center Approval? Appeal Deadlines in 12 States
The clock to challenge a data center rezoning, special use permit, or zoning board decision runs from 10 days in Texas to 90 days in Illinois. Statute by statute for 12 states, what starts the clock, which court hears it, and the standing trap that ends cases before they start. Confirm every deadline with counsel.
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us