Data Center Registry
Percheron Data Center
Boardman area (Tower Road), Morrow County, Oregon
Percheron Data Center is a data center under construction in Boardman area (Tower Road), Oregon (Morrow County), operated by Rowan Green Data (DBA Rowan Digital Infrastructure). The public record puts it at 300 MW planned, 275 acres.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Under construction
- Operator
- Rowan Green Data (DBA Rowan Digital Infrastructure)
- Facility type
- Data center
- Location
- Boardman area (Tower Road), Morrow County, OR
- Coordinates
- 45.7113, -119.8262
- Power capacity
- 300 MW planned
- Land
- 275 acres
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- PacifiCorp
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Reported by at least one credible outlet or filing
Opposition and litigation at this site
Nothing on record as of September 10, 2026. No lawsuit, organized opposition, or contested hearing over Percheron Data Center in Boardman area (Tower Road), Morrow County, Oregon appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Notes on the record
Rowan Digital Infrastructure (formerly Rowan Green Data, a Quinbrook/Birch Infrastructure JV) is developing a single unified campus on a 275-acre parcel in Morrow County, OR: four buildings totaling 1.125M sq ft, 300MW planned capacity by mid-2027. County approved rezoning Sept 2023 (East Oregonian, DCD). This is the canonical record for the campus; osm_ids 1501824327/328/329 are near-identical coordinates (within ~0.2km) almost certainly representing OSM nodes for the same single campus/buildings and are dropped as duplicates. Capacity re-sourced 2026-08-08: Rowan's own portfolio page states "300 MW" on "275AC" with phased buildout completing by 2030. Public-reception check (2026-09-10): Checked baxtel.com's project page (2026-09-10). Important correction: a Gov. Tina Kotek data-center land-sale cancellation reported elsewhere concerns a DIFFERENT project near Salem, OR (developer Verrus) -- NOT Percheron/Morrow County -- and must not be attributed to this record. No community reaction, hearing, or official statement specific to Percheron/Boardman was found; the page states only that the project is under construction with planned 2027 completion.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- How the community has received it
Which document closes each gap
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Our reporting on this site
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Amazon Boardman Exascale Data Center Campus · Boardman · Amazon Web Services11 mi · Proposed · 1 GW · Mixed reception
- DMG Blockchain Boardman Facility · Boardman · DMG Blockchain Solutions11 mi · Proposed · 3.75 MW
- AWS Hermiston Data Center Campuses · Hermiston · Amazon Web Services27 mi · Operating
- SDC Umatilla Campus · Umatilla · Sabey Data Centers28 mi · Under construction · 150 MW · Supported
Questions people ask about this site
Is there opposition to the Percheron Data Center in Boardman area (Tower Road)?
Nothing on record as of September 10, 2026. No lawsuit, organized opposition, or contested hearing over Percheron Data Center in Boardman area (Tower Road), Morrow County, Oregon appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the Percheron Data Center?
No lawsuit over Percheron Data Center appears in the record we track as of September 10, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Percheron Data Center use?
No water withdrawal figure for Percheron Data Center is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Percheron Data Center, and how big is it?
Rowan Green Data (DBA Rowan Digital Infrastructure) is the operator on record. Capacity on record is 300 MW. The site is recorded at 275 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "Percheron Data Center," updated September 10, 2026, https://suedatacenters.org/data-centers/percheron-data-center-or.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/percheron-data-center-or, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Baxtel facility profile: Rowan Percheron Data Center · Baxtel · retrieved July 22, 2026
- 2.OpenStreetMap way/1501824326 · OpenStreetMap · retrieved July 22, 2026
- 3.HIFLD Electric Retail Service Territories (ORNL/DOE-CESER, 2023-08 vintage) · Oak Ridge National Laboratory (ORNL) / HIFLD · retrieved July 23, 2026
- 4.Rowan Digital Infrastructure, Percheron: 300 MW, 275 acres · Rowan Digital Infrastructure · retrieved August 8, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us