DPO Wisconsin Rapids AI Computing Facility is a proposed data center in Wisconsin Rapids, Wisconsin (Wood County), operated by Digital Power Optimization. The public record puts it at announced January 31, 2025, 20 MW planned, a reported $200 million investment.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Proposed

Operator
Digital Power Optimization
Facility type
Data center, AI use confirmed
Location
Wisconsin Rapids, Wood County, WI
Coordinates
44.3918, -89.8229 (approximate)
Power capacity
20 MW planned
Land
Not established from a public source
Investment
$200 million
Announced
January 31, 2025
Utility
Consolidated Water Power Company
Power source
Hydro
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
No reception on record
Source confidence
Reported by at least one credible outlet or filing

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. January 31, 2025
    Proposed
    DPO announced a $200M, 20 MW AI computing development with land and firm hydro power secured through CWPCo; energization targeted for 2026. Source: PR Newswire / Digital Power Optimization

Opposition and litigation at this site

Nothing on record as of August 18, 2026. No lawsuit, organized opposition, or contested hearing over DPO Wisconsin Rapids AI Computing Facility in Wisconsin Rapids, Wood County, Wisconsin appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.

Power and water

Firm power from CWPCo (a Billerud subsidiary and regulated utility operating 32 MW of hydroelectric generation). DPO secured a land lease of up to 50 years and interconnection rights to an existing, energized substation.

Notes on the record

Pre-development funded by an investor consortium led by Salutem Capital; Stantec providing engineering support. Exact street address and acreage not disclosed in the announcement, so coordinates are the Wisconsin Rapids city geocode. Single-source, hence 'reported'.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • Land area
  • How the community has received it
Which document closes each gap
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Land area
The rezoning application, the plat, or the deed recorded with the county.
How the community has received it
Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Our reporting on this site

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the DPO Wisconsin Rapids AI Computing Facility in Wisconsin Rapids?

Nothing on record as of August 18, 2026. No lawsuit, organized opposition, or contested hearing over DPO Wisconsin Rapids AI Computing Facility in Wisconsin Rapids, Wood County, Wisconsin appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

Has anyone filed a lawsuit over the DPO Wisconsin Rapids AI Computing Facility?

No lawsuit over DPO Wisconsin Rapids AI Computing Facility appears in the record we track as of August 18, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does DPO Wisconsin Rapids AI Computing Facility use?

No water withdrawal figure for DPO Wisconsin Rapids AI Computing Facility is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates DPO Wisconsin Rapids AI Computing Facility, and how big is it?

Digital Power Optimization is the operator on record. Capacity on record is 20 MW.

How to cite this page

SueDataCenters.org Data Center Registry, "DPO Wisconsin Rapids AI Computing Facility," updated August 18, 2026, https://suedatacenters.org/data-centers/dpo-wisconsin-rapids-hpc-wi.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/dpo-wisconsin-rapids-hpc-wi, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.DPO Launches $200 Million AI Data Center Development in Partnership with Billerud · PR Newswire / Digital Power Optimization · retrieved August 18, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us