CoreWeave Dalton II / Core Scientific Old Tilton Road Data Center
Dalton, Whitfield County, Georgia · All 10 Core Scientific sites
CoreWeave Dalton II / Core Scientific Old Tilton Road Data Center is a data center under construction in Dalton, Georgia (Whitfield County), operated by Core Scientific. The public record puts it at 173.3 acres, a reported $1.2 billion investment. It has documented support and documented opposition on record.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Under construction
- Operator
- Core Scientific
- Facility type
- Data center
- Location
- Dalton, Whitfield County, GA
- Coordinates
- 34.6927, -84.9418
- Power capacity
- Not established from a public source
- Land
- 173.3 acres
- Investment
- $1.2 billion
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- Mixed reception
- Source confidence
- Confirmed by multiple independent sources or official documentation
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- June 4, 2026Under constructionunder construction per Whitfield County Board of Commissioners rezoning vote, Old Tilton Road (Core Scientific) Source: Dalton Daily Citizen
Opposition and litigation at this site
Partly. Both documented support and documented opposition to CoreWeave Dalton II / Core Scientific Old Tilton Road Data Center in Dalton, Whitfield County, Georgia appear in the record, with no clear majority position. Rezoning approved on a 3-2 vote, tie broken by the board chairman (March 2025).
How the community has taken it
Reception is a sourced signal, not an editorial judgment: mixed reception means documented support and documented opposition both exist with no clear majority position on record.
Rezoning approved on a 3-2 vote, tie broken by the board chairman (March 2025).
Notes on the record
Whitfield County BOC rezoning (3-2, tie broken by Chairman Jevin Jensen) approved March 2025 for 'heavy manufacturing' use (AI data center per contemporaneous reporting), conditioned on Enterprise Drive access. A June 2026 Whitfield Superior Court validated a $1.2B Integra SPV equipment-bond package tied to this ~167-173 acre site, naming CoreWeave Dalton II LLC as sublessee/operator. Same June 2026 hearing validated much larger CoreWeave Dalton / CoreWeave Dalton II bond series ($900M + $6.4B + $6.7B) that likely cover Core Scientific's OTHER Whitfield campus sites (Industrial South Road, Enterprise Drive), those are separate parcels/rezonings and were not pursued as additional candidates this pass to avoid parcel-level double-counting; flagged for a future lane pass with GIS/parcel-level dedup once individual site addresses for those bond packages are confirmed. Core Scientific is site owner; CoreWeave Dalton II, LLC is sublessee/operator.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- Which utility serves it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- CleanSpark Dalton Bitcoin Mining Facility · Dalton · CleanSpark, Inc.6 mi · Operating
- Project Springbank (Atlas Development Bartow County Campus) · Adairsville · Atlas Development LLC22 mi · Proposed · 432 MW
Questions people ask about this site
Is there opposition to the CoreWeave Dalton II / Core Scientific Old Tilton Road Data Center in Dalton?
Partly. Both documented support and documented opposition to CoreWeave Dalton II / Core Scientific Old Tilton Road Data Center in Dalton, Whitfield County, Georgia appear in the record, with no clear majority position. Rezoning approved on a 3-2 vote, tie broken by the board chairman (March 2025).
Has anyone filed a lawsuit over the CoreWeave Dalton II / Core Scientific Old Tilton Road Data Center?
No lawsuit over CoreWeave Dalton II / Core Scientific Old Tilton Road Data Center appears in the record we track as of July 26, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does CoreWeave Dalton II / Core Scientific Old Tilton Road Data Center use?
No water withdrawal figure for CoreWeave Dalton II / Core Scientific Old Tilton Road Data Center is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates CoreWeave Dalton II / Core Scientific Old Tilton Road Data Center, and how big is it?
Core Scientific is the operator on record. We hold 10 sites for that company across the registry. No capacity figure is on record for this site. The site is recorded at 173.3 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "CoreWeave Dalton II / Core Scientific Old Tilton Road Data Center," updated July 26, 2026, https://suedatacenters.org/data-centers/coreweave-dalton-ii-old-tilton-road-whitfield-ga.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/coreweave-dalton-ii-old-tilton-road-whitfield-ga, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Whitfield County Board of Commissioners rezoning vote, Old Tilton Road (Core Scientific) · Dalton Daily Citizen · retrieved July 17, 2026
- 2.Court reviews $15 billion in data center bonds: Integra SPV A/B/C $1.2B bonds for ~167-acre Tilton Road site owned by Core Scientific, subleased to CoreWeave Dalton II · Dalton Daily Citizen · retrieved July 17, 2026
- 3.Judge validates $15.2 billion in data center-related bonds · Dalton Daily Citizen · retrieved July 17, 2026
- 4.Trump highlights AI data center energy use as construction for Dalton facility advances · NewsChannel 9 · retrieved July 17, 2026
- 5.Whitfield County GIS/Tax Assessor parcel detail, parcel 13-060-01-000 · retrieved July 18, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us