Data Center Registry
Clocktower - NWB 05 Data Center (Quanah)
Quanah, Hardeman County County, Texas
Clocktower - NWB 05 Data Center (Quanah) is a proposed data center in Quanah, Texas (Hardeman County County), operated by 19000-200 Holdings, LLC.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Proposed
- Operator
- 19000-200 Holdings, LLC
- Facility type
- Data center
- Location
- 4628 Four Corners Rd, Quanah, Hardeman County County, TX, 79252
- Coordinates
- 34.2979, -99.7406 (approximate)
- Power capacity
- Not established from a public source
- Land
- Not established from a public source
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- October 27, 2026ProposedTDLR registration: new single-story 288,355 sq ft data center, start 11/1/2026, completion 12/31/2028 Source: Texas Department of Licensing and Regulation
Opposition and litigation at this site
Nothing on record as of November 4, 2026. No lawsuit, organized opposition, or contested hearing over Clocktower - NWB 05 Data Center (Quanah) in Quanah, Hardeman County County, Texas appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Notes on the record
The TDLR registered estimated cost is $8,000,000,000 for this one building. It is not recorded here as campus investment. A third-party report links the site to Integra, but that has not been verified, so the operator is the registrant shown on the filing. A registration does not confirm that construction has started.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- Land area
- How the community has received it
- Which utility serves it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Google Wilbarger County Campus · Vernon · Google27 mi · Under construction
- Soluna Project Fei · Childress · Soluna Holdings28 mi · Proposed · 100 MW
- Crusoe-Lancium Childress AI Data Center Campus (Project Hyper) · Childress · Crusoe / Lancium28 mi · Proposed · 1 GW
- IREN Horizon, Childress, TX · Childress · IREN (Iris Energy)28 mi · Under construction · 50 MW · Supported
Questions people ask about this site
Is there opposition to the Clocktower - NWB 05 Data Center (Quanah) in Quanah?
Nothing on record as of November 4, 2026. No lawsuit, organized opposition, or contested hearing over Clocktower - NWB 05 Data Center (Quanah) in Quanah, Hardeman County County, Texas appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the Clocktower - NWB 05 Data Center (Quanah)?
No lawsuit over Clocktower - NWB 05 Data Center (Quanah) appears in the record we track as of November 4, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Clocktower - NWB 05 Data Center (Quanah) use?
No water withdrawal figure for Clocktower - NWB 05 Data Center (Quanah) is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Clocktower - NWB 05 Data Center (Quanah), and how big is it?
19000-200 Holdings, LLC is the operator on record. No capacity figure is on record for this site.
How to cite this page
SueDataCenters.org Data Center Registry, "Clocktower - NWB 05 Data Center (Quanah)," updated November 4, 2026, https://suedatacenters.org/data-centers/clocktower-quanah-hardeman-county-tx.
Facility data from Compute Atlas (E. Kubiak), version 1.35.1 (November 2, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/clocktower-quanah-hardeman-county-tx, retrieved November 5, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.TDLR TABS2027004544 - Clocktower - NWB 05 · Texas Department of Licensing and Regulation · retrieved November 4, 2026
Is a data center disrupting your home?
Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.
- Tell us about your situation
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us