Project Longhorn Data Center Campus

Cedar Creek, Bastrop County County, Texas

ProposedNo reception on recordRecord updated November 4, 2026

Project Longhorn Data Center Campus is a proposed data center in Cedar Creek, Texas (Bastrop County County), operated by Black Chamber Partners (BlackChamber Group affiliate). The public record puts it at 490 MW planned.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Proposed

Operator
Black Chamber Partners (BlackChamber Group affiliate)
Facility type
Data center
Location
Cedar Creek, Bastrop County County, TX
Coordinates
30.0754, -97.4262 (approximate)
Power capacity
490 MW planned
Land
Not established from a public source
Investment
Not established from a public source
Announced
Not established from a public source
Utility
Not established from a public source
Power source
On site gas
On site generation
710 MW
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
No reception on record
Source confidence
Reported by at least one credible outlet or filing

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. October 9, 2026
    Proposed
    Building One ($366M, 498,165 sq ft) filed with TDLR, construction targeted to start 2026-11-30 Source: Baxtel

Opposition and litigation at this site

Nothing on record as of November 4, 2026. No lawsuit, organized opposition, or contested hearing over Project Longhorn Data Center Campus in Cedar Creek, Bastrop County County, Texas appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.

A new status, a permit, a reception finding, or a lawsuit. Nothing else, ever.

Power and water

Pacifico Energy is developing an on-site gas-fired plant, which delivers power directly rather than through the grid.

Notes on the record

Located on Earl Callahan Road near Walter Hoffman Road, on a campus of about 2,800 acres. The developers withdrew their county tax-abatement requests in August 2026, but the project was not cancelled. Reports say Anthropic is in talks to lease the campus, which has not been confirmed.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • Land area
  • How the community has received it
  • Which utility serves it
Which document closes each gap
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Land area
The rezoning application, the plat, or the deed recorded with the county.
How the community has received it
Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Tell us about your situation

Living near Project Longhorn Data Center Campus?

Tell us the basics. Where a participating attorney in your state is available, we may share your information with them with your consent. Free, no obligation, and no guarantee anyone will contact you.

Questions people ask about this site

Is there opposition to the Project Longhorn Data Center Campus in Cedar Creek?

Nothing on record as of November 4, 2026. No lawsuit, organized opposition, or contested hearing over Project Longhorn Data Center Campus in Cedar Creek, Bastrop County County, Texas appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

Has anyone filed a lawsuit over the Project Longhorn Data Center Campus?

No lawsuit over Project Longhorn Data Center Campus appears in the record we track as of November 4, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Project Longhorn Data Center Campus use?

No water withdrawal figure for Project Longhorn Data Center Campus is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Project Longhorn Data Center Campus, and how big is it?

Black Chamber Partners (BlackChamber Group affiliate) is the operator on record. Capacity on record is 490 MW.

How to cite this page

SueDataCenters.org Data Center Registry, "Project Longhorn Data Center Campus," updated November 4, 2026, https://suedatacenters.org/data-centers/blackchamber-project-longhorn-cedar-creek-tx.

Facility data from Compute Atlas (E. Kubiak), version 1.35.1 (November 2, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/blackchamber-project-longhorn-cedar-creek-tx, retrieved November 5, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Anthropic-linked $366M data center project proposed in Cedar Creek, Texas · Baxtel · retrieved November 4, 2026
  2. 2.BlackChamber: Project Longhorn Campus · Baxtel · retrieved November 4, 2026
  3. 3.Anthropic-linked $366M data center filed in Cedar Creek · iRecruit · retrieved November 4, 2026
  4. 4.New $2.2B Cedar Creek data center project abatements under review · Community Impact · retrieved November 4, 2026
  5. 5.Developers withdraw tax break requests · Elgin Courier · retrieved November 4, 2026

Is a data center disrupting your home?

Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.

  • Tell us about your situation
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us