Sue Data Centers

Data Center Registry

Atlas Compute AI Data Center Campus

Fort Pierce, St. Lucie County, Florida

ProposedNo reception on recordRecord updated October 20, 2026

Atlas Compute AI Data Center Campus is a proposed data center in Fort Pierce, Florida (St. Lucie County), operated by Atlas Compute (infrastructure by Penguin Solutions). The public record puts it at 240 MW planned.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Proposed

Operator
Atlas Compute (infrastructure by Penguin Solutions)
Facility type
Data center
Location
Post Office Road, Midway Industrial Park, Fort Pierce, St. Lucie County, FL
Coordinates
27.4400, -80.3300 (approximate)
Power capacity
240 MW planned
Land
Not established from a public source
Investment
Not established from a public source
Announced
Not established from a public source
Utility
Not established from a public source
Power source
On site gas
Cooling
air
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
No reception on record
Source confidence
Confirmed by multiple independent sources or official documentation

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. November 6, 2025
    Proposed
    Land and utilities secured for a 240 MW initial campus, with up to 1 GW expansion capacity. Source: GlobeNewswire

Opposition and litigation at this site

Nothing on record as of October 20, 2026. No lawsuit, organized opposition, or contested hearing over Atlas Compute AI Data Center Campus in Fort Pierce, St. Lucie County, Florida appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.

A new status, a permit, a reception finding, or a lawsuit. Nothing else, ever.

Power and water

Atlas Compute plans to build its own natural gas-fired power plant to serve the campus rather than draw the full load from the utility; the site borders FPUA's Treasure Coast Energy Center.

Company release states the facility will feature "cooling technology to eliminate the need for water use" (WFLX, March 2026). No recirculating water circuit is described.

Notes on the record

Land and utilities secured. Targeting operational Q4 2026-Q1 2027. Up to 1 GW expansion capacity. Distinct from the withdrawn Sentinel Grove/Project Jarvis project in the same county.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Tax abatements or other public subsidy
  • Permanent jobs promised
  • Land area
  • How the community has received it
  • Which utility serves it
Which document closes each gap
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.
Land area
The rezoning application, the plat, or the deed recorded with the county.
How the community has received it
Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
Which utility serves it
The electric service agreement or the utility's filing with the state public utility commission.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Tell us about your situation

Living near Atlas Compute AI Data Center Campus?

Tell us the basics. Where a participating attorney in your state is available, we may share your information with them with your consent. Free, no obligation, and no guarantee anyone will contact you.

Questions people ask about this site

Is there opposition to the Atlas Compute AI Data Center Campus in Fort Pierce?

Nothing on record as of October 20, 2026. No lawsuit, organized opposition, or contested hearing over Atlas Compute AI Data Center Campus in Fort Pierce, St. Lucie County, Florida appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

Has anyone filed a lawsuit over the Atlas Compute AI Data Center Campus?

No lawsuit over Atlas Compute AI Data Center Campus appears in the record we track as of October 20, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Atlas Compute AI Data Center Campus use?

No water withdrawal figure for Atlas Compute AI Data Center Campus is on record here. Cooling is recorded as air, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.

Who operates Atlas Compute AI Data Center Campus, and how big is it?

Atlas Compute (infrastructure by Penguin Solutions) is the operator on record. Capacity on record is 240 MW.

How to cite this page

SueDataCenters.org Data Center Registry, "Atlas Compute AI Data Center Campus," updated October 20, 2026, https://suedatacenters.org/data-centers/atlas-compute-ai-data-center-campus-fort-pierce-fl.

Facility data from Compute Atlas (E. Kubiak), version 1.34.1 (October 4, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/atlas-compute-ai-data-center-campus-fort-pierce-fl, retrieved October 29, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Atlas Compute secures land and utilities for 240 MW AI data center campus · GlobeNewswire · retrieved July 17, 2026
  2. 2.Florida-based company announces plans to build AI data center in Fort Pierce · WFLX · retrieved October 20, 2026
  3. 3.Massive AI Server Farm Sets Sights On Fort Pierce, Neighbors Want Answers · retrieved September 10, 2026
  4. 4.TCPalm via Yahoo News, Atlas Compute's St. Lucie County campus would be powered by its own natural gas-fired power plant, on over 26 acres at Midway Industrial Park bordering the Treasure Coast Energy Center · TCPalm / Treasure Coast Newspapers · retrieved September 14, 2026

Is a data center disrupting your home?

Tell us what is happening. Where a participating attorney who handles data center cases in your state is available, we may share your information with them with your consent. It is free and carries no obligation, but we cannot promise that anyone will contact you.

  • Tell us about your situation
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us