Tenaska: The Omaha Power Developer Behind the Cass County, Nebraska Data Center Fight
Tenaska is a privately held energy company headquartered in Omaha that manages a 6,622 megawatt generating fleet. In Nebraska it optioned 1,354 acres in Cass County for a proposed natural gas plant and data center with Google, and residents answered with a twelve month county moratorium and an outright village ban. No lawsuit has been filed, and that is what makes the record worth reading.
Tenaska on the tracker
- Tracker entries
- One: the Cass County, Nebraska moratorium and the Nehawka village ban. No lawsuit has been filed by anyone, including Tenaska
- What the company is
- A privately held energy company headquartered in Omaha, Nebraska, with more than 800 employees, describing itself as one of the largest privately held energy companies in the United States
- Business lines
- Natural gas marketing, power marketing, power generation, and energy project development, managing a generating fleet of 6,622 megawatts across natural gas, wind, and solar
- The Nebraska project
- Announced June 25, 2026: 1,354 acres optioned in Cass County along Highway 75 south of Murray and Beaver Lake, for a proposed 2,000 acre natural gas power plant and data center in partnership with Google, per KETV
- Where it stands
- Cass County commissioners voted 5 to 0 on August 11, 2026 for a twelve month moratorium on data center permits; the village of Nehawka banned data centers in every zoning district on August 26, 2026
Key Takeaways
- Tenaska is an energy developer first and a data center name second. Its own corporate site describes natural gas and power marketing, generation, and project development, and does not describe a data center business.
- In Nebraska it is the land assembler behind the state's biggest data center fight. Flatwater Free Press reported in March 2026 that Tenaska had optioned more than 2,600 acres across southeast Nebraska since December, and on June 25, 2026 the company announced 1,354 acres in Cass County for a proposed natural gas plant and data center with Google.
- The scale is the story. That reporting described a project needing 1,000 to 3,000 megawatts, more than the 800 megawatts Lincoln Electric System needs across its entire service area in summer.
- No one has sued. Cass County residents stopped the project at the permit counter: a planning commission moratorium on July 13, 2026, a 5 to 0 county board vote for a twelve month pause on August 11, and a village of Nehawka zoning ban on August 26 that reaches substations, transformers, and generators.
- The pressure went statewide. Governor Jim Pillen signed Executive Order 26-17 on July 20, 2026 barring new data centers from ImagiNE Nebraska Act tax incentives, and twelve Nebraska counties had approved temporary moratoriums by early September 2026.
In this article
Tenaska is not a hyperscaler. It is a privately held energy company headquartered in Omaha, Nebraska, with more than 800 employees and a generating fleet of 6,622 megawatts across natural gas, wind, and solar, and its business lines are natural gas marketing, power marketing, generation, and project development. Its own site does not describe a data center business at all. It appears on this tracker because in Nebraska the power developer and the land assembler turned out to be the same company: Tenaska announced on June 25, 2026 that it had optioned 1,354 acres in Cass County along Highway 75 for a proposed 2,000 acre natural gas power plant and data center campus in partnership with Google. What happened next is the most instructive entry we have, because nobody sued. Residents used ordinary land use process and stopped the project cold.
Every case on the tracker
- Dispute, no suit filedNebraskaCass County, Nebraska Paused Data Centers and a Village Banned Them Outright. No Lawsuit Was Filed, and That Is the Point.
No lawsuit filed; county moratorium adopted 5 to 0 on August 11, 2026, village ban adopted August 26, 2026
After Tenaska optioned 1,354 acres in Cass County for a proposed natural gas plant and data center tied to Google, the county commissioners voted 5 to 0 on August 11, 2026 for a twelve month moratorium and the village of Nehawka banned data centers in every zoning district on August 26. No suit has been filed. Here is how residents did it and what Nebraska law gives the next community.
The power developer as the front door
A gigawatt scale data center is a power project before it is a computing project, and Nebraska is where that became visible to residents. Flatwater Free Press reported in March 2026 that Tenaska had optioned more than 2,600 acres across southeast Nebraska since December, including at least 1,000 acres in Gage County, at least 860 acres in Cass County, at least 450 acres in Lancaster County, and nearly 300 acres in Otoe County, for a Google project that documents indicated could be online as soon as 2029 and that would require 1,000 to 3,000 megawatts.
That structure has a practical consequence for anyone watching for a project near them. The first public paper trail was not a rezoning application from a technology company. It was land option agreements filed by an energy developer, and it appeared months before any hearing was scheduled. Cass County residents found it because they went looking in the county records, which Nebraska law lets any resident examine free of charge.
What Cass County did, without a courtroom
The county planning commission approved a moratorium at its July 13, 2026 meeting, three weeks after the Tenaska announcement. On August 11, the Cass County Board of Commissioners voted 5 to 0 for a twelve month moratorium on data center permits and tabled its proposed data center regulations to September 22, deliberately separating the pause from the rulemaking. On August 26, the village of Nehawka, population under 200, amended its zoning code to prohibit data centers in every district, along with the substations, transformers, and generators that serve them.
Nothing in that sequence required a lawsuit, a filing fee, or a judge. Our full report on the Cass County matter has the meeting by meeting record, the residents' group that tracked the land options, and the Nebraska statutes that set the deadlines if litigation ever does become necessary. The Nebraska state page covers the wider footprint and the state's public power structure.
What happens after the pause
A twelve month moratorium is a clock, not an outcome. The substantive questions in Cass County, what setbacks, sound limits, water conditions, and decommissioning security a data center must meet, were tabled to September 22, 2026 and remain open. Those regulation hearings are where the terms of any future Tenaska project get written, and they are the meetings worth attending.
The statewide backdrop has moved too. Governor Jim Pillen signed Executive Order 26-17 on July 20, 2026, barring new data centers from ImagiNE Nebraska Act tax incentives and creating a seventeen member task force whose membership includes the chief executives of the state's three largest public power utilities. LB1010, signed April 14, 2026, requires data center owners and operators to report annual electricity and water use, bear decommissioning costs, and enter community benefit agreements. By early September 2026, twelve Nebraska counties had approved temporary moratoriums.
If a project is being assembled near you, our guide to fighting a proposed data center covers the approval process, and our guide to who pays for data center power covers the utility questions a gas plant and campus combination raises. If a facility near you has already been built and is affecting your home, our free case review connects you with an independent attorney in our network who handles data center cases in your state, at no cost and with no obligation.
Frequently asked questions
Has Tenaska been sued over a data center?
No. As of September 3, 2026 no lawsuit has been filed over the proposed Tenaska data center and power plant in Cass County, Nebraska, by residents, the county, the village of Nehawka, or the developer. The dispute has been handled entirely through county and village land use process.
What is Tenaska?
Tenaska is a privately held energy company headquartered in Omaha, Nebraska with more than 800 employees. It operates in natural gas marketing, power marketing, power generation, and energy project development, and manages a generating fleet of 6,622 megawatts across natural gas, wind, and solar. Its corporate site does not describe a data center business.
What is the Tenaska data center project in Nebraska?
Tenaska announced on June 25, 2026 that it had optioned 1,354 acres in Cass County along Highway 75 south of Murray and Beaver Lake for a proposed 2,000 acre natural gas power plant and data center in partnership with Google, according to KETV. Flatwater Free Press reported in March 2026 that the broader project would require 1,000 to 3,000 megawatts and could be online as soon as 2029.
Did Cass County, Nebraska stop the Tenaska data center?
The county paused it. Commissioners voted 5 to 0 on August 11, 2026 for a twelve month moratorium on data center permits and tabled proposed data center regulations to September 22. Separately, the village of Nehawka amended its zoning code on August 26, 2026 to prohibit data centers and their substations, transformers, and generators in every zoning district.
Article sources
Our editorial standards require primary sources: government publications, regulator data, company filings, and established industry research.
Is a Tenaska data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us