Vantage Data Centers VA4 Stafford Campus

Stafford County, Virginia · All 20 Vantage Data Centers sites · Every Vantage Data Centers case on our tracker

Under constructionNo reception on recordAI mixed useRecord updated July 6, 2026

Vantage Data Centers VA4 Stafford Campus is a data center under construction in Virginia (Stafford County), operated by Vantage Data Centers. The public record puts it at announced November 2025, 192 MW planned, 82 acres, a reported $2 billion investment.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Under construction

Operator
Vantage Data Centers
Facility type
Data center, AI use mixed
Location
Stafford County, VA
Coordinates
38.4400, -77.4400
Power capacity
192 MW planned
Land
82 acres
Investment
$2 billion
Announced
November 2025
Utility
Dominion Energy
Power source
Grid
Cooling
Closed loop
Water use
Not established from a public source
Jobs
50 permanent; 1,100 construction
Public subsidy
Not established from a public source
Community reception
No reception on record
Source confidence
Confirmed by multiple independent sources or official documentation

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. November 2025
    Proposed
    Announced November 6, 2025; DPR Construction engaged as general contractor; three data centers, 929,000 sq ft total; first building target late 2027 Source: Vantage Data Centers
  2. November 2025
    Under construction
    Groundbreaking ceremony held November 6, 2025 per Vantage press release; active development underway with DPR Construction as general contractor. Source: Vantage Data Centers

Opposition and litigation at this site

Nothing on record as of July 6, 2026. No lawsuit, organized opposition, or contested hearing over Vantage Data Centers VA4 Stafford Campus in Stafford County, Virginia appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.

Power and water

Closed-loop chilled water system with liquid-to-liquid cooling; LEED Silver target; designed to minimize water consumption

Notes on the record

Vantage's fourth Virginia campus; approximately 40 miles south of Washington DC in Stafford County (Fredericksburg region). Coordinates are county-centroid approximation, specific site address not confirmed in sources. Groundbreaking held November 6, 2025; DPR Construction engaged as GC.

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Tax abatements or other public subsidy
  • How the community has received it
Which document closes each gap
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
How the community has received it
Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the Vantage Data Centers VA4 Stafford Campus in Stafford County, Virginia?

Nothing on record as of July 6, 2026. No lawsuit, organized opposition, or contested hearing over Vantage Data Centers VA4 Stafford Campus in Stafford County, Virginia appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.

Has anyone filed a lawsuit over the Vantage Data Centers VA4 Stafford Campus?

No lawsuit over Vantage Data Centers VA4 Stafford Campus appears in the record we track as of July 6, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Vantage Data Centers VA4 Stafford Campus use?

No water withdrawal figure for Vantage Data Centers VA4 Stafford Campus is on record here. Cooling is recorded as closed_loop, which is the strongest available clue: closed loop and air cooled plant draw far less than evaporative cooling. We leave the number blank rather than estimate one.

Who operates Vantage Data Centers VA4 Stafford Campus, and how big is it?

Vantage Data Centers is the operator on record. We hold 20 sites for that company across the registry. Capacity on record is 192 MW. The site is recorded at 82 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Vantage Data Centers VA4 Stafford Campus," updated July 6, 2026, https://suedatacenters.org/data-centers/vantage-stafford-va4-va.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/vantage-stafford-va4-va, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Vantage Data Centers Invests $2B in Fredericksburg Virginia Region · Vantage Data Centers · retrieved July 6, 2026
  2. 2.Vantage Data Centers to invest $2B on Stafford campus · Virginia Business · retrieved July 6, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us