Data Center Registry
Segra Winston-Salem Data Center
Winston-Salem, Forsyth County, North Carolina · All 3 Segra sites
Segra Winston-Salem Data Center is an operating data center in Winston-Salem, North Carolina (Forsyth County), operated by Segra.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Operating
- Operator
- Segra
- Facility type
- Data center
- Location
- 3310 Old Lexington Road, Winston-Salem, Forsyth County, NC, 27107
- Coordinates
- 36.1028, -80.2608 (approximate)
- Power capacity
- Not established from a public source
- Land
- Not established from a public source
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- No reception on record
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- August 29, 2026OperatingListed as fully operational colocation space. Source: Baxtel
Opposition and litigation at this site
Nothing on record as of August 29, 2026. No lawsuit, organized opposition, or contested hearing over Segra Winston-Salem Data Center in Winston-Salem, Forsyth County, North Carolina appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
If you live near this site and something is happening that this page does not show, that is worth telling us. Send us the document and it goes in the record with the source attached. For sites where opposition is already established, see every contested site we track.
Notes on the record
Built 2002 as DataChambers; acquired by North State Communications and now operated under the Segra brand. Directory listings disagree on capacity (about 3.5 MW versus 8 MW) and on building size (about 120,000 to 140,000 sq ft with roughly 26,000 to 27,000 sq ft of raised floor), so no capacity figure is asserted here.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- Land area
- How the community has received it
- Which utility serves it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Land area
- The rezoning application, the plat, or the deed recorded with the county.
- How the community has received it
- Planning commission and governing body minutes, public comment records, and any petition or lawsuit filed in the county.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Rural Hall Data Center (The Drox Group) · Rural Hall · The Drox Group11 mi · Cancelled · Contested
- Project Delta Data Center, Stokes County · Walnut Cove · Undisclosed (rezoning applicant: Engineered Land Solutions)14 mi · Proposed · In litigation
- WhiteFiber NC-1 AI Data Center Campus · Madison · WhiteFiber (Bit Digital)25 mi · Operating · 200 MW · Supported
- ImpactData Greensboro · Greensboro · ImpactData26 mi · Under construction · 20 MW
- Long Ferry Road Data Center Campus (Rowan County) · Undisclosed developer29 mi · Proposed · Opposed
Questions people ask about this site
Is there opposition to the Segra Winston-Salem Data Center in Winston-Salem?
Nothing on record as of August 29, 2026. No lawsuit, organized opposition, or contested hearing over Segra Winston-Salem Data Center in Winston-Salem, Forsyth County, North Carolina appears in the sources this registry tracks. That is an absence in our sources rather than a finding that none exists, and local opposition often predates any coverage a national dataset would pick up.
Has anyone filed a lawsuit over the Segra Winston-Salem Data Center?
No lawsuit over Segra Winston-Salem Data Center appears in the record we track as of August 29, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does Segra Winston-Salem Data Center use?
No water withdrawal figure for Segra Winston-Salem Data Center is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates Segra Winston-Salem Data Center, and how big is it?
Segra is the operator on record. We hold 3 sites for that company across the registry. No capacity figure is on record for this site.
How to cite this page
SueDataCenters.org Data Center Registry, "Segra Winston-Salem Data Center," updated August 29, 2026, https://suedatacenters.org/data-centers/segra-winston-salem-data-center-nc.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/segra-winston-salem-data-center-nc, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Segra: Winston-Salem Data Center · Baxtel · retrieved August 29, 2026
- 2.NorthState Data Center Locations (Salem Data Center, 3310 Old Lexington Road) · Cloud and Colocation · retrieved August 29, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation
Attorney or law firm handling data center matters? Speak with us