Data Center Registry
King George Technology Center
King George, King George County, Virginia
King George Technology Center is a proposed data center in King George, Virginia (King George County), operated by Green Energy Ventures. The public record puts it at 352 acres. It has documented support and documented opposition on record.
Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.
Facility record
Proposed
- Operator
- Green Energy Ventures
- Facility type
- Data center
- Location
- King George, King George County, VA
- Coordinates
- 38.2503, -77.2901
- Power capacity
- Not established from a public source
- Land
- 352 acres
- Investment
- Not established from a public source
- Announced
- Not established from a public source
- Utility
- Not established from a public source
- Cooling
- Not established from a public source
- Water use
- Not established from a public source
- Jobs
- Not established from a public source
- Public subsidy
- Not established from a public source
- Community reception
- Mixed reception
- Source confidence
- Reported by at least one credible outlet or filing
Timeline from the record
Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.
- July 17, 2026Proposed352 acres (40 already industrial-zoned) in the Route 3 West Settlement Area, bordering Stafford; rezoning pending. Source: Fredericksburg Advance
Opposition and litigation at this site
Partly. Both documented support and documented opposition to King George Technology Center in King George, King George County, Virginia appear in the record, with no clear majority position. At a Dec.
How the community has taken it
Reception is a sourced signal, not an editorial judgment: mixed reception means documented support and documented opposition both exist with no clear majority position on record.
At a Dec. 10, 2024 Planning Commission meeting, commissioners withheld support pending more detail, saying they 'don't want to see GEV's application go the way of Amazon's,' and required specifics on diesel-generator/fuel-tank siting, traffic, and economic impact before advancing; as of the Jan.
Notes on the record
352 acres (40 already industrial-zoned) in the Route 3 West Settlement Area, bordering Stafford; rezoning pending.
What the record does not establish, and the document that would
In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.
- Power capacity in megawatts
- Cooling method and water use
- Tax abatements or other public subsidy
- Permanent jobs promised
- Which utility serves it
Which document closes each gap
- Power capacity in megawatts
- The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
- Cooling method and water use
- The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
- Tax abatements or other public subsidy
- The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
- Permanent jobs promised
- The economic development application or incentive agreement, which usually states a job commitment and a clawback.
- Which utility serves it
- The electric service agreement or the utility's filing with the state public utility commission.
Have one of these documents? Send it to us and we will add it to the record with attribution.
Other sites within 30 miles
Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.
- Birchwood Data Campus · King George · Amazon Web Services2 mi · Permitted · In litigation
- Project Sisson · Peterson Companies6 mi · Proposed
- Crossroads Technology Campus · RCK Digital Crossroads LLC8 mi · Proposed · Contested
- Summit Crossing Tech Campus · Massaponax · Amazon Web Services9 mi · Under construction · Mixed reception
- Pairmont Data Center Campus · Eagle Rock Partners10 mi · Proposed
- Carter's Store Tech Campus · Spotsylvania · Amazon Web Services11 mi · Permitted · Mixed reception
- Cosner Technology Campus · Massaponax · Amazon Web Services11 mi · Under construction · Mixed reception
- Hunters Ridge South Data Center Campus · Spotsylvania · American Real Estate Partners (AREP)11 mi · Permitted · Mixed reception
Questions people ask about this site
Is there opposition to the King George Technology Center data center in King George?
Partly. Both documented support and documented opposition to King George Technology Center in King George, King George County, Virginia appear in the record, with no clear majority position. At a Dec.
Has anyone filed a lawsuit over the King George Technology Center data center?
No lawsuit over King George Technology Center appears in the record we track as of August 26, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.
How much water does King George Technology Center use?
No water withdrawal figure for King George Technology Center is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.
Who operates King George Technology Center, and how big is it?
Green Energy Ventures is the operator on record. No capacity figure is on record for this site. The site is recorded at 352 acres.
How to cite this page
SueDataCenters.org Data Center Registry, "King George Technology Center," updated August 26, 2026, https://suedatacenters.org/data-centers/green-energy-ventures-king-george-technology-center-va.
Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/green-energy-ventures-king-george-technology-center-va, retrieved September 14, 2026.
Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.
Sources for this record
As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.
- 1.Green Energy Ventures presents King George Technology Center · Fredericksburg Advance · retrieved July 17, 2026
- 2.King George County official Parcels GIS layer, Tax Map 21 Parcels 49 & 73, Tax Map 22 Parcels 46A & 49A, per the county's own voluntary proffer statement · retrieved July 18, 2026 · original offline, no archived copy found
- 3.King George Technology Center Voluntary Proffer Statement (Dec 12, 2025) · Green Energy Ventures / J2 Engineers · retrieved August 26, 2026
Is a data center disrupting your home?
Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.
- Free case review
- Independent attorneys
- No obligation