Sue Data Centers

Data Center Registry

Summit Crossing Tech Campus

Massaponax, Spotsylvania County, Virginia · All 54 Amazon Web Services sites · Every Amazon case on our tracker

Under constructionMixed receptionRecord updated July 26, 2026

Summit Crossing Tech Campus is a data center under construction in Massaponax, Virginia (Spotsylvania County), operated by Amazon Web Services. The public record puts it at announced June 2023, 231 acres. It has documented support and documented opposition on record.

Every line on this page traces to a public source listed at the bottom. Where a figure was looked for and not found, the row says so. A blank is never a zero.

Facility record

Under construction

Operator
Amazon Web Services
Facility type
Data center
Location
Massaponax, Spotsylvania County, VA
Coordinates
38.1885, -77.4405 (approximate)
Power capacity
Not established from a public source
Land
231 acres
Investment
Not established from a public source
Announced
June 2023
Utility
Rappahannock Electric Co-op
Cooling
Not established from a public source
Water use
Not established from a public source
Jobs
Not established from a public source
Public subsidy
Not established from a public source
Community reception
Mixed reception
Source confidence
Confirmed by multiple independent sources or official documentation

Timeline from the record

Newest first. Record entries come from the filings and reports the registry cites. Coverage entries are headlines from publisher feeds we monitor daily, linked to the outlet; last checked September 14, 2026.

  1. July 17, 2026
    Under construction
    Status change recorded. Source: Data Center Frontier

Opposition and litigation at this site

Partly. Both documented support and documented opposition to Summit Crossing Tech Campus in Massaponax, Spotsylvania County, Virginia appear in the record, with no clear majority position. Board of Supervisors approved the rezoning on a 5-2 vote (Oct 2023).

How the community has taken it

Reception is a sourced signal, not an editorial judgment: mixed reception means documented support and documented opposition both exist with no clear majority position on record.

Board of Supervisors approved the rezoning on a 5-2 vote (Oct 2023).

Notes on the record

One of Amazon Web Services' four Spotsylvania/Caroline data center campuses (Summit Crossing, Carter's Store, Cosner [tracked as aws-cosner-technology-campus-massaponax-va, ST23-0031], Orrock [tracked as aws-mattermeade-caroline-va]). ~231 acres, up to ~2.1M sq ft of data center buildings (Phase 1 max ~900k sq ft). Located on the south side of Summit Crossing Road, ~0.5 mi west of the Spotsylvania/Caroline county line; borders the Carter's Store campus. Amazon Data Services filed June 2023 to rezone from Rural (RU) to Industrial-1 (I-1); Board of Supervisors approved the four AWS rezonings in a 5-2 vote in October 2023 (Spotsylvania "ST23" case series). Reported under construction / buildings going up per The Fredericksburg Advance (2026). Coordinates approximate (Summit Crossing Road geocode; parcels not GIS-confirmed this pass).

What the record does not establish, and the document that would

In every fight on our tracker the decisive fact came out of a public records request. These are the requests for this site.

  • Power capacity in megawatts
  • Cooling method and water use
  • Tax abatements or other public subsidy
  • Permanent jobs promised
Which document closes each gap
Power capacity in megawatts
The utility's large load service agreement, the interconnection request in the grid operator's queue, or the electrical site plan in the permit file.
Cooling method and water use
The water service agreement, any groundwater appropriation permit, and the mechanical narrative in the site plan.
Tax abatements or other public subsidy
The abatement, PILOT, or development agreement approved by the county, city, or development authority, and the state's data center sales tax exemption certificate if one was issued.
Permanent jobs promised
The economic development application or incentive agreement, which usually states a job commitment and a clawback.

Have one of these documents? Send it to us and we will add it to the record with attribution.

Other sites within 30 miles

Distances are between recorded coordinates, many of which are a city or county centroid, so treat them as approximate. Cumulative load on one utility and one aquifer is the question a planning commission rarely asks.

Questions people ask about this site

Is there opposition to the Summit Crossing Tech Campus in Massaponax?

Partly. Both documented support and documented opposition to Summit Crossing Tech Campus in Massaponax, Spotsylvania County, Virginia appear in the record, with no clear majority position. Board of Supervisors approved the rezoning on a 5-2 vote (Oct 2023).

Has anyone filed a lawsuit over the Summit Crossing Tech Campus?

No lawsuit over Summit Crossing Tech Campus appears in the record we track as of July 26, 2026. Residents most often reach a lawyer over water supply, well drawdown, noise from cooling plant, property value, or a rezoning approved without the notice the ordinance required. If any of that is happening near this site, it is worth a review whether or not a case has been filed yet.

How much water does Summit Crossing Tech Campus use?

No water withdrawal figure for Summit Crossing Tech Campus is on record here. Water use is rarely published voluntarily; it usually surfaces through a utility service agreement or a state withdrawal permit, both of which are public records. We leave the number blank rather than estimate one.

Who operates Summit Crossing Tech Campus, and how big is it?

Amazon Web Services is the operator on record. We hold 54 sites for that company across the registry. No capacity figure is on record for this site. The site is recorded at 231 acres.

How to cite this page

SueDataCenters.org Data Center Registry, "Summit Crossing Tech Campus," updated July 26, 2026, https://suedatacenters.org/data-centers/aws-summit-crossing-tech-campus-spotsylvania-va.

Facility data from Compute Atlas (E. Kubiak), version 1.32.0 (September 7, 2026), licensed CC BY 4.0, record https://www.compute-atlas.com/facilities/aws-summit-crossing-tech-campus-spotsylvania-va, retrieved September 14, 2026.

Corrections with a public source are welcome at the Compute Atlas record or through our contact page. The whole registry is available as CSV and JSON under CC BY 4.0.

Sources for this record

As compiled and cited by Compute Atlas, with our own reporting appended. Archived links are used where the original has moved.

  1. 1.Data Center Frontier, Amazon plans major data center expansion in Spotsylvania County (Summit Crossing: 231 ac, 2.1M sq ft) · Data Center Frontier · retrieved July 17, 2026
  2. 2.The Fredericksburg Advance, Digital Insights: status of data centers in Spotsylvania (all four AWS campuses under construction, buildings going up) · The Fredericksburg Advance · retrieved July 17, 2026
  3. 3.Baxtel, Amazon Summit Crossing Tech Campus (231 ac, Phase 1 max 900k sq ft, rezoning approved Oct 2023) · Baxtel · retrieved July 17, 2026
  4. 4.HIFLD Electric Retail Service Territories (ORNL/DOE-CESER, 2023-08 vintage) · Oak Ridge National Laboratory (ORNL) / HIFLD · retrieved July 23, 2026

Is a data center disrupting your home?

Tell us what is happening. We will connect you with an independent attorney who handles data center cases in your state, free and with no obligation. These cases are commonly taken on contingency, so there are typically no upfront fees.

  • Free case review
  • Independent attorneys
  • No obligation

Attorney or law firm handling data center matters? Speak with us